HomeMy WebLinkAboutA Good Sign and Graphics Co. - Wayfinding Signage Project - CIP No. 16-03 - Change Order No. 8 - 2017WAYFINDING SIGNAGE PROJECT CIP NO. 16-03 A Good Sign, Inc. Reason/Purpose for this Change Order: + ,,CAUFORNiA`- talfirONAktirry 160V zNC08PORATED CHANGE ORDER NO. 8 October 2, 2017 This Change Order replaces the banners that uses double brackets with a single bracket install method. During the placement of the double banners in NC Old Town district, it was observed that the large light posts blocked portions of the banner due the installation. After looking at a sample installation on -site, the designer decided that it would be best to have the banners installed using a single bracket method instead of the double bracket method to avoid blocking any part of the signage. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall replace the double bracket installation for banners to single bracket installation. The contractor shall install all hardware and appurtenances associated with this change order. The agreed upon price for all cost associated is$l- 00 6 - .t3, Z 31 • / o Original Contract Amount Net change by previously authorized Change Orders... Subtotal Amount of this change order 270, 359.00 34,265.01 304, 624.01 3,239.10 New contract amount......... $ Workin • days added: 0 Working days subtracted: 0 Percent change in Contract to date 13.87% Pro Approved by: D 307,863.11 Date . City Manager, required for Change Orders >$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. ted and a ►reed to r A Good Sign, Inc.: Name: Date : Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380 CALIFORNIA N!L1(T'V INCORPORATED WAYFINDING SIGNAGE PROJECT CHANGE ORDER NO. 8 CIP NO. 16-03 DATE: October 2, 2017 WORK PERFORMED BY: A Good Sign, Inc. DESCRIPTION OF WORK: Modification of double bracket method to single bracket method ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Single pole banner harware Discount for additional hardware cost Unit EA EA Qty 36.00 36.00 Rate 93.00 (16.75) Total 3,348.00 (603.00) Sub -Total Labor: $ 2,745.00 Material Markup (15%): 411.75 TOTAL MATERIALS: Bonding (3%) GRAND TOTAL: 82.35 $ 3, 239,1 O PROJECT PROFESSIONALS CORPORATION TRANSMITTAL COVER To: National City Engineering Department Project Name: Wayfinding Signage project, CIP No. 16-03 ITEMS DELIVERED: Change Order No. 7 and 8 Delivered by: Vim Project Professionals Corporation Received by: Date: