HomeMy WebLinkAboutCC Policy No. 502 - Change Orders As adopted October 5 2021CITY COUNCIL POLICY
CITY OF NATIONAL CITY
AMENDED OR REVISED: October 5, 2021 ADOPTED: FEBRUARY 6, 1990
POLICY #502 TITLE: PUBLIC IMPROVEMENTS OR PROFESSIONAL
SERVICE CONTRACT CHANGE ORDERS
PURPOSE
The purpose of this policy is to establish authorization limits and standard methods for the
approval of changes in contracts.
DEFINITIONS
Construction Contract: A written contract with a properly licensed contractor to construct public
improvements within the City of National City that conforms to the Standard Specifications for
Public Works Construction (hereinafter, "Green book") and special provisions.
Construction Change Order: A Construction Change Order is a written directive to the contractor
to make changes in the work within the general scope of the contract during the construction
period. Changes might involve additions to or deletions from the contract, adjustment of bid or
line item quantities exceeding the limits set by the latest edition of the Green Book, and special
provisions as follows:
• Addition of an item of work not specified in the original contract.
• Deletion of an item of work specified in the original contract or subsequent approved
change order.
• Adjustment of line item quantities beyond the limits allowed· in the latest edition of the
Green book and/or special provisions.
• Adjustment of contract time for reasons other than those allowed in the Green book or
special provisions.
On-Call Consultant Contract: A written agreement between the City and a professional services
provider that specifies the services to be provided to the City at defined rates on an as-needed
basis as requested by the City through written work orders.
On-Call Consultant Work Order: Written request from the City to an on-call consultant that
authorizes the consultant to perform work on a specific project within the budget, scope and
schedule defined in the work order that are within the scope and budget of the On-Call Consultant
Contract.
On-Call Consultant Contract Amendment: A written agreement with a consultant to make
specified changes to the On-Call Consultant Contract. An On-Call Consultant Contract
Amendment shall specify changes to services, rates, schedule adjustments and/or overall
contract value. The Amendment must be agreed to by the City and the Consultant.
CITY COUNCIL POLICY
CITY OF NATIONAL CITY
AMENDED OR REVISED: October 5, 2021 ADOPTED: FEBRUARY 6, 1990
POLICY #502 TITLE: PUBLIC IMPROVEMENTS OR PROFESSIONAL
SERVICE CONTRACT CHANGE ORDERS
Standard Consultant Contract: A written agreement between the City and a professional services
provider that specifies the services to be provided to the City at defined specific rates for a specific
project within a specific time.
Standard Consultant Contract Amendment: A written agreement with a consultant to make
specified changes to the Standard Consultant Contract. A Standard Consultant Contract
Amendment shall specify changes to services, rates, schedule adjustments and/or overall
contract value. The amendment must be agreed to by the City and the Consultant.
POLICY
1. Public improvement projects shall be administered in accordance with the latest edition of
the Green book, specifications and contract special provisions.
2. Adjustment of bid or line item quantities may be approved by the City Engineer for
adjustments within the limits set by the latest edition of the Green book and special
provisions. Adjustment of line item quantities that exceed the latest edition of the Green book
and/or the special provisions (whichever is greater) shall proceed under the Contractor
Change Order policy limits as prescribed below.
3. Designated officials of the City are authorized to approve Contract Change Orders to public
improvement contracts and amendments to on-call consultant contracts within the scope of the
contract, Council approved funding and the limits set forth as follows:
Designated Official Limits
City Engineer Aggregate Contract Change Orders,
Amendments to On-Call Consultant Contracts,
and Standard Consultant Contracts up to 15% of
the original contract amount, not to exceed a
maximum of $25,000 per change order or
amendment.
City Engineer Adjustments of contract time for justifiable delays
within the limits of the latest edition of the Green
book and special provisions.
City Manager Aggregate Contract Change Orders, Amendments
CITY COUNCIL POLICY
CITY OF NATIONAL CITY
AMENDED OR REVISED: October 5, 2021 ADOPTED: FEBRUARY 6, 1990
POLICY #502 TITLE: PUBLIC IMPROVEMENTS OR PROFESSIONAL
SERVICE CONTRACT CHANGE ORDERS
to On-Call Consultant Contracts, and Standard
Consultant Contracts up to 25% of the original
contract amount not to exceed a maximum
of $50,000 per change order or amendment.
City Manager May exceed the limits of authorization set forth
herein, if in the City Manager's opinion the
situation requiring the Contract Change Order is
of a nature that presents an emergency in which
there is a concern for public safety, or if delay
would cause un-necessary additional expenses.
In such a case, the Contractor Change Order will
subsequently be presented to the City Council for
ratification at the next regular City Council
meeting.
City Council Contract Change Orders, Amendments to On-Call
Consultant Contracts, and Standard Consultant
Contracts that exceed 25% of the original .contract
amount or $50,000 for a single Change Order or
Amendment.
CITY COUNCIL POLICY
CITY OF NATIONAL CITY
AMENDED OR REVISED: October 5, 2021 ADOPTED: FEBRUARY 6, 1990
POLICY #502 TITLE: PUBLIC IMPROVEMENTS OR PROFESSIONAL
SERVICE CONTRACT CHANGE ORDERS
Related Policy References
Prior Policy Amendments
November 9, 1982 (Resolution No. 13,924) Establishing Policy
February 6, 1990 (Resolution No. 16,173)
March 2, 2010 (Resolution No. 2010-30)
October 5, 2021 (Resolution No. 2021-148)