HomeMy WebLinkAboutCC RESO 2005 - 48RESOLUTION NO. 2005 — 48
RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF NATIONAL CITY
AUTHORIZING THE CITY ENGINEER TO EXECUTE
CHANGE ORDER NO. 15 WITH MARCOTTE & HEARNES BUILDERS, INC.
IN THE TOTAL AMOUNT OF $37,378 FOR UPGRADES TO THE
TRAINING TOWER BEING CONSTRUCTED AS PART
OF THE FIRE STATION PROJECT
WHEREAS, the contract for the Fire Department Construction Project was
awarded to Marcotte & Heames Builders, Inc. on February 17, 2004, by the adoption of
Resolution No. 2004-31; and
WHEREAS, a number of training items and upgrades requested by the
Fire Department during the design of the training tower were not included in the plans
and specifications due to budget concerns; and
WHEREAS, now that the project is well along in construction, it is clear
that the budget will support the previously requested training items and upgrades.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City
of National City hereby authorizes the City Engineer to execute Change Order No. 15
with Marcotte & Heames Builders, Inc. in the total amount of $37,378 for upgrades to the
training tower being constructed as part of the fire station project.
PASSED and ADOPTED this 1st day of March, 2005.
WOW
Ni Inzunza, Mayor
ATTEST:
s
Midhael Dalla/ City Clerk
APPROVED AS TO FORM:
George H. iser, III
City Attorney