RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
APPROVING A SUBCONTRACTOR SUBSTITUTION FOR THE CONSTRUCTION
OF NATIONAL CITY BOULEVARD BRIDGE, SPECS. NO 92-15,
FEDERAL PROJECT NO. 5066(004), BRIDGE NO. 57C-122
WHEREAS, Shasta Constructors, Inc., the prime contractor for the construction of the
National City Boulevard Bridge, has requested authorization to substitute itself and perform
pile driving services in lieu of its previously designated subcontractor, Intra American and
Drilling Co., which has failed and refused to perform its subcontract; and
WHEREAS, the City has provided notice to the subcontractor of the prime
contractor's request to substitute, and the City Council has conducted a hearing on said request
at which oral and documentary evidence was received.
NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City of
National City finds that Intra American and Drilling Co. has failed and refuses to perform its
subcontract, and such substitution is in the best interests of the public and will thereby
minimize further delay.
BE IT FURTHER RESOLVED that the City Council hereby approves the substitution
of Shasta Constructors, Inc., prime contractor, for the performance of Intra American and
Drilling Company, Inc., subcontractor, for pile driving services on the construction of the
National City Boulevard Bridge, Specs No. 92-15, Federal Project No. 5066(004), Bridge No.
57C-122.
PASSED and ADOPTED this 20th day of October, 1998.