HomeMy WebLinkAboutCC RESO 2024-4 Dick Miller Inc. Eastside I-805 Community Greenbelt ProjectRESOLUTION NO. 2024
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY, CALIFORNIA,
1 AWARDING A CONTRACT TO DICK MILLER, INC. IN THE NOT -TO -EXCEED AMONT
OF $3,155,990.50 FOR THE EASTSIDE 1-805 COMMUNITY GREENBELT PROJECT, CIP
NO. 2 - ; 2 AUTHORIZING A 15% CONTINGENCY IN THE AMOUNT OF $473,398.58
FOR ANY UNFORESEEN CHANGES; AND 3 AUTHORIZING THE MAYOR TO EXECUTE
THE CONTRACT.
WHEREAS, the National City Eastside 1-805 Community r Greenbelt Project (the "Project")
is a combination of public right-of-way, multi -use path, and local park improvements located in
the City of National City along the east side of Interstate 805 between Division Street and Plaza
Boulevard; and
WHEREAS, the Project addresses ongoing issues related to waste debris, under-utilized
public right-of-way, safety, and comfort and is intended to implement a greenbelt for the
neighborhoods on the east side of Interstate 805 between Division Street and Plaza Boulevard,
as well as improving connections to El Toyon Elementary School, Rancho de la Nacion
Elementary School, El Toyon Park, and local shopping centers; and
WHEREAS, Project improvements include replacement of concrete paving, driveways,
sidewalk transitions, curb and gutter, asphalt and concrete pavement improvements, bus pad
improvements, reconstructing cross gutter, speed cushions, utility relocations, gravity retaining
wall, decorative concrete, stabilized DG, new landscape and irrigation, enhanced bus plaza
including installation of decorative memorial light columns, removable bollards, Spigot and Art
improvements, traffic signal modifications at Euclid and Plaza, LED illuminated crossings,
drainage improvements, ents, installation of a multi -use trail between 4th and Division and
miscellaneous electrical improvements; and
WHEREAS, on March 8, 2022, the State of California's Department of Transportation
notified the City that the Project had been awarded a Clean California Local Grant Program grant
in the amount of $4,998,761, with a $20,000 in -kind contribution of City staff, for a total project
cost of $5,01 ,7 1, and the City Council accepted the grant and established a Project budget on
June 21, 2022, per Resolution No. 2022-114; and
WHEREAS, on September 21, 2023, the bid solicitation for the Project was posted on
PlanetBids, a free public electronic bidding system for contractors; and
WHEREAS, on September 27th and 29th, 2023, the bid solicitation was advertised in the
local newspaper; and
WHEREAS, on October 11, 2023, one 1 bid was received by the 5:00 p.m. . deadline but,
upon review of all documents submitted, staff rejected the bid as non -responsive as it did not
meet the minimum Project requirements; and
WHEREAS, as a result of not receiving any responsive bids from the initial solicitation, on
November 8, 2023 staff re -advertised the Project on PlanetBids with a revised scope of work in
order to receive the bids within the budget allocations; and
WHEREAS, on November 1 1h and 20th 2023, the bid solicitation was advertised in the
local newspaper; and
WHEREAS, on December 1 , 2023, six (6) bids were received by the 5:00 pm deadline;
and
WHEREAS, upon review of all documents submitted, Dick Miller, Inc.'s bid in the total bid
amount of $3,155,990.50 was deemed responsive and the lowest responsible bidder qualified to
perform the work as described in the Project specifications; and
WHEREAS, City staff recommends 1) awarding a contract to Dick Miller, Inc. in the not -
to -exceed amount of ,1 5,990. 9 for the Eastside 1-805 Community Greenbelt Project, CIP No.
22-09; 2) authorizing a 1 %;/% contingency in the amount of S473,398.58 for any unforeseen
changes; and 3) authorizing the Mayor to execute the contract.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF NATIONAL CITY,
CALIFORNIA, DOES RESOLVE, DECLARE, DETERMINE, AND ORDER AS FOLLOWS:
Section 1: That the City Council hereby authorizes the Mayor to execute the contract
with Dick Miller, Inc. for $3,155,990.50 for the base bid and alternate bid for the Eastside 1-805
Community Greenbelt Project, CIP No, 22-09.
Section 2: That the City Council hereby authorizes a 15% contingency in the amount
of $473,398.58 for any unforeseen changes.
Section 3: That the City Clerk shall certify as to the passage and acoption of this
Resolution and enter it into the book of original Resolutions.
PASSED
and ADOPTED this 16th day of J�r ary 2024.
R " Morrison, Mayor
ATTEST:
7r)(IL
helle y Chi eI, MMC, C, City Clerk
p y
APPROVED AS TO FORM:
emety
Barry J. Sick1; , City Attorney
Passed and adopted by the City Council of the City of National City, California, on
January 16, 2024 by the following vote, to -wit:
Ayes: Bush, Molina, Rodriguez, Yamane, Morrison
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
BY:
Mayor of the City of National City, California
Shelley Chapel
City Clerk of the City of National City, California
Shelley Chapel, M M C, City Clerk
a.