HomeMy WebLinkAboutCC RESO 15,637RESOLUTION NO. 15,637
RESOLUTION DECLARING E & J WEED ABATEMENT CO. THE LOWEST
RESPONSIBLE BIDDER AND AUTHORIZING THE CITY MANAGER TO
EXECUTE AN AGREEMENT WITH E & J WEED ABATEMENT CO.
WHEREAS, the Fire Marshal of the City of National City did
on May 31, 1988, publicly open, and examine and declare all
sealed proposals or bids for Weed Abatement and Rubbish Removal
in National City.
NOW, THEREFORE, IT IS HEREBY RESOLVED that the City Council
of the City of National City hereby rejects all of said bids
except that herein mentioned, and hereby awards the contract for
Weed Abatement and Rubbish Removal in National City to the lowest
responsible bidder, to wit:
E & J WEED ABATEMENT CO.
BE IT FURTHER RESOLVED by the City Council of the City of
National City, California, that the City Manager is hereby
authorized to execute on behalf of the City, a contract between E
& J Weed Abatement Co. and the City of National City to provide
for Weed Abatement and Rubbish Removal in National City.
PASSED AND ADOPTED this 14th day of June, 1988.
ATTEST:
George W ters, Mayor
IONE CAMPBELL
Ione Ca bell, Clty Clerk
BY: JCL)
( �� A1'tont
George H. Eiser, III - City Attorney
B I D
for
WEED ABATEMENT & RUBBISH REMOVAL
in the
CITY OF NATIONAL CITY
Bids must be received (either mailed to or
delivered to) the MAIN FIRE STATION,
333 E. 16th Street, National City,
California 92050 by 2:00 P.M. on
MAY 31, 1988 where they will
be publicly opened and
read aloud.
NOTICE INVITING SEALED BIDS
Sealed bids will be received at the National City Fire
Department, Attn.: Fire Marshal, 333 E. 16th Street,
National City, CA 92050, until 2:00 P.M. on May 31, 1988,
at which time they will be publicly opened and read aloud.
They shall be submitted in sealed envelopes marked on the
outside with the project title:
WEED ABATEMENT AND RUBBISH REMOVAL SERVICES
PROJECT DESCRIPTION
Work under this contract will include hand -cutting or
machine -cutting of weeds to a height of two (2) inches,
removing debris so generated and hauling it to an
appropriate landfill; and removal of rubbish either by hand
or by equipment, loading it and hauling it to an appropriate
landfill. The work may be accomplished primarily on private
property, but some may be on public property. It is the
intent of the City to assign all weed abatement and rubbish
cleanup required to be done on private property to this
Contractor.
Bids are required for the entire work described herein.
The City reserves the right, after opening bids, to reject
any or all bids, or to make award to the lowest responsible
bidder and reject all other bids, to waive any informality
in the bidding and to accept any bid or portion thereof.
Bids will be compared on the basis of the Contractor's
estimate of the quantities of the several items of work as
shown on the Bid Schedule.
Date: ~
(r-- I �- �=-re5
Patricia Schiff, Fireshal
SCOPE OF CONTRACT:
Work under this contract will include hand -cutting or
machine -cutting of weeds to a height of two inches, removing
debris so generated and hauling it to an appropriate land-
fill; and removal of rubbish either by hand or by equipment,
loading it and hauling it to an appropriate landfill. The
work will be accomplished primarily on private property, but
some may be on public property. It is the intent of the
City to assign all weed abatement and rubbish cleanup
required to be done on private property to this Contractor.
TERM OF CONTRACT:
The term of this contract will be for ONE YEAR, renewable
for one additional year at the option of the City.
Specification
A. Indemnification and Insurance - Contractor agrees to
indemnify, defend, and hold harmless, at its own risk,
cost and expense, the City, its officers, agents and
employees from and against any and all liability or
loss, including defense costs, arising from
Contractor's performance under the terms of this
agreement.
Contractor, at its sole cost and expense, shall
purchase and maintain throughout the term of this
agreement, the following insurance policies:
1. Automobile insurance covering all bodily injury
and property damage liability incurred during the
performance of this agreement, with a minimum
coverage of $500,000 combined single limit per
accident. Such automobile insurance shall include
non -owned vehicles.
2. Comprehensive general liability insurance, with
minimum limits of $500,000 combined single limit
per occurrence, covering all bodily injury and
property damage arising out of Contractor's
operation under this agreement.
3. Workers' compensation insurance covering all of
its employees and volunteers.
4. The aforesaid policies, except for the workers'
compensation policy, shall name City and its
officers, agents, and employees as additional
insured, and shall constitute primary insurance as
2
to City, its officers, agents and employees, so
that any other policies held by City shall not
contribute to any loss under said insurance. Said
policies shall provide for thirty (30) days prior
written notice to City of cancellation or material
change.
If any required insurance coverage is provided on a
"claims made" rather than "occurrence" form, Contractor
shall maintain such insurance coverage for three years
after expiration of the term (and any extensions) of
this agreement.
If Contractor does not keep all of such insurance
policies in full force and effect at all times during
the term of this agreement, City may elect to treat the
failure to maintain the requisite insurance as a breach
of the contract and terminate the agreement.
B. A BUSINESS LICENSE from the City of National City will
also be required.
C. Wherever practical, mowing is the preferred method of
weed abatement. Areas designated will be completely
mowed including easements, setbacks and parkways, to a
length of two inches maximum. "Scalping" of the ground
is to be avoided. Mechanized mowing should be used
where areas and contours permit. Some hand -mowing will
be required in these areas. Other areas, because of
their size or contour or other conditions, will require
hand -mowing. All debris generated by mowing and all
litter is to be removed, and the premises, including
streets and sidewalks, left in clean condition. Debris
and litter so generated will be hauled to an
appropriate landfill in suitable containers or
equipment.
D. Where the primary work is rubbish removal, all rubbish
designated by the City is to be removed from the
premises and hauled to an appropriate landfill in
suitable equipment or containers. It should be noted
that while the bid quantity is truckloads (5 cu. yds.)
as a method to estimate the quantity of material to be
moved, the Contractor may use any legal method of
hauling. NO SCAVENGING OF RUBBISH WILL BE PERMITTED.
Payment for rubbish removal will include leaving the
premises, including streets and sidewalks, in clean
condition.
3
E. Field work shall not start before 7:30 A.M. Work may
be accomplished on Saturday and Sunday only by
arrangement with the City and by payment to the City of
sufficient funds to offset compensation to inspection
personnel at overtime rates. Appropriate safety
equipment shall be available and used at all times.
WORK AUTHORIZATION
For each parcel to be mowed, a square footage figure will be
provided by the City. Upon agreement between the City and
the Contractor as to the application of bid amounts and as
to the total cost of abatement of the parcel, authorization
will be given to accomplish. "Before" and "after" photos
will be taken by the Contractor. Photos are also required
anytime the work site is vacated for more than four hours.
All such photos will be required to be submitted with
payment requests as a precedent to payment. Each work
authorization will contain a parcel number (or numbers), a
square footage, an agreed price based upon bid amounts, a
work authorization number, a start date and a latest
completion date, an actual completion date, and an area for
"REMARKS." Upon satisfactory completion, the city inspector
will sign off on each authorization.
For each parcel to have rubbish removed, an on -site joint
visit will be made by the Contractor and by a representative
of the City. Upon agreement between the Contractor and the
City as to the application of bid amounts, a Work
Authorization will be given to accomplish. "Before" and
"after" photos will be taken by the Contractor. Photos are
also required anytime the work site is vacated for more than
four hours. All such photos will be required to be
submitted with payment requests as a precedent to payment.
Each work authorization will contain similar information as
the weed abatement authorization. Upon satisfactory
completion, the city inspector will sign off on each
authorization.
TIME FOR ACCOMPLISHMENT
The Contractor must respond within three working days to the
city telephone call to schedule a joint on -site meeting.
The Contractor must complete the abatement work within 15
working days of receipt of work authorization for any
specific parcel.
4
COMPLAINTS AND DEFECTIVE WORK
All work which is determined by the inspector to be
defective or deficient in any of the requirements of the
specifications shall be remedied by the Contractor at his
expense in a manner acceptable to the city inspector.
The Contractor will be responsible for promptly answering
inquiries and complaints of the city inspector or private
property owners or citizens relative to any work, charges,
damage or any other questions that may arise as a result of
weed abatement operations by the Contractor.
The Contractor will promptly notify the city inspector of
any damage to private or public property as a result of weed
abatement operations.
PUBLIC HEARING
Citizens who object to payment of the amounts assessed by
the City for weed abatement or rubbish hauling, for any
reason, are entitled to a public hearing before the City
Council. The Contractor will be required to be present at
this public hearing to address any questions pertaining to
his work.
PAYMENT
Payment will be made by the City upon receipt of billing (at
a time convenient to the Contractor but not more often than
twice monthly). Billing will consist of a bill citing each
parcel, the work authorization number, the date work
satisfactorily completed, and the amount owing for each
parcel and the total amount owed. The work authorizations
(or copies) will accompany the bill and will serve as backup
for the bill, as will the "after" photos taken by the
Contractor, and the dump receipts.
HOW TO BID
Scope
Prior year activity in this effort involved thirty-seven
(37) separate parcels.
Although no guarantee can be given as to the amount of work
to be accomplished under this contract, the City will use
the following figures in comparing the total price of any
bid.
5
130,000 sq. ft. MOWING
20 5-CY TRUCKLOADS RUBBISH
75 MAN DAYS "OTHER"
It is repeated that the above quantities are for bid evalua-
tion purposes only, and for no other purpose.
Weed Abatement
Hand -Mowing - This is to be bid on a dollars -per -square -foot
basis. The work includes machine -mowing or hand -mowing of
the parcel including easements, setbacks and parkways,
loading, hauling and cleanup. The price given will include
all contractor cost elements including but not limited to
overhead, insurance, profit, direct labor, supervision,
equipment operation and amortization. A minimum
authorization square footage is established at 500 sq. ft.
If a parcel is smaller than 500 sq. ft., it is to be billed
and paid for as 500 sq. ft. If larger, it will be billed
and paid for at the actual square footage as agreed.
DUMPING FEES ARE REIMBURSABLE. VALID DUMP RECEIPTS TO BE
SUBMITTED, WITH BILLINGS, FOR SPECIFIC WORK AUTHORIZATION.
Rubbish Removal
This is to be bid on a 5-yard TRUCKLOAD basis. The number
of truckloads of rubbish will be jointly estimated by the
Contractor and by the City. The work will consist of
loading, hauling and site cleanup. The price given to
include all contractor elements of cost as cited above.
DUMPING FEES ARE REIMBURSABLE. VALID DUMP RECEIPTS TO BE
SUBMITTED, WITH BILLINGS, FOR SPECIFIC WORK AUTHORIZATION.
NO SALVAGE OF REMOVED MATERIALS WILL BE PERMITTED, AND ALL
MATERIALS WILL GO TO THE LANDFILL. A minimum authorization
yardage is established at one (1) 5-cu.yd. TRUCKLOAD. If
the amount of rubbish to be removed from a parcel (or
contiguous group of parcels) is less than one truckload it
is to be billed and paid for as one 5-cu.yd. TRUCKLOAD. If
more truckloads are required, it will be billed at the
actual number of truckloads. Unusually difficult access or
heavy or unwieldy materials will cause adjustment to the bid
price as below and mutually agreeable; or if agreement
cannot be reached, as directed by the city inspector.
Other:
This to be bid on a dollars -per -man -day basis. The work
will include any adjustments to bid prices on account of
unusually difficult access, very heavy or extremely unwieldy
materials or other very unusual conditions. This item will
6
not be used under normal or predictable circumstances and
preferably will not be used on the contract. Its purpose is
to relieve the Contractor of the need to increase his bid
price to cover any and every extraordinary condition
imaginable. The price should include all contractor
elements of cost as cited above.
7
B I D
MOWING, including raking,
loading & hauling and
cleanup.
(DUMPING FEES ARE
REIMBURSABLE)
RUBBISH REMOVAL,
including loading,
hauling and cleanup
(DUMPING FEES ARE
REIMBURSABLE)
OTHER, for price
adjustment for difficult
access or difficult work
as described
$ .069 PER SQUARE FOOT
$ (257 °5 PER TRUCKLOAD
(5 CU. YD.)
$ //a . B; PER MAN DAY
The undersigned hereby agrees to accomplish
the work described above under the conditions
described above for the price as bid above.
(This document must be signed by an officer
of the Company to be a conforming bid.)
Name
Company Name
(0--1 as
Date
*************************************************************
The above bid is accepted as the low
conforming bid and the work is
hereby awarded to
orized Signature
g ryl°
osition
CITY OF NATIONAL CITY
Date
Date
WEED ABATEMENT/RUBBISH REMOVAL AUTHORIZATION
PROPERTY ADDRESS
JOB/FILE NUMBER
PARCEL #
OWNER'S NAME
OWNER'S ADDRESS
DATE NOTICE SENT
**************************************************************
ESTIMATED COST;
(A) Sq. Ft. MOWING @ =
(B) 5 Yd. TRUCKLOADS RUBBISH @ =
(C) Days OTHER @ =
(D) ESTIMATED COST (A+B+C) _
Date "BEFORE" Pictures by
Date "AFTER" Pictures by
Date WORK STARTED
Date WORK COMPLETED
**************************************************************
(E) Dump receipts attached, total $
TOTAL PAYMENT REQUESTED $
(Line D + Line E)
APPROVED FOR PAYMENT
City Inspector
**************************************************************
REMARKS: