HomeMy WebLinkAboutCC RESO 12,392RESOLUTION NO. 12,392
RESOLUTION AUTHORIZING EXECUTION OF A LETTER
OF AGREEMENT BETWEEN ENVIRONMENTAL IMPACT
PROFILES AND CITY OF NATIONAL CITY FOR
PREPARATION OF ENVIRONMENTAL REPORT/STATEMENT
FOR EUCLID AVENUE
BE IT RESOLVED by the City Council of the
City of National City that the Mayor is authorized and
directed to execute on behalf of the City of National
City that certain letter of agreement between Environmental
Impact Profiles and the City of National City for
preparation of an Environmental Report/Statement for
Euclid Avenue.
PASSED AND ADOPTED this 28th day of June, 1977.
ATTEST:
N. U. toes. no. 1L,.77L
vJ
O
U
Dedicated to improving Man's use of his environment
CDO
642 SOUTH B STREET TUSTIN, CALIFORNIA 92680 (714) 544-3263
June 24, 1977
Mr. Dale W. E[offland, City Engineer
Director of Public Works
CITY OF NATIONAL CITY
1243 National Avenue
National City, California 92050
GIIY U- P!, :UIV,IL LIII
EN":INEERING DEPT.
RECEIVED
Date_JUN 27 1977
Re: Contract to Prepare an Environmental Impact Report/Environmental
Impact Statement for the Euclid Avenue Extension
Dear Mr. Hoffland:
Environmental Impact Profiles (EIP) is pleased to accept the contract
for preparing an Environmental Impact Report/Environmental Impact
Statement for the four -lane facility which would complete Euclid
Avenue between Plaza Boulevard and 22nd Street.
In accordance with our proposal, dated June 9, 1977, traffic
generation, volumes, safety benefits, both vehicular and pedestrian,
will be prepared by Herman Kimmel and Associates, Inc., of Newport
Beach, California.
Olson Laboratories, Inc., Anaheim, California, will analyze the noise
problems and offer mitigation measures. Air quality problems and
possible mitigation measures will be addressed by J. Robert Stinson,
Ph. D., meteorologist and air pollution consultant. Erosion control
methods and water conservation considerations will be prepared under
the direction of Dr. Stinson and Burton B. Milburn, Dr. P.H.
Clarice C. Corbett will be Project Coordinator, and Christopher
Danforth will be Project Manager.
Schedule and Report:
EIP and Herman Kimmel and Associates will start work immediately upon
notification that our contract has been formally accepted and approved.
EIP's draft EIR/EIS would be completed within fifteen (15) working
days after receipt of reports from the Traffic Engineers and Olson
Laboratories, Inc. Under separate contract to Environmental Impact
Profiles, Herman Kimmel and Associates, Inc., agree to submit their
Mr. Dale W. Hoffland, City Engineer
CITY OF NATIONAL CITY
June 24, 1977 - Page Two
report to Environmental impact Profiles within 30 working days
after receiving notificction that their contract has been awarded.
EIP will submit fifty (50) copies of the Draft EIR/EIS and will
submit fifty (50) copies of the Final EIR/EIS, which would incorporate
responses to the Draft as an Addendum.
Fee:
EIP's fixed fee for performing these tasks will be $11,200
(EIP - $5,500; Herman K mmel and Associates, $5,700).
EIP proposes that a ziner of $4,000 be issued, from which they will
pay Herrman Kimmel and ssociates' retainer:
EIP proposes that a payment of $4,800 be paid upon submission of the
Draft EIR/EIS, and that a payment of the remainder ($2,400) be paid
upon submission of the Final EIR/EIS.
EIP will attend one meeting of the Planning Commission and one Council
meeting (pre -planning meetings are not considered to be extra ::ost)
for its fixed fee of $5,500. If Herman Kimmel and Associates are
required to attend Planning and Council meetings, their fees would be
negotiated through this firm. If EIP is required to attend more than
the above -listed two meetings, their fee for doing so is $50.00 per
hour, including travel time.
Environmental Impact Profiles thanks you for your consideration. If
there are further questions, please feel free to call.
Sincerely yours,
ENVIRONMENTAL IMPACT PROFILES
Clarice C. Corbett,
Manager - Treasurer
C3/tm
ACCEPTED AND APPROVED:
CITY OF NATIONAL CITY