HomeMy WebLinkAboutCC RESO 2018-152RESOLUTION NO. 2018 — 152
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
ACCEPTING THE WORK PERFORMED BY PALM ENGINEERING
CONSTRUCTION COMPANY, INC., FOR THE WESTSIDE MOBILITY
IMPROVEMENTS PROJECT, APPROVING THE FINAL CONTRACT
AMOUNT OF $2,096,000.70, RATIFYING THE RELEASE OF RETENTION
IN THE AMOUNT OF $104,800.03, AND AUTHORIZING THE MAYOR
TO EXECUTE THE NOTICE OF COMPLETION FOR THE PROJECT
BE IT RESOLVED by the City Council of the City of National City as follows:
It appearing to the satisfaction of the Engineering Department that all work
required to be done by Palm Engineering Company, Inc., for the total final contract amount of
$2,096,000.70, for the Westside Mobility Improvements Project (CIP No. 17-04) has been
completed, the City Council of National City hereby accepts said work, ratifies the release of the
retention in the amount of $104,800.03, authorizes the Mayor to execute the Notice of
Completion, and orders that payment for said work be made in accordance with said contract.
PASSED and ADOPTED this 4th day of Septe er, 2018.
on Morrison, Mayor
ATTEST:
!r .4.xjjAr
Michel R. Della, Clerk
APPROVED AS TO FORM:
47\
Angil P. Morris -Jones
City Attorney
Passed and adopted by the Council of the City of National City, California, on
September 4, 2018 by the following vote, to -wit:
Ayes: Councilmembers Cano, Mendivil, Morrison, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
1� 4t
City Cl rk of the City of National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2018-152 of the City of National City, California, passed and
adopted by the Council of said City on September 4, 2018.
City Clerk of the City of National City, California
By:
Deputy