HomeMy WebLinkAboutCC RESO 2004 - 226RESOLUTION NO. 2004 — 226
RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF NATIONAL CITY
AUTHORIZING THE CITY ENGINEER TO EXECUTE
CHANGE ORDER NO. 11 WITH MARCOTTE & HEARNES BUILDERS, INC.
IN THE "NOT TO EXCEED" AMOUNT OF $68,679 TO RELOCATE THE
ULTRAVIOLET WATER TREATMENT/PUMP ASSEMBLY UNDERGROUND VAULT
FOR THE FIRE STATION CONSTRUCTION PROJECT
AS REQUESTED BY THE FIRE DEPARTMENT
WHEREAS, the contract for the Fire Department Construction Project was
awarded to Marcotte & Hearnes Builders, Inc. on February 17, 2004, by the adoption of
Resolution No. 2004-31; and
WHEREAS, upon visiting the site, Fire Department personnel found that
the location of the ultraviolet water treatment/pump assembly underground vault would
limit their ability to place equipment around the training tower, and thereby limit their
ability to train.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City
of National City hereby authorizes the City Engineer to execute Change Order No. 11
with Marcotte & Hearnes Builders, Inc. in the not to exceed amount of $68,679 for the
relocation of the ultraviolet water treatment/pump assembly underground vault for the
Fire Station Construction Project.
PASSED and ADOPTED this 7th day of December, 2004.
Nick Inzunza, Mayor
ATTEST:
Michael R. Dalla, ity Clerk
APPROVED AS TO FORM:
gam.
George H. Eiser, III
City Attorney