HomeMy WebLinkAboutCC RESO 2018-24RESOLUTION NO. 2018 — 24
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
AUTHORIZING THE ESTABLISHMENT OF AN APPROPRIATION OF
REVENUES AND EXPENDITURES IN THE AMOUNT OF $325,000
FOR FEDERAL ACTIVE TRANSPORTATION GRANT FUNDS FOR
THE EL TOYON-LAS PALMAS BICYCLE CORRIDOR PROJECT
WHEREAS, the El Toyon-Las Palmas Bicycle Corridor Project (the "Project")
includes construction of a new bicycle corridor parallel to the east side of 1-805 connecting El
Toyon Park and Las Palmas Park; and
WHEREAS, the City desires to expand and install improvements to the bicycle
corridor to the existing trail between Division Street and East 4th Street immediately adjacent to
1-805; and
WHEREAS, improvements along the bicycle corridor will include Class II and III
bike route pavement markings (sharrows) and signage; pedestrian curb ramps for ADA
compliance; traffic calming measures such as pedestrian refuge islands, corner bulb -outs and
pedestrian actuated flashing crosswalk signs; and storm water treatment infiltration areas; and
WHEREAS, on December 10, 2014, the California Department of Transportation
(Caltrans) awarded a $375,000 Federal Active Transportation Program (ATP) grant to National
City for the Project with no local match requirement; and
follows:
WHEREAS, the State's $375,000 allocation is distributed by Project phases as
• Project Approval and Environmental Documents (PA&ED) - $50,000
• Plans, Specifications and Estimate (PS&E) — $250,000
• Right -of -Way (ROW) - $75,000; and
WHEREAS, on April 25, 2016, Caltrans issued an Authorization to Proceed to
the City for the PA&ED phase, establishing the date for eligible reimbursement; and
WHEREAS, on June 21, 2016, City Council adopted Resolution No. 2016-96
authorizing staff to establish an appropriation of revenues and expenditures for $50,000 in
Federal ATP grant funds for the PA&ED phase of the project.
WHEREAS, on November 8, 2017, Caltrans issued an Authorization to Proceed
to the City for the PS&E and ROW phases, which requires the establishment of an appropriation
of revenues and expenditures in the amount of $325,000 for Federal ATP grant funds to
complete the PS&E and ROW phases of the Project.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby authorizes the establishment of an appropriation of revenues and
expenditures in the amount of $325,000 for Federal Active Transportation Grant funds for the El
Toyon-Las Palmas Bicycle Corridor Project.
[Signature Page to Follow]
Resolution No. 2018 — 24
Page Two
PASSED and ADOPTED this 20th day of Febru , 2018.
n Morrison, ayor
ATTEST:
c aeI R. D II
Mi a a, ity Clerk
APPROVED AS TO FORM:
rri
y Attorney
Passed and adopted by the Council of the City of National City, California, on
February 20, 2018 by the following vote, to -wit:
Ayes: Councilmembers Cano, Mendivil, Morrison, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
Jerk of the City do
City y f National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2018-24 of the City of National City, California, passed and adopted
by the Council of said City on February 20, 2018.
City Clerk of the City of National City, California
By:
Deputy