HomeMy WebLinkAboutA Good Sign and Graphics Co. - Wayfinding Signage Project - CIP No. 16-03 - Change Order No. 8 - 2017WAYFINDING SIGNAGE PROJECT
CIP NO. 16-03
A Good Sign, Inc.
Reason/Purpose for this Change Order:
+ ,,CAUFORNiA`-
talfirONAktirry
160V
zNC08PORATED
CHANGE ORDER NO. 8
October 2, 2017
This Change Order replaces the banners that uses double brackets with a single bracket install method. During
the placement of the double banners in NC Old Town district, it was observed that the large light posts blocked
portions of the banner due the installation. After looking at a sample installation on -site, the designer decided
that it would be best to have the banners installed using a single bracket method instead of the double bracket
method to avoid blocking any part of the signage.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall replace the double bracket installation for banners to
single bracket installation. The contractor shall install all hardware and appurtenances associated with this
change order. The agreed upon price for all cost associated is$l- 00 6 -
.t3, Z 31 • / o
Original Contract Amount
Net change by previously authorized Change Orders...
Subtotal
Amount of this change order
270, 359.00
34,265.01
304, 624.01
3,239.10
New contract amount......... $
Workin • days added: 0 Working days subtracted: 0 Percent change in Contract to date 13.87%
Pro
Approved by:
D
307,863.11
Date . City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
ted and a ►reed to r A Good Sign, Inc.:
Name: Date :
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA
N!L1(T'V
INCORPORATED
WAYFINDING SIGNAGE PROJECT CHANGE ORDER NO. 8
CIP NO. 16-03
DATE: October 2, 2017
WORK PERFORMED BY: A Good Sign, Inc.
DESCRIPTION OF WORK: Modification of double bracket method to single bracket method
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Single pole banner harware
Discount for additional hardware
cost
Unit
EA
EA
Qty
36.00
36.00
Rate
93.00
(16.75)
Total
3,348.00
(603.00)
Sub -Total Labor:
$ 2,745.00
Material Markup (15%): 411.75
TOTAL MATERIALS:
Bonding (3%)
GRAND TOTAL:
82.35
$ 3, 239,1 O
PROJECT PROFESSIONALS CORPORATION
TRANSMITTAL COVER
To: National City Engineering Department
Project Name: Wayfinding Signage project, CIP No. 16-03
ITEMS DELIVERED:
Change Order No. 7 and 8
Delivered by: Vim
Project Professionals Corporation
Received by:
Date: