HomeMy WebLinkAbout2025-120 - Griffith Company - Awarding Contract for the Bayshore Bikeway Segment 5 and Connection ProjectRESOLUTION NO. 2025 - 120
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY, CALIFORNIA, 1)
AWARDING A CONTRACT TO GRIFFITH COMPANY IN THE NOT -TO -EXCEED AMOUNT OF
$13,076,599.50 FOR THE BAYSHORE BIKEWAY SEGMENT 5 AND CONNECTIONS
PROJECT, CIP NO. 19-24; 2) AUTHORIZING A 10% CONTINGENCY IN THE AMOUNT OF
$1,307,660 FOR ANY UNFORESEEN CHANGES; AND 3) AUTHORIZING THE MAYOR TO
EXECUTE THE CONTRACT.
WHEREAS, the Bayshore Bikeway Segment 5 and Connections Project, CIP No. 19-24
(the "Project") will provide nearly 1.5 miles of protected bicycle facilities along Harbor Drive,
McKinley Avenue, W. 23rd Street, and Marina Way in the City of National City ("City"), as well as
constructing a dedicated pedestrian and bicycle pathway on 19th Street under the 1-5 overpass
to provide safe connections for vulnerable roadway users between the Westside Neighborhood
and the Bayshore Bikeway; and
WHEREAS, on June 26, 2025, the bid solicitation for the Project was posted on
PlanetBids, a free public electronic bidding system for contractors; and
WHEREAS, on July 2"d and July 91h, 2025, the bid solicitation was advertised in the local
newspaper; and
WHEREAS, on July 22, 2025, five (5) bids were received by the 5:00 p.m. deadline; and
WHEREAS, upon review of all documents submitted, Griffith Company's bid in the total
bid amount of $13,076,599.50 was deemed responsive and they are the lowest responsible bidder
qualified to perform the work as described in the Project specifications; and
WHEREAS, City staff recommends 1) awarding a contract to Griffith Company in the not -
to -exceed amount of $13,076,599.50 for the Bayshore Bikeway Segment 5 and Connections
Project, CIP No. 19-24; 2) authorizing a 10% contingency in the amount of $1,307,660 for any
unforeseen changes; and 3) authorizing the Mayor to execute the contract.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF NATIONAL CITY,
CALIFORNIA, DOES RESOLVE, DECLARE, DETERMINE, AND ORDER AS FOLLOWS:
Section 1: That the City Council hereby authorizes the Mayor to execute the contract
with Griffith Company in the not -to -exceed amount of $13,076,599.50 for the Bayshore Bikeway
Segment 5 and Connections Project, CIP No. 19-24.
Section 2: That the City Council hereby authorizes a 10% contingency in the amount
of $1,307,660 for any unforeseen changes.
Section 3: That the City Clerk shall certify to the passage and adoption of this
Resolution and enter it into the book of original Resolutions.
PASSED and ADOPTED this 16th day of Se ber, 2025.
FV Morrison, Mayor
ATTEST:
Shelle hapel, MMC, City Clerk
APPROVED AS TO FORM:
Barry J. XcVz, City Attorney
Passed and adopted by the City Council of the City of National City, California, on
September 16, 2025 by the following vote, to -wit:
Ayes:
Molina, Rodriguez, Yamane, Bush, Morrison
Nays:
None.
Absent:
None.
Abstain:
None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
Shelley Chapel
City Clerk of the City of National City, California
BY:
Shelley Vpel, MMC, City Clerk