HomeMy WebLinkAboutCC RESO 2017-207RESOLUTION 2017 — 207
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
ACCEPTING THE WORK PERFORMED BY KINSMAN CONSTRUCTION
COMPANY, INC., FOR THE POLICE DEPARTMENT BUILDING
IMPROVEMENTS PROJECT, APPROVING THE FINAL CONTRACT
AMOUNT OF $1,127,648.27, RATIFYING THE RELEASE OF RETENTION
IN THE AMOUNT OF $5,527.43, AND AUTHORIZING THE MAYOR
TO SIGN THE NOTICE OF COMPLETION FOR THE PROJECT
WHEREAS, the Engineering Department is satisfied that all work required to be
performed by Kinsman Construction Company, Inc., for the Police Department Building
Improvements Project has been completed.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
National City that the work performed by Kinsman Construction Company, Inc., for the Police
Department Building Improvements Project is accepted, the total final contract amount of
$1,127,648.27 is approved, the Mayor is authorized to execute the Notice of Completion, and
payment for said work is ordered to be made in accordance with said contract, including release
of retention in the amount of $5,527.43.
PASSED and ADOPTED this 7th day of Nove 017.
on .rrison, 'ayor
ATTEST:
Mic .el R. Dalla, CClerk
APPROVED AS
taWirr
Morn -Jones
Attorney
FORM:
Passed and adopted by the Council of the City of National City, California, on
November 7, 2017 by the following vote, to -wit:
Ayes: Councilmembers Cano, Mendivil, Morrison, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
pof the /
CI rk •f
CityCity
National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2017-207 of the City of National City, California, passed and
adopted by the Council of said City on November 7, 2017.
City Clerk of the City of National City, California
By:
Deputy