HomeMy WebLinkAbout2006 CC RESO 2006-194 CDCRESOLUTION NO. 2006 — 194
RESOLUTION OF THE
COMMUNITY DEVELOPMENT COMMISSION
OF THE CITY OF NATIONAL CITY APPROVING
DOWNTOWN SPECIFIC PLAN CONSISTENCY REVIEW
FOR DEVELOPMENT PROJECT, 'PARK LOFTS'
LOCATION: 1509, 1531, 1535 NATIONAL CITY BOULEVARD
AND 49 EAST 16TH STREET
APPLICANT: WILLMARK COMMUNITIES, INC.
CASE FILE NO.: DSP-2006-1
WHEREAS, .the applicant has filed an application for Downtown Specific Plan
Consistency Review; and
WHEREAS, the adopted procedures for Consistency Review require the
Community Development Commission Board to consider all development proposals at a public
hearing; and
WHEREAS, the Community Development Commission Board considered the
application at a duly advertised public hearing held on August 22, 2006 at which time oral and
documentary evidence was presented; and
WHEREAS, at said public hearing the Community Development Commission
Board considered the recommendation and findings of the staff report contained in Case File
No. DSP-2006-1, which is incorporated herein by reference, along with the evidence and
testimony at said hearing; and
WHEREAS, this action is taken pursuant to all applicable procedures required by
State law and City law; and
WHEREAS, the action recited herein is found to be essential for the preservation
of public health, safety, and general welfare; and
WHEREAS, the Community Development Commission Board desires to achieve
the goals and implement the policies of the Downtown Specific Plan; and
WHEREAS, the Community Development Commission Board has determined
that the adoption of the action recited herein would further the goals and policies of the
Downtown Specific Plan.
NOW, THEREFORE, BE IT RESOLVED that the Community Development
Commission Board finds that the testimony and evidence presented at the public hearing
support the following findings:
1. Basic Compliance — The project complies with the maximum height, minimum setback,
maximum floor -area -ratio, maximum density (where applicable), minimum build -to -line, and
minimum parking requirements and standards of the Specific Plan.
2. Creating a Place for People — The project enhances the pedestrian experience with
attractive and distinctive design and amenities.
3. Enrich the Existing — The project enriches the qualities of the existing downtown by
exhibiting a distinctive design that arises from and complements its setting, including the
scale of the downtown, the block, and the street.
Resolution No. 2006 —194
September 5, 2006
Page 2
4. Make Connections — The project is integrated physically and visually with its surroundings.
The project exhibits attention on how to get around by foot, bicycle, public transportation
and automobile — in that order.
5. Work with the Landscape — The project strikes a balance between the natural and man-
made environment and utilizes each site's intrinsic resources — the climate, landform,
landscape, and ecology to maximize energy conservation and create distinctive amenities.
6. Mix Uses and Forms — The project weaves together different building forms, uses, textures,
and densities.
7. Design for Change — The project is designed for energy and resource efficiency; creating
flexibility in the use of property, public spaces (including the sidewalk) and the service
infrastructure and introduces or acknowledges through design; new approaches to
transportation, traffic management and parking.
BE IT FURTHER RESOLVED that the Community Development Commission
Board has considered that the Program Environmental Impact Report for the Downtown Specific
Plan serves as adequate environmental documentation, together with any comments received
during the public review process, and finds on the basis of the whole record that that the project
was adequately considered by the Program Environmental Impact Report, which reflects the
Community Development Commission Board's independent judgment and analysis, and hereby
authorizes the filing of a Notice of Determination.
BE IT FURTHER RESOLVED that based on the findings hereinbefore stated,
that the Community Development Commission Board approves said Downtown Specific Plan
Consistency Review subject to the following conditions:
1. Mitigation Measures. The project shall be subject to all applicable mitigation measures of
the adopted Mitigation Monitoring and Reporting Program of the certified Program EIR for
the Downtown Specific Plan.
2. Approved Plan. The project shall be developed and maintained in substantial conformance
with Exhibit (DSP-2006-1), dated June 20, 2006, except as modified by the conditions of
approval.
3. Paseo Plans. The applicant shall submit paseo improvement plans for approval and shall
install and construct all improvements pursuant to the approved plans prior to occupancy.
The paseo shall be designed to allow ingress and egress of emergency, maintenance, and
service vehicles to the adjacent park and library. Restroom facilities shall be provided if
determined to be feasible and desirable by the City.
4. Library Parking. The applicant shall install a second driveway approach on National City
Boulevard to the adjacent library parking lot, and shall restripe and improve the parking lot
to provide the maximum number of parking spaces possible.
5. Landscape Plans. The applicant shall submit landscape and irrigation plans for approval
and shall install and construct all improvements pursuant to the approved plans prior to
occupancy.
Resolution No. 2006 —194
September 5, 2006
Page 3
6. Lighting Plans. The applicant shall submit lighting plans for approval and shall install and
construct all lighting pursuant to the approved plans prior to occupancy. Lighting shall be
designed to provide adequate illumination for safety, security, identification, and direction as
well as for landmark visibility of the primary buildings and/or significant features of the
project.
7. Sign Program. The applicant shall submit a sign program for approval, and all signs shall
be designed and installed pursuant to the approved sign program.
8. Public Art Program. The applicant shall submit a public art program for approval and shall
install, construct, or implement the approved public art program prior to occupancy.
9. Green Design. The applicant shall incorporate green design, energy efficiency, waste
reduction, recycling, conservation, and sustainable design in the project to the maximum
extent feasible.
10. Public Improvements. The applicant shall submit improvement plans for all adjacent public
rights -of -way for approval. The plans shall be consistent with the Downtown Specific Plan,
including the Open Space Framework, the Streetscape Master Plan, and the Design
Guidelines. The improvements shall include but not be limited to streets; alleys; curbs and
gutter; sidewalks; medians; parkways; landscape; street lights; street furniture; traffic
control; parking facilities; utilities; water, sewer, and drainage facilities; and other necessary
facilities and infrastructure. The applicant shall install and construct the improvements
pursuant to the approved plans prior to occupancy.
11. Engineering Requirements. The applicant shall comply with all engineering requirements,
including the listed requirements contained in Engineering Department memorandum dated
April 17, 2006.
a) A Hydrology study (100 year flood) is required for the new project. The study should
consider the proposed project area to the closest municipal storm drain collection
point. The study should consider the adequacy of the existing storm drain system to
convey any additional run off. All Hydrology study findings and recommendations
are part of Engineering Department requirements.
b) The Priority Project Applicability checklist for the Standard Urban Storm -water
Mitigation Plan (SUSMP) is required to be completed and submitted to the
Engineering Department. The checklist will be required when a project site is
submitted for review of the City Departments. The checklist is available at the
Engineering Department. If it is determined that the project is subject to the `Priority
Project Permanent Storm Water BMP Requirements" and the City of National City
Storm Water Best Management Practices of the Jurisdictional Urban Runoff
Management Program (JURMP), an approved SUSMP will be required prior to
issuance of an applicable engineering permit. The SUSMP shall be prepared by a
Registered Civil Engineer.
Resolution No. 2006 — 194
September 5, 2006
Page 4
c) The Best Management Practices (BMPs) for the maintenance of the proposed
construction shall be undertaken in accordance with the National Pollutant
Discharge Elimination System (NPDES) regulations which may require a Storm
Water Pollution Prevention Plan (SWPPP) for the project. An approved SWPPP
will be required prior to issuing of a construction permit.
d) All surface run-off shall be collected by approved drainage facilities and directed to
the street by sidewalk underdrains or a curb outlet. Adjacent properties shall be
protected from surface run-off resulting from this development.
e) A grading and drainage plan shall be submitted showing all of the proposed and
existing on -site and off -site improvements. The plan shall be prepared in
accordance with the City's standard requirements by a Registered Civil Engineer.
All necessary measures for prevention of storm water pollution and hazardous
material run-off to the public storm drain system from the proposed parking lot or
development shall be implemented with the design of the grading. This shall include
the provision of such devices as storm drain interceptors, clarifiers, or filters. Best
Management Practices for the maintenance of the parking lot, including sampling,
monitoring, and cleaning of private catch basins and storm drains, shall be
undertaken in accordance with the National Pollution Discharge Elimination System
(NPDES) regulations. A private storm water treatment maintenance agreement
shall be signed and recorded. The checklists for preparation of the grading plan
drainage plan and Standard Urban Storm Water Mitigation Plan (SUSMP) are
available at the Engineering Department.
f) A National Pollutant Discharge Elimination System (NPDES) permit is required for
discharged of storm water runoff associated with construction activity where
clearing, grading, and excavation results in a land disturbance. A construction
stormwater permit shall be obtained from the Regional Water Quality Control Board.
A copy of the permit shall be given to the City of National City Engineering
Department prior to any work beginning on the project.
A sewer permit will be required. A sewer study shall consider the adequacy of the
existing sewer system. The sewer study recommendations shall be part of the
Engineering Department Requirements. The method of sewage collection and
disposal shall be shown on the grading/drainage plan. Any new sewer lateral in the
City right-of-way shall be 8-inch in size with a clean out and the installation of a
manhole in the street. A sewer stamp "S" shall be provided on the curb to mark the
location of the lateral. A sewer main runs through the alley that shall be addressed
or relocated if building is to be constructed in this location.
h) A soils engineering report shall be submitted for the Engineering Department's
review, after Planning Commission approval. The report shall address the
adequacy of the building pads, the criteria for any new retaining wall design, the
maximum allowable soil bearing pressure. As a minimum, the parking lot pavement
sections shall be 2-inch A.C. over 4-inch Class II aggregate base. The street
pavement sections shall be in accordance with National City modified Standard
Drawing G-34. All soils report findings and recommendations shall be part of the
Engineering Department requirements.
g)
Resolution No. 2006 — 194
September 5, 2006
Page 5
i) The deteriorated portions of the existing street improvements (including sidewalks
and curbs) along the property frontages shall be removed and replaced.
j) A permit shall be obtained from the Engineering Department for all improvement
work within the public right-of-way, and any grading construction on private
property.
k) Street improvements shall be in accordance with City Standards. Abandoned
driveway aprons shall be replaced with curbs, gutters, and sidewalks.
I) A title report shall be submitted to the Engineering Department, after the Planning
Commission approval, for review of all existing easements and the ownership of the
property.
m) A cost estimate for all of the proposed grading, drainage, street improvements,
landscaping and retaining wall work shall be submitted with the plans. A
performance bond equal to the approved cost estimate shall be posted. Three
percent (3%) of the estimated cost shall also be deposited with the City as an initial
cost for plan checking and inspection services at the time the plans are submitted.
The deposit is subject to adjustment according to actual worked hours and
consultant services.
n) An existing 35-foot wide drainage easement reserved to the City of National City
exists at the sough side of the property. No building encroachment will be allowed
within the easement. The easement shall be shown on the grading plans and on
the final map
o) The Final Map shall meet all of the requirements of the Subdivision Map Act, and
the City of National City Municipal Codes including certification, acknowledgement,
complete boundary information and monumentation.
p) The subdivider shall submit an approval letter from Sweetwater Authority stating fire
flow requirements have been met. If additional improvements are needed, the
developer shall enter into an agreement for the water improvements with the
Authority prior to obtaining the Final Map approval.
q) The developer shall bond for the monumentation, the public improvements and the
on -site grading, drainage, landscaping, and other improvements through an
agreement with the City prior to the approval of the Final Map.
r) The proposed street and alley vacation at this site shall be approved by the City
council prior to the final map approval. City vehicle access shall be provided to
maintain the park.
s) All utility distribution facilities within the boundaries of the subdivision, and within the
half street abutting the new subdivision, shall be placed underground.
t) The Final Map shall be recorded prior to issuance of any building permit.
Resolution No. 2006 — 194
September 5, 2006
Page 6
u) All new property line survey monuments shall be set on private property, unless
otherwise approved.
v) The Final Map shall use the California Coordinate System for its "Basis of Bearings"
and express all measured and calculated bearings in terms of the system. The
angle of grid divergence from a true meridian and the north point shall appear on
the map. Two measured ties from the boundary of the property to existing horizontal
control stations shall be shown.
12. Public Works Requirements. The applicant shall comply with all public works requirements,
including the listed requirements contained in Public Works Department memoranda dated
January 5, 2006 and April 12, 2006.
a) The developer shall replace the existing sidewalks adjacent to the project.
b) 15th Street pedestrian paseo — Any material other than standard asphalt concrete
hot mix shall be maintained by the project HOA. Ingress and egress via the paseo
to the City Library shall be preserved.
c) Sewer facilities — The developer shall agree to obtain occupancy of the project after
the City completes its trunk line upgrade project.
d) The developer shall replace the existing street trees with a tree palette
commensurate with the building's architecture and adjacent landscaping theme.
e) The developer shall install streetlights along street and paseo frontages.
f) Vine type plants shall be planted to cover the wall along the east project boundary,
and shall be maintained by the project HOA.
g) Access to the park and library for emergency vehicles and delivery trucks (10-ton)
shall be maintained.
13. Fire Department Requirements. The applicant shall comply with all Fire Department
requirements, including the listed requirements contained in Fire Department memoranda
dated March 21, 2006.
a) Project to be designed, developed and constructed in compliance with the
California Fire Code (CFC) 2001 edition or CFC in effect at time of permit issuance
and the most current National Fire Protection Association (NFPA) Standards as
adopted by the City of National City
b) Automatic fire sprinkler system will be required.
c) Automatic and manual fire alarm system with communications system will be
required.
d) Class I standpipe system will be required
Resolution No. 2006 —194
September 5, 2006
Page 7
e) Emergency vehicle access will be required on the north side of the structure.
Roadway to have a minimum width of 20 feet with a minimum vertical clearance of
13 feet, 6 inches. Turnaround will be required.
f) Clear and easily accessible emergency ingress and egress to and throughout the
facility must be provided and maintained.
14. Building Department Requirements. The applicant shall comply with all Building
Department requirements, and plans shall comply with the 2001 editions of the California
Building Code, the California Mechanical Code, the California Plumbing Code, the
California Electrical Code, and California Title 24 energy and handicapped regulations.
15. Police Department Requirements. The applicant shall comply with all Police Department
requirements, including the requirements contained in Police Department memorandum
dated March 13, 2006.
a) The project shall comply with the crime free multi -housing criteria and crime
prevention through environmental design standards.
16. National City Transit Requirements. The applicant shall comply with all National City
Transit requirements, including the requirements contained in National City Transit
memorandum dated April 20, 2006.
a) Evaluate the installation of a new bus stop along National City Boulevard near the
intersection of 14th Street (Library) or other nearby locations with a shelter, benches,
route map and trash containers. This shelter should include an electrical lighting
component and at least two CCTV security cameras with a direct feed to NCPD.
b) Include this stop (and project) in any evaluation of a Green Car -Community circulator
shuttle operation such as under consideration with Revolution R2 (Constellation
Property Group) S-2006-6/DSP-2005-1 & Centro (Constellation Property Group) S-
2006-6/DSP-2005-1.
c) The developer should bear all associated costs to implement any Transit
recommendations.
d) Submit the plans to MTS Planner Mike Daney (mike.daney@sdmts.com) for his review
and comments.
17. Covenants, Conditions, and Restrictions. The applicant shall submit a declaration of
covenants, conditions, and restrictions for approval prior to approval of a final subdivision
map. The CC&Rs shall run with the land, clearly setting forth privileges and
responsibilities, including maintenance, involved in the common ownership of buildings,
streets, parking areas, walks, open spaces, recreation areas, utilities, and common areas
and facilities. The CC&Rs shall allow the City of National City the authority but not the
obligation to assume the maintenance of the property and assess the full cost, including
overhead costs, as a lien against the property if said property is not adequately maintained
pursuant to the CC&Rs. The CC&Rs shall include a determination that the funds provided
Resolution No. 2006 —194
September 5, 2006
Page 8
by the maintenance provisions will be sufficient to cover all contemplated costs. The
CC&Rs shall be approved as to form and content by the City Attorney of the City of National
City.
18. Property Owners Association. A corporation, association, property owners' group, or
similar entity shall be formed with the right to assess properties that are jointly owned with
interests in the common areas and facilities in the entire development to meet the
expenses of such entity, and with authority to control, and the duty to maintain, all such
common areas and facilities. Such entity shall operate under recorded CC&Rs approved
by the City of National City, which shall include compulsory membership of all property
owners and flexibility of assessments to meet changing costs of maintenance, repairs, and
services.
19. Business Improvement District. Pursuant to the Implementation Program of the Downtown
Specific Plan, the subject property shall be incorporated into the Morgan Square Business
Improvement District and assessed as provided for in the district for purposes for which the
district was formed.
20. Landscape Maintenance District. Pursuant to the Implementation Program of the
Downtown Specific Plan, all properties within the boundaries of the Downtown Specific
Plan shall be incorporated into a landscape maintenance district and assessed as provided
for in the district for purposes for which the district was formed.
21. Parking District. Pursuant to the Implementation Program of the Downtown Specific Plan,
all properties within the boundaries of the Downtown Specific Plan shall be incorporated
into a parking district and assessed as provided for in the district for purposes for which the
district was formed.
22. Acceptance of Conditions. The applicant and property owner shall sign and have notarized
an Acceptance Form acknowledging and accepting all conditions of approval of this permit.
Failure to return the signed and notarized Acceptance Form within 30 days of approval of
this permit shall automatically terminate this permit. The applicant shall record a Notice of
Restriction on Real Property with the San Diego County Recorder. The Notice of
Restriction shall provide that the conditions of approval of this permit are binding on all
present and future interest or estate holders of the property. The Notice of Restriction shall
be approved as to form by the City Attorney of the City of National City and signed by the
City Manager of the City of National City prior to recordation.
23. Expiration. This permit shall expire two years after the effective date of approval unless
prior to that date a request for a time extension has been filed in writing to the Community
Development Commission. The process for a time extension shall be the same as the
process for application for the original permit.
BE IT FURTHER RESOLVED that copies of this Resolution shall be transmitted
forthwith to the applicant.
Resolution No. 2006 —194
September 5, 2006
Page 9
BE IT FURTHER RESOLVED that this Resolution shall become effective and
final on the day following the Community Development Commission meeting where the
resolution is adopted. The time within which judicial review of this decision may be sought is
governed by the provisions of Code of Civil Procedure Section 1094.6.
PASSED and ADOPTED this 5th day of September, 2006.
ATTES
is Zapata, ect tary
APPROVED AS TO FORM:
George H. Eiser, III
Legal Counsel
Passed and adopted by the Community Development Commission of National City,
California, on September 5, 2006, by the following vote, to -wit:
Ayes: Councilmembers Inzunza, Morrison, Natividad, Parra, Zarate.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY:
NICK INZUNZA
Chairman Counity Development Commission
Secreta
omm
ty Development Commission
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2006-194 of the Community Development Commission of the City
of National City, California, passed and adopted on September 5, 2006.
Secretary Community Development Commission
By:
Deputy