HomeMy WebLinkAboutCC RESO 2011-191RESOLUTION NO. 2011 — 191
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
ACCEPTING THE WORK PERFORMED BY OHNO CONSTRUCTION, INC.,
FOR THE TOTAL FINAL CONTRACT AMOUNT OF $626,708.25,
AUTHORIZING THE FILING OF THE NOTICE OF COMPLETION,
AND AUTHORIZING THE RELEASE OF THE REMAINING
RETENTION IN THE AMOUNT OF $53,249.81 FOR
THE NATIONAL CITY EL TOYON SOCCER FIELD PROJECT
BE IT RESOLVED by the City Council of the City of National City as follows:
It appearing to the satisfaction of the Engineering Division of the Development
Services Department that all work required to be done by Ohno Construction, Inc., for the total
final contract amount of $626,708.25, for the National City El Toyon Soccer Field Project has
been completed, the City Council of National City hereby accepts said work, authorizes the file
of the Notice of Completion, and orders that payment for said work be made in accordance with
said contract, including release of the remaining retention in the amount of $53,249.81.
PASSED and ADOPTED this 6th day of September, 2011.
n Morrison, Mayor
ATTEST:
ft
Michael R. Dalla, City Clerk
APP OVED AS TO FORM:
Cla
City • ttorney
Passed and adopted by the Council of the City of National City, California, on
September 6, 2011 by the following vote, to -wit:
Ayes: Councilmembers Morrison, Natividad, Rios, Sotelo-Solis, Zarate.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
Cyi,,/,,(Ar
of the City of N
City 'ational City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2011-191 of the City of National City, California, passed and
adopted by the Council of said City on September 6, 2011.
City Clerk of the City of National City, California
By:
Deputy