HomeMy WebLinkAboutCC RESO 2003 - 118RESOLUTION NO. 2003 —118
RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF NATIONAL CITY
AUTHORIZING THE CLOSURE OF THE
SWEETWATER CHANNEL LEVEE BIKE PATH
WHEREAS, the California Department of Transportation is constructing a section
of the Bay Shore Bikeway, Class I bike path along Interstate 5, between F Street in the
City of Chula Vista and 24th Street in the City of National City, which requires the
temporary closure of the existing bake path and rerouting of bicycle and pedestrian
traffic for approximately six (6) months, beginning September 15, 2003, and ending no
later than March 15, 2004, in order to construct a temporary falsework structure; and
WHEREAS, the falsework structure will be assembled atop the existing Class 1
bike path that runs along the north levee of the Sweetwater River Flood Control
Channel, and would provide insufficient vertical and horizontal clearance, creating
unsafe conditions for bike path users.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby authorizes the closure of the Sweetwater Channel Levee bike path
during the construction of a temporary falsework structure by the California Department
of Transportation, beginning September 15, 2003, and ending no later than March 15,
2004.
PASSED and ADOPTED this 19th day of August, 2003.