HomeMy WebLinkAboutCC RESO 15,867RESOLUTION NO. 15,867
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL
CITY APPROVING THE 1989 FIVE-YEAR REGIONAL TRANSPORTATION
IMPROVEMENT PROGRAM FOR THE CITY OF NATIONAL CITY
WHEREAS, each year all local agencies within the County
of San Diego are required to submit to SANDAG their lists of
proposed major street and road projects; and
WHEREAS, each local agency's list must include those
projects which are funded using Federal, State, and local
(Proposition A) funds, and must specify those projects which are
projected for the next five years; and
WHEREAS, the lists of projects will eventually become
part of the Regional Transportation Improvement Program (RTIP),
and only projects which are listed will qualify for funding; and
WHEREAS, the City Engineer has prepared a proposed list
of major street projects to be completed within the City.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of National City that the list of major street projects
submitted by the City Engineer as the City's 1989 five-year
Regional Transportation Improvment Program (RTIP), attached
hereto as Exhibit "A", is hereby approved.
PASSED and ADOPTED this 7th day of February, 1989.
GEORGE H. WATERS, MAYOR
ATTEST:
(LN.AA-t 17/41-10Z41,.)
LO., ANNE PEOPLES, UITY CLERK
APPROVE, AS TO E21RM:
GEORGE H. EISER, III -CITY ATTORNEY
£xhrib;-1- `»
City of National City
Office of the City Engineer
1243 National City Boulevard, National City, California 92050-4397
(619) 336-4380
January 17, 1989
To: Gerald Bolint, C.I.P. Chairman.
From: Burton S. Myers, City Engineer
Subject: 1989 Five Year RTIP - Project ,.. 'ttals
Proposition A - Local Streets and Road Projects
Each year all of the Local Agencies within the County of San Diego are
required to submit to SANDAG their list of proposed major street and road
projects. This list must include those projects which are funded using
Federal, State and Local Funds (Proposition A).
The list must specify those projects which are projected for the next five
years. The list is not binding, and can be revised once each year. The
list of projects will eventually become part of the Regional RTIP. Only
projects which are listed on the RTIP qualify for funding, in other words
if the project is not listed on the RTIP, it would have to wait until the
next add on, or change period (once a year) before it could the constructed.
I have reviewed last years project list, and find that the list was
generated based upon floating a bond issue for the Proposition A projects.
In other words, the list was front end loaded, and there are insufficient
funds available to complete the proposed projects.
The existing Proposition "A" project Funding list is as follows:
Estimated Estimated
F.Y. Available Funds Projects Project Costs
88-89 680,000
$680,000
89-90 $720,000
$720,000
Euclid Avenue 20-22 (Design and
right-of-way $850,000
"N" Avenue 8th - Plaza (Const.) 380,000
Euclid Avenue 20-22 (Const.)
Pavement Management
Division St. -Palm to Euclid
(Design and R/W)
Hoover Avenue Concrete Box
(Design)
$1,230,000
$700,000
60,000
440,000
25,000
$1,225,000
Page 1 of 3
Estimated Estimated
F.Y. Available Funds Projects Project Costs
90-91 $788,000
$788,000
$2,188,000
Hoover Avenue Concrete Box
(Const.)
Division St. -Palm to Euclid
(Const.)
Pavement Maintenance
Grand Total - 3 years
$450,000
800,000
1,200,000
$2,450,000
$4,905,000
Based upon this list the available funding for the initial 6 years would be
spent during the first 3 years, and no additional construction would be
done during the following 3 years.
I would recommend a pay as you go program with the estimated available
funding equaling the yearly estimated project costs. The pay as you go,
program would spread the work out more evenly constructing some projects
each year, and save the expensive costs involved with bonding, thus
allowing these funds to be spent on the projects instead of increasing the
overhead costs. For the Proposition "A" portion of the funding budget, I
am recommending the following spread.
F.Y.
Estimated
Available Funds Projects Project Costs
Estimated
89-90 $400,000 Euclid Avenue 20-22 (Design & R/W) $400,000
(Carry over
funding from
FY 88-89)
$720,000
$1,120,000
90-91 $788,000
$788,000
91-92 $857,000
$857,000
92-93 $922,000
93-94 $989,000
Euclid Avenue 20-22 (Const.)
$720,000
$1,120,000
"N" Avenue 8th-Plaza (Design-R/W)
Hoover Avenue concrete Box (Design)
Pavement Maintenance
Division St. -Palm to Euclid -Phase II
(R /TAT and Const.)
"N" Avenue 8th-Plaza (Const)
Hoover Avenue concrete Box (Const.)
Pavement Maintenance
Division St. S.R. 5 to Palm -Phase II
Pavement Maintenace
Division St. S.R. 5 to Palm -Phase III
Pavement Maintenance
$ 20,000
25,000
420,000
323,000
$788,000
$380,000
$450,000
27,000
$857,000
$500,000
422,000
$922,000
$600,000
389,000
$989,000
Page 2 of 3
I am recommending that the FAU Funding be expended in the following manner.
Estimated
F.Y. Available Funds
89-90
90-91 $70,000
91-92 $116,500
92-93 $116,500
93-94 $116,500
I am recommending that
following manner:
Estimated
F.Y. Available Funds
89-90 $680,000
(Includes carry
over funding)
90-91 $250,000
91-92 $500,000
(Includes carry
over funding)
92-93 $250,000
93-94 $500,000
Projects
Transfer the funding to FY 91-92
Pavement Maintenance
Transfer the funding to FY 91-92
Pavement Maintenance
the Route 252 mitigation funding
Projects
Division St. -Palm to Euclid
( R/W and Contt) Phase I
be
Carry over Funding to FY 91-92)
Estimated
Project Costs
$186 , 500
$233,000
expended in the
Estimated
Project Costs
$ 680,000
Division St.-S.R. 5 to Palm
(Phase I) $ 500,000
Carry over funding to FY 93-94
Division St. S.R. 5 to Palm $500,000
(Phase II)
The last major project to be considered on this list is the La Paleta Crecy
Bridges. The majority of this project will be funded using a special State
Grant ($704,000.00). The Cities share is $176,000.
The design portion of the project is scheduled for FY 88-89 while the
construction phase is scheduled for FY 89-90.
As a reminder, the first two years of the 5 year program are the most
critical, those projects which are in the projected area (last 3-years) are
space holders, in other words as the 5 year program is updated each year,
there is a good chance that the project list will be changed or mdified.
The projected 5 year program contains only those projects funded by Prop.
"A" funds, FAU funds, 252 mitigation funds, and special Caltrans Grants.
The other C.I.P. funds which include General Funds, General Capital Outlay
Funds, Gas Taxes, C.D.B.G., and Sewer Service Funds need to be reviewed
and allocated during the normal budget process.
B'I: tcg
Page 3 of 3
TABLE 1
Agency: City of National City
RTIP/PROPOSITION A • PROJECT INFORMATION FORM
Prepared By: Burton S. Myers
Date: 1-17-89 ftme: (619) 336-4380
Agency
Priority
1.
2.
3.
4.
5.
6.
7.
8.
Project Description & Convents
(Location & Type of Work)
Miles
Work
Phase
Escalated Project Cost (S000,$)
TOTAL
Federal
State
Prop.A
Loral
Private
Fiscal
Tear
Euclid Avenue - 20th to 22nd
Streets construct a new 4-lane
Road.
Division Street - Palm to Euclid
Phase I - Widening and Construct
4-lane road.
La Paleta Creek Bridges
Division Street Palm to Euclid
Phase II
"N" Avenue-8th Street to Plaza
Construct a new 4-lane road
Hoover Avenue concrete box (bridge)
Division Street S.R. #5 to Palm
Avenue Phase I
Division Street - S.R.#5 to Palm
Avenue Phase II .:
0.1 T 1,120
R 100
0.6 C . 580
-0- C 880
0-.6 R 50
C 273
0.2 E 20
C 380
-0- E 25
C 450
1.1 E 50
C 450
1.1 C 500
176
1,120
50
273
20
380
25
450
500
100
580
50
450
704
90
90
90
90
91
91
91
92
91
92
92
92
93
Work Phase: E [Engineering & Planning); R [Right -of -Way]; C (Construction]; T (Total].
Federal Funds: Federal Aid Urban [FAUI; Federal Aid Secondary (FASI Federal Bridge Replacement (BR].
TABLE 1
RTIP/PROPOSITION A - PROJECT INFORMATION FORM
Agency: City of National City prepared By: Burton S. Myers Date: 1/17/89 Phone: (619) 136-4180
Agency
Priority
Project Description & Comments
(Location & Type of Work)
9. Division Street - S.R.#5 to Palm
Avenue - Phase III
10.
Pavement Maintenace - City
Wide - Various Streets
Niles
N/A
Work
Phase
C
T
T
T
Escalated Project Cost (5000's)
TOTAL
1,100
Federal
FAU
420
422
213.1 186.5
622 i 233
State
Gas Tax
Prop.A
600
420
422
27
389
Fiscal
Local 1 Private ( Year
252-Mit ¢tate Grai%t
500 94
91
93
92
94
7,655.1 419.5
176
4,676
1,680
704
Work Phase: E [Engineering & Planning]; R [Right -of -Way]; C [Construction]; T (Total].
Federal Funds: Federal Aid Urban [FAU]; Federal Aid Secondary [FAS] Federal Bridge Replacement [BR).