HomeMy WebLinkAboutA Good Sign and Graphics Co. - Wayfinding Signage Project - CIP No. 17-06 - Change Order No. 2 - 2017+r- CALIFORNIA *-0
NATIONAL CITY
eliVeV
agjcu
INCORPORATED
WAYFINDING SIGNAGE PROJECT
CIP NO. 16-03
A Good Sign, Inc.
CHANGE ORDER NO. 2
August 10, 2017
Reason/Purpose for this Change Order:
Fourteen (14) National City map panels are proposed to be installed throughout the downtown and Kimball Park
areas of the city. According to the Contractor, these map panels will have an estimated procurement time of 8-10
weeks. The contractor received final proofs for the map panels on June 5, 2017 (41 days after the Notice to
Proceed was provided) due to design and content modifications. The Contractor will require additional days in
order to have the maps fabricated.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with the fabrication and installation of
wayfinding signs provided with the time extension noted by this change order at no cost to the City. Forty-one
(41) working days shall be added after the original completion date as desginated by the Notice to Proceed. The
new completion date of the project is October 3, 2017. The agreed upon price for all cost associated with the
additional working days is $0.00.
Original Contract Amount . $
Net change by previously authorized Change Orders 16,441.03
Subtotal
Amount of this change order
New contract amount
Working days added: 41 Working days subtracted: 0
286,800.03
Percent change in Contract to date 6.08%
270,359.00
286,800.03
Sub "tte. by:
AIV
0.10.7_017
Proje*Inger
Date
Approved by:
, ,r1Y.e?
City Date
City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by A Good Sign, Inc.:
Name:
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
Date
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
A GOOD SIGN & GRAPHICS CO
COR # 02
Job Name: National City Wayfinding
Job Number. 1221
Full Description of Change in Sco •
Date: August 1, 2017
ASI # Phone Discussion
Time Impact 41 days per contract
Additional Days at no cost added to contract for getting an approval later than expected
Approval was given on Monday June 5th at 2:12 PM pendin • a actual di • ital • rint before
Breakdown Direct Labor
Rate Cost
Sign Type
Sign Detail
Hours
All sigrn types
Additional days at no cost
$0.00
SUBTOTALS 0.0
$0.00
Breakdown
n' i ype,
Sign
iatttity.
Direct Materiels
hatet
o
0
SUBTOTALS 0.0 $0.00
Breakdown Direct Equipment
Sign Type Sign Detail Qty Rate Cost
Breakdown
Sign Type Sign Detail
SUBTOTALS 0.0
Quantity
Other
Rate
$0.00
(Including GC & First Tier Sub cost)
SIJB. CON - NAME/TITLE
SUBTOTALS
'Combined Subtotal:
15% Markup:
Combined Subtotal + Markup:
Bond 1% (of 'Subtotal):
GRAND TOTAL
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
1
PROJECT PROFESSIONALS CORPO= %':1li?N
TRANSMITTAL COVER
To: National City Engineering Department
Project Name: Wayfinding Signage Projects, CIP No. 16-03
ITEMS DELIVERED:
Change Order No.2
Delivered Project Professionals Corporation
Received by:
Date: 17