RESOLUTION NO. 2009 — 129
RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF NATIONAL CITY
RATIFYING CHANGE ORDER NO. 4 WITH
L.B. CIVIL CONSTRUCTION IN THE NOT -TO -EXCEED
AMOUNT OF $17,468.34 TO PROVIDE CONSTRUCTION
CHANGES FOR THE FINAL DESIGN PLANS FOR
SDG&E AND AT&T UNDERGROUNDING FOR
THE BAY MARINA DRIVE WIDENING PROJECT
WHEREAS, on February 17, 2009, the City Council adopted Resolution No.
2009-25, approving a contract in the amount of $1,060,500.30 with L.B. Civil Construction, Inc.,
for construction improvements associated with the Bay Marina Drive Widening Project; and
WHEREAS, on April 29, 2009, Change Order No. 1 was approved in the amount
of $3,303.09 to address the stripping necessary to change 23rd Street from a one-way street to
a two-way street to provide access to businesses in the area when Harrison Avenue is closed to
through traffic; and
WHEREAS, Change Order No. 2 provided for the slurry seal of casings installed
under railroad crossings to accomplish final designs for SDG&E at one location, but was voided
and is now included in Change Order No. 4, which includes all locations; and
WHEREAS, Change Order No. 3 in the amount of $2,537.50 dated May 5, 2009,
provided for the installation of the future waterline tie-in under the sidewalk at Harrison adjacent
to Bay Marina Drive, which will save the cost of removing and replacing a new sidewalk for the
Naar Streetscape phase of the work in the future; and
WHEREAS, Change Order No. 4 in the amount of $17,468.34, provides for the
slurry seal of casings installed under the railroad crossings; and
WHEREAS, pursuant to the Disposition and Development Agreement between
the Community Development Commission of the City Of National City and Marina Gateway
Development Company, LLC., and Sycuan Tribal Development Corporation, the City of National
City is obligated to complete the Bay Marina Project by June 1, 2009, therefore it was necessary
to authorize Change Order No. 4 prior to council approval.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby ratifies Change Order No. 4 to the Agreement with L.B. Construction, Inc.,
in the amount of $17,468.34 for the slurry seal of casings installed under the railroad crossings
for the Bay Marina Drive Widening Project.
PASSED and ADOPTED this 2nd day of June,
ATTEST:
hael R. Dalla,
My
on Morrison, Mayor
APPROVED AS TO FORM:
i t Clerk
George H. Eiser, III, City Attorney
Passed and adopted by the Council of the City of National City, California, on June 2,
2009 by the following vote, to -wit:
Ayes: Councilmembers Parra, Sotelo-Solis, Van Deventer, Zarate.
Nays: None.
Absent: Councilmember Morrison.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
ict624iiiiii)
erk of the City of f�a
City tional City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2009-129 of the City of National City, California, passed and adopted
by the Council of said City on June 2, 2009.
City Clerk of the City of National City, California
By:
Deputy