HomeMy WebLinkAbout1988 02-26 CC ADJ MINBook 69/Page 123
J1 held 2/26/88
2(I
MINUTES OF THE FEBRUARY III, 1988 ADJOURNED MEETING
OF THE CITY COUNCIL OF THE CITY OF
NATIONAL CITY, CALIFORNIA
HELD FEBRUARY 26, 1988
The adjourned (workshop) meeting of the City Council was called to
order by Mayor Waters at 3:00 p.m. in the Main Conference Room of the
Civic Center.
ROLL CALL
Council members present: Cooper, Dalla, Pruitt, VanDeventer, Waters.
Administrative officials present: Bolint, Caloza, Campbell, Eiser,
McCabe.
Others present: Staff: Tom Deese, Terry Hart, NCPD; Randy Kimble,
NCFD; Arnold Peterson, CDC; Jim Ruiz, Park/Rec; Richard Schulman,
Personnel; Jerry Stafford, Engr; Curtis Williams, Pub Wks.
Public & Press: Warren Neilsen, Walter Popelar and others. Carol
Casteneda, San Diego Union; George McCrory, Star —News; Laura Preble,
Evening Tribune.
Mayor Waters announced the meeting was for the purpose of reviewing
the DEVELOPMENT ALTERNATIVES FOR THE POLICE FACILITY. He would ask
that Council hear first from City Staff, then from the Starboard
Corporation, the public and, finally, the City Council. The Mayor
turned the meeting over to City Manager McCabe
CITY STAFF
City Manager McCabe spoke briefly on the project to date, saying
Council met in workshop session ten days ago on alternative methods of
financing the police facility; today's meeting was on alternative
methods of development. Mr. McCabe said there were two alternatives
for consideration: the first, construction management or turnkey
approach and the other was the more traditional contracting approach.
Mr. McCabe said both staff and the Capital Improvement Committee
recommended the turnkey approach as the project costs are determined
in advance; whereas, in the traditional approach, the cost estimates
are determined following completion of appraisal and construction
documents; final costs upon receipt of bids or completion of property
acquisition. The City Manager turned the meeting over to Assistant
City Manager Bolint for a more detailed presentation of the two
approaches.
Assistant City Manager Bolint displayed "PROJECT DEVELOPMENT
BACKGROUND", explaining that on 9/15/87 Council
from the Starboard Development Corp. re general
finance the Police Facility, preferred site west
11/3/87 the bond measure failed; 11/10/87 Council
to the City Manager for study of financing and
2/16/88 Council met in Workshop and approved tax
concept. (See Exh. "A")
approved a proposal
obligation bond to
of Civic Center; on
referred the project
development; and on
increment financing
Mr. Bolint next displayed "THE CONSTRUCTION MANAGEMENT OR 'TURNKEY
APPROACH'", explaining that a development company assembles land and
builds for the City and then sells or leases the facility to the City;
the project budget and development/construction schedule are
established and guaranteed in advance. (See Exh. "B")
Mr. Bolint followed with a display "LAND ACQUISITION — 'TURNKEY'
(ILLUSTRATIVE PURPOSES ONLY)" and said, assuming the developer is able
to assemble land without need for eminent domain proceedings, starting
3/1/88 with purchase options, escrow might close 5/23/88 and tenants
relocated by 7/22/88. (See Exh. "C")
The next chart displayed was "PROJECT DEVELOPMENT — CONSTRUCTION
MANAGEMENT OR 'TURNKEY' APPROACH — TOTAL ESTIMATED TIMEFRAME: 17
MONTHS".
Mr. Bolint explained that if EIR was required, the schedule could be
impacted. (See Exh. "D")
Book 69/Page 124
held 2/26/88
Mr. Bolint next displayed "THE TRADITIONAL CONSTRUCTION CONTRACT
APPROACH" and said under this approach, the City would coordinate all
phases of land acquisition and project development from A/E and
appraisal work to bid preparation, issuance and review through project
construction and completion. (See Exh. "E")
Next Mr. Bolint displayed a chart "LAND ACQUISITION — TRADITIONAL
APPROACH (ILLUSTRATIVE PURPOSES ONLY) and said the schedule shown
assumes no extraordinary problems and shows possession of the
necessary land 10/88, under the illustrative example. (See Exh.
"F")
Finally, Mr. Bolint displayed "PROJECT DEVELOPMENT — TRADITION
CONTRACTING APPROACH — TOTAL ESTIMATED TIME FRAME 22 MONTHS" and
explained that the project might be impacted if an EIR was required or
if bids came in high or many change orders were necessary. (See Exh.
G")
STARBOARD DEVELOPMENT CORPORATION
Brad Saunders, President, and Ian Gill, Vice President, Starboard
Development Corp. were introduced.
Mr. Saunders reviewed their Revised Turnkey Proposal (Document No. 302-
03-01 on file in the office of the City Clerk); the revised project
total cost is $7,990,395.00,exclusive of finance cost, is an increase
of $318,935.00, an increase of less than 4%, made necessary by cost
escalations in material and labor since October 1987. Mr. Saunders
recommended Variable Rate Weekly Demand Certificates of Participation
for financing during the construction period although the City could
convert to a fixed rate any time subsequent to completion and delivery
of the facility. Mr. Saunders said all other development costs have
been held to the level negotiated previously. Mr. Saunders spoke of
other projects they have completed and are now engaged in.
PUBLIC
Warren Nielsen, 2108 Harrison, San Diego, inquired if consideration
was given to expanding the present police facility to the east.
No one else spoke.
CITY COUNCIL
Members of the City Council asked questions of Mr. Saunders and Mr.
Gill, including but not limited to: Was the thirty day plan check,
proposed under turnkey, realistic? (Dir. Bldg. & Safety Reid assured
all that it was possible.) Did Starboard have their own appraiser?
Would the cost of appraisal be included in the total? (Mr. Gill said
their costs would not change even if they had to go to eminent domain;
it might affect the time schedule but not the cost.) Would the City
have a coordinator on site? What was the cost to the City of a
coordinator at Kimball Towers? (Arnold Peterson, Exec. Dir.,
Community Development Commission answered.) What would the total
square footage of the project be? How could the turnkey developer
guarantee the cost? What if he ran into problems such as eminent
domain proceedings? Etc.
The City Council next discussed the Traditional Contracting
alternative and asked questions of staff, including but not limited
to: prevailing wage rates, Davis Bacon Act, coordinator present
during construction of Kimball Tower. Mayor Waters asked the City
Attorney to look at the development alternatives very closely.
Mayor Waters read into the record a letter from Kile Morgan stating
his opposition to development of the police facility without
competitive bidding. (See Exh.
"H")
The City Council discussed the need for staff to study the
alternatives further, to determine if the costs are within reason,
etc.; and give Council their input. Moved by VanDeventer, seconded by
Cooper, this be an agenda item for the City Council on March 15, 1988,
possibly a joint meeting with the Community Development Commission
(amended motion). Councilman Pruitt said he would also like to have a
report from Mr. Peterson.
Book 69/Page 125
AillINMES held 2/26/8
ADJOURNMENT
Moved by Cooper, seconded by VanDeventer, the meeting be adjourned to
4:00 p.m., Tuesday, March 1, 1988. Carried by unanimous vote. The
meeting closed at 4:35 p.m.
Approved at the regular meeting of March 1, 1988
Corrections No Corrections
yor
ALL CITY COUNCIL MEETINGS ARE TAPE RECORDED. YOU MAY LISTEN TO THE
TAPES AT THE CITY CLERK'S OFFICE OR THE NATIONAL CITY PUBLIC LIBRARY.
COPIES OF THE TAPES MAY BE PURCHASED FROM THE CITY CLERK.
4)- "A"
Book 69/Page 126
PROJECT DEVELOPMENT BACKGROUND
Date Action
• September 15, 1987 City Council approves proposal from
Starboard Development Corporation
regarding G.O. Bond revenue -funded
approach to Police Facility to be located
at designated preferred site directly
across the street from Civic Center.
• November 3, 1987 G.O. Bond measure does not receive
required 2/3 voter approval.
• November 10, 1987 Police Facility issue referred to the City
Manager to review alternative
approaches to financing and development.
• February 16, 1988 City Council holds Police Facility
financing workshop and approves tax
increment financing concept. Sets
development alternatives workshop for
February 26, 1988 at 3:00 p.m.
Book 69/Page 127
THE CONSTRUCTION MANAGEMENT
OR
"TURNKEY" APPROACH
Defined: A development company assembles land and builds for the City, a new
Police facility and then sells or leases the facility to the City. The
project budget and development/construction schedule are established
and guaranteed in advance.
Features:
• Maximum project cost on a "not to exceed" basis established at
beginning of project. Any savings revert to the City, overruns to
be absorbed by developer. Maximum cost serves as insurance
aganst project cost fluctuations.
• Generally no advance appropriations required (e.g., Architectural
and Engineering A/E work). Funding comes from long term
financing revenues.
• Developer, rather than City, responsible for construction
management and coordination. Developer's fee for project
management incorporated into maximum project cost.
• Project "fast tracking" results in shorter time frame for completion
- estimate of approximately 5 months shorter time frame than
traditional approach.
• Project can proceed prior to completion of final bid documents due
to bid package process and guaranteed maximum project price.
• A/E work is accomplished at lower cost since vendors do certain
design work in developing bid package responses. Under more
traditional approach, project A/E does all design work.
• Programming incorporated to meet City needs at the desired cost
by early value engineering.
Potential
Timeframe: (See PERT Chart)
rJ
LAND ACQUISITION - "TURNKEY"
(ILLUSTRATIVE PURPOSES ONLY)
PERT Chart
02-23-88 09:S7
r001
PURCHASE OPTIONS
23
03-01-88<03-23-88
-.002
ESCROW
60
03-24-88<05-22-88
-JICLOSE ESCROW
105-23-88<05-23-88
RELOCATE TENANTS
61
05-23-88<07-22-88
NOTES:
1. Assumes developer able to assemble land without need
for condemnation proceedings.
PERT Cf•rt
02-27-00 12117
10
MECN.PERF.SPEC.
30
0]-01-00<03-]0-00
IT
ELEC.PCRF.SPEC.
30
03-01-00<03-70-06
r1
SCNEMRiIC DESIGN
70
0]-01-60<03-]0-O0
PROJECT DEVELOPMENT
CONSTRUCTION MANAGEMENT OR "TURNKEY" APPROACH
TOTAL ESTIMATED TIMEFRAME — 1 YEAR, 5 MONTHS (17 MONTHS)
(ILLUSTRATIVE PURPOSES ONLY)
11
BID PAC. •110
MECNRNICRL 15
04-01-60<04-15-00
12
BIO PAC. ••B•
- PLUMBING 5
04-01-00<04-05-00
13
BID PAC. ••C^
FIRE SPA. 15
04-01-00<04- 15-00
10
•ID PRC. "0"ELECTRICAL 1S
04-01-09<04-15-90
02
DCSION DEVELOP
•
--I VALUE ENGINEER
29
04-16-00<05-14-00
16
fl'ECH.CONST.DOCS.
67
S-16-BB<07-1i-0R
IS 19
AWARD BID ►RCS. 1., ►LURB.CONST.DOCS
•••• R.B.C.D. O 1••-• 60
05-16-00<0S-15-00J 05-16-60<07-14-00
04-01-00<04-30-00
•
25
••• I EKTER.FIN 14
•••-••- 05-01-00<0S-14-00
STRUCT. STEEL. DOC
59
04-01-60<05-29-00
rF29
F9[ OCSION DEW.
29
05-01-00<05-29-00
OB26
ID.►RC. •F••
GLASS • OL 1A
05-01-00t05-14-OB
SOS
BID PAC "0""0"•-
• STRUCT.STL 15
06-]O-0O<06-17-00
]O
FF•E CONET.DOCS.
91
05-30-00<00-20-00
•••
•••- Il0LZ
PLAN CHECK BLDG.
PERMIT
••--- IFIRE SP.CONST.00
60
- 0S-16-60<0T-14-00
21
ELEC.CONST.DOC
60
05-16-00<07-14-00
2T
VALUE ENGINEER
--- 30
05-15-00<06-13-06
06
RMRRD •ID PAC.
O •' 0
06-14-00<06-14-66
71
•ID.PRC. ••J••
FF•E 72
00-29-00<09-29-00
NOTES:
1. Environmental review could
were required. If negative
2. Land acquisition timeframe
• --•• <LINK> •••• <Cr1t1c•1 'Ink, r1 <T•ok> T11 <Crltic•1 took)
00-25-00<09-26-00
••- •
• ]5
• BID PAC. •'I•'
00 SITEWORK 20
• Ob-09-00<OB-2b-•B
•
009
nncn.c0NS1. DOGS.
120
OS-01-00<06-20-00
26
RMRRD BID PRCS.
-•- E 6 F 0
06-14-00<06-14-66
-•-I BID PRC ••N••
22
00-29-00<09-19-00
rALVALUE ENGINEER
10
9-20-00<09-29-06
11°
21
SI TEWORK
70
09-26-00<10-25-00
24
BUILOINO CONST.
••••• 270
10-26-00<0T-70-09
-- - - ...00056 11 YARD BID IRE I -- -- •-- --
--
SITEUORKO
OW-2tl-06 0tl 00-28-00
09
[fIAWARD BID PAC H
0
09-30-00<09-70-66
.d72 75
AWARD BID PAC.
110
09-30-06<09-90-06 1-26-09
'ORDER FF•E
I10-01-00<O
.907
ORDER STEEL
90
06-15-00<09-12-00
impact schedule in the event EIR
declaration, impact minimal.
on separate chart.
•
•
•
•
•
•
•
DELIVER 'FOE
]2
06-05-09<07-04-09
6ZI a'Bud/69 )100g
Book 69/Page 130
THE TRADITIONAL
CONSTRUCTION CONTRACT APPROACH
Defined: The City coordinates all phases of land acquisition and project
development from A/E and appraisal work to bid preparation,
issuance and review through project construction and completion.
Features:
• City staff responsible for overall project coordination through a
contract construction manager.
• Final project construction cost could be lower or higher than
Engineer's estimate which is developed by A/E. Final project
construction cost unknown until bids received.
• Advance City appropriations required due to the fact that long
term financing (issue sizing) would not commence until project
cost determined.
1) A/E Work - cost estimate is $350,000-$400,000 for
remaining work through preparation of bid documents.
(Cost dependent upon size and characteristics of
proposed facility.)
2) Property Appraisal - cost estimate is $20,000-$25,000.
3) Acquisition/Relocation Assistance - cost estimate
is $30,000-$35,000.
4) Furniture, Furnishings and Equipment Design - cost
estimate is $10,000-$15,000.
• Longer project development and construction schedule than under
turnkey approach - estimate of approximately 5 months longer
time frame than under turnkey approach.
• No developer's fee per se. City should retain project
construction manager - cost estimate is approximately $400,000
which consists of inspection services, site supervision, value
engineering, clerical support and testing services.
Potential
Timeframe: (See PERT Chart)
PERT Chart
02-23-00 10:40
13 01
RFP-ACOUI SI TION
RELOCATION 50
03-01-0e>05-30-0e
rO3
RFP
I SAL
70
03-01-00 05-30-00
,OD2
AWARD CONTRACT
•
1
oa-os-ee<o.-os-se
04
AWARD CONTRACT
• 1
04-05-ee<04-05-0e
LAND ACQUISITION
TRADITIONAL APPROACH
(ILLUSTRATIVE PURPOSES ONLY)
OS 06
ISAL PURCHASE OFFERS
• 31 •24
04-06-ee<05-06-00 05-07-00<0S-50-00
SO
NECESSITY NOTICE
11
05-71-00<06-10-0e
• 07
ESCROW
61
05-71-9e<07-50-00
11
COUNCIL HEARING
• 1
06-21-09<06-21-e0
O6
CLOSE ESCROW
1
07-31-se<07-n1-ee
i12
EMINENT DOMAIN
• FILE•SERVE 30
06-22-88<07-21-00
15
RELOCATION
62
06-22-00<00-22-00
09
RELOCATION
61
00-01-00<09-50-e0
16
POSSESSION L
0
10-OI-BB 10-01-se r
14 15
ORDER POSSESSIONfluI
•• On • 0
07-22-ee<o7-22-BB 10-20-00 10-20-00
NOTES:
1. This schedule assumes no extraordinary problems.
(e.g. inability to locate owners, etc.)
• a"• <Link> •••• <Critic.I link> r1 <T.sk> R'av <Critical t.sk>
i£i a$ed/69 xoog
PROJECT DEVELOPMENT
TRADITIONAL CONTRACTING APPROr=�CH<
TOTAL ESTIMATED TIMEFRAME — 1 YEAR, 10 MONTHS (22 MONTHS)
PERT Chart ( ILLUSTRATIVE PURPOSES ONLY)
02-27-00 17:17
i° 01--
SCHEMATIC DESIGN
70
07-01-00<07-70-00
02
DESION DEVELOP
• 70
04-01-00<04-70-00
•
.009
CONTRUCTION DOC.
120
05-01-00<00-20-08
04
BUILDING PERMIT
PLAN CHECK 72
00-29-00<09-29-00
,y005
IIBI ODI NO
• 71
00-29-00<09-20-00
F0
FFOE DESIGN DEV.
31
00-29-00<09-20-00
•
-.006
VALUE ENGINEER
29
09-29-00<10-27-00
09
FFOE CONST_ DOCS
O7
09-29-00<12-24-00
•
*007
i
CONSTRUCTION
760
10-20-00<10-70-09
10
FFOE BID
70
12-25-00<01-25-09
•
.011
F FOE DEL INSTALL
60
11-01-09<12-70-89
NOTES:
1 Environmenta1 review could impact schedule in the event EIR
were required_ If negative declaration, impact minimal.
2. Land acquisition timeframe on separate chart_
3, SCHEDULE COULD BE AFFECTED IF BIDS COME IN HIGH OR MANY CHANGE ORDERS ARE REQUIRED,
<L1 nK> ON, <Cri tl cal l i nk> r—, <T.sk> m.-n <Cri t1 cal task>
ZET a2sd/69 )100R
Exhibit "H"
Book 69/Page 133
KILE MORGAN
1223 "J" Avenue
National City, CA 92050
February 25, 1988
City of National City
Vice Mayor Dalla, Michael R.
1243 National City Blvd.
National City, CA 92050
Dear Vice Mayor Dalla:
I have read the recent newspaper articles on the recommended method
of financing the proposed National City police facility. I am very
much opposed to financing the new police facility through the re-
developing agency since this is the only agency left to keep
progress going in the city of National City.
If this does not change your mind, I am absolutely opposed to
building the police facility for an estimated $8 million dollars
without competitive bids. The city built Kimbell Tower for $8
million dollars, Morgan Tower for $5 million dollars, the City
Hall, $5 million dollars of sewer work, $30 million dollars of
drainage and streets, four community buildings, and all other city
projects based on competitive bidding. It does not build
confidence in government to do otherwise.
The 55,000 people in National City have the right to know that they
are receiving a fair price for anything being built with city
funds. I believe it will be an injustice to the city and its
people if the police facility is built without competitive bidding.
Sincerely,
Kile Morgan