RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY, CALIFORNIA,
1) ACCEPTING THE WORK PERFORMED BY WRIGHT CONSTRUCTION ENGINEERING
CORP. FOR THE PARADISE CREEK MITIGATION PROJECT AT KIMBALL WAY, CIP
NO. 19-35; 2) RATIFYING CHANGE ORDER WORK IN THE AMOUNT OF $64,218.07; 3)
APPROVING THE FINAL CONTRACT AMOUNT OF $1,005,761.71; 4) RATIFYING THE
RELEASE OF RETENTION IN THE AMOUNT OF $23,980.24; AND 5) AUTHORIZING THE
MAYOR TO SIGN THE NOTICE OF COMPLETION.
WHEREAS, the Paradise Creek Mitigation Project at Kimball Way repaired sections of
Paradise Creek at Kimball Way, including removing existing concrete lining on the south creek
bank, earthwork and regrading, and installing articulated concrete blocks and cutoff wall on the
south creek bank (the "Project"); and
WHEREAS, in addition, the Project enhanced the drainage, including adding new bar
screen gates at the outlet and inlet of existing reinforced concrete box storm drains, and rip rap,
as well as other site improvements that included installing a new retaining wall, concrete
driveways, perimeter wrought iron fencing, and access gates to secure the area; and
WHEREAS, on September 7, 2021, City Council awarded the contract for the Project to
Wright Construction Engineering Corp. ("Wright") in the amount not to exceed $818,733.60 and
authorized a 15% contingency in the amount of $122,810.04 to address any unforeseen
conditions that may arise; and
WHEREAS, on February 9, 2022, the Notice to Proceed with construction was issued to
Wright; and
WHEREAS, construction on the Project started on February 14, 2022 and was completed
on October 24, 2022; and
WHEREAS, after Project completion and within the Project's 1-year contractual
maintenance period, a failure of the adductor canal block ("ACB") developed on the south channel
slope; and
WHEREAS, after investigating the site with the Project team, the City Engineer directed
Wright to repair the slope on a time and materials ("T&M") basis in the interest of public safety;
and
WHEREAS, during repairs, Wright discovered that the failure was attributable to an
unknown pipe just below the slope excavation that ultimately created soil intrusion, resulting in
the slope failure and causing the ACB to settle; and
WHEREAS, total T&M costs for this work was $68,952.17; and
WHEREAS, the total amount of change order work completed for the Project exceeds the
original authorized 15% contingency amount by $64,218.07; and
WHEREAS, Project change orders and line -item adjustments increased the contract by
$187,028.11, which results in an 18.6% increase to the original contract award, for a final contract
balance of $1,005,761.71; and
WHEREAS, the Notice of Completion will be filed with the San Diego County Recorder's
Office.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF NATIONAL CITY,
CALIFORNIA, DOES RESOLVE, DECLARE, DETERMINE, AND ORDER AS FOLLOWS:
Section 1: That the City Council hereby accepts the work performed by Wright
Construction Engineering Corp. for the Paradise Creek Mitigation Project at Kimball Way, CIP No.
19-35.
Section 2: That the City Council hereby ratifies change order work in the amount of
$64,218.07.
Section 3: That the City Council hereby approves the final contract amount of
$1,005,761.71.
Section 4: That the City Council hereby ratifies the release of retention in the amount
of $23,980.24.
Section 5: That the City Council hereby authorizes the Mayor to sign the Notice of
Completion.
Section 6: That the City Clerk shall certify to the passage and adoption of this
Resolution and enter it into the book of original Resolutions.
PASSED and ADOPTED this 21st day of Lri 2024.
Morrison, Mayor
ATTEST:
,t Shelley Chapel, MMC, City Clerk
APPROVED AS TO FORM:
Barry J. SEh, City Attorney
Passed and adopted by the City Council of the City of National City, California, on
May 21, 2024 by the following vote, to -wit:
Ayes: Bush, Molina, Rodriguez, Yamane, Morrison
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
BY:
Mayor of the City of National City, California
Shelley Chapel
City Clerk of the City of National City, California
Shelley el, MMC, City Clerk