HomeMy WebLinkAboutProject Professionals Corporation - Kimball Park Ballfield Lighting Improvements - CIP No. 24-10 - Change Order No. 1 - 2025 P C
PROJECT PROFESSIONALS CORPORATION
CHANGE ORDER MEMORANDUM
MAY 16,2025
To: Stephen Manganiello,TE
Director of Engineering&Public Works/City Engineer
Engineering and Public Works Department
City of National City
From: Josh Johnson
Senior Construction Manager
Project Professionals Corporation
Project: Kimball Park Ballfield Lighting Improvements
CIP No.: 24-10
Subject: Change Order No.1
Change Order No. I provides for:
Proceeding with horizontal directional drilling approximately 50 linear feet of new 4"Schedule 80 PVC conduit
from last pullbox, beneath plaza improvements and into electrical room.
Payment for this change order will be as agreed upon lump sum.
Supporting Information:
During the installation of conduit and pull boxes,the Contractor was unable to locate the 4" PVC conduit as shown
on the construction plans,which was intended to run from the edge of the sidewalk beneath the park plaza's
concrete improvements and into the electrical building.
To investigate further,the Contractor potholed along the entire front edge of the concrete plaza.This investigation
revealed a direct-burial electrical wire in the approximate location where the conduit was expected,indicating a
deviation from the design plans.
To install the new conduit to the electrical building,two methods were evaluated:directional drilling and open
trenching(which would require removal and replacement of decorative concrete).After a thorough review of both
options,including cost and schedule impacts,directional drilling was determined to be the most cost-effective and
time-efficient solution.
Time Adjustment:
Five(5)working days are to be added to the contract.
Cost Adjustment:
The additional cost for this change in the scope of work has been agreed upon at a lump sum price of$17,813.53.
The pay method and amount have been reviewed by the Project Manager and are considered fair and reasonable.The
supporting documentation is on file with the project records.
Johnson, PPC 5/30/25
P ject anager Date
•%- CALIFORNIA --0-
NATIONAL CITY
INCORPORATZD
KIMBALL PARK BALLFIELD LIGHTING IMPROVEMENTS CHANGE ORDER NO. 1
CIP NO. 24-10 MAY 16,2025
Contractor: Huntington Beach Electric, Inc.
PO Box 1626
Huntington Beach,CA 92647
This Change Order modifies Contractor's and the City's obligations and rights under the abovementioned
contract. This change order is not effective until approved by the City.
Time adjustment:
Five(5)working days are to be added to the contract.
Cost of Change Order:
The City and the Contractor agree that the Contractor shall proceed with horizontal directional drilling
approximately S0 linear feet of new 4"Schedule 80 PVC conduit from last pullbox, beneath plaza
improvements and into electrical room.The total amount for all labor, material, equipment and all other
associated work is$17,813.53.
Recommended by Project Manager. os Johnson, PPC Date: 5/30/25
By signing this Change Order the Contrac or confirms that he/she is completely familiar with and has fairly
negotiated its price,terms and conditions. If this Change Order is approved, Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is
authorized to bind the Contractor to this Change Order.
Agreed and Accepted by Contractor: P.
(Print Name and Title) Date: 05/28/25
Approved by Project Coordinator: 14
. __ Date:
Approved by Assistant Director of E&PW: Inr Date:
J
Approved by City Engineer: , i� 7 Date:
Approved by City Manager: Date:
(Required for change orders$25,000 and above)
. CALIFORNIA
NATIONAL Clint
aCAV �
INCORPORATED
KIMBALL BALLFIELD LIGHITNG IMPROVEMENTS CHANGE ORDER NO. 1
CIP NO. 24-10
DATE: May 16,2025
WORK PERFORMED BY: Devco Development and Engineering
DESCRIPTION OF WORK: Horizontal Directional Drilling 4"Sch.80 PVC conduit
ACCOUNTING FOR TIME, MATERIALS,AND EQUIPMENT
SUBCONTRACTOR Unit Qty Rate Total
Horizontal Directional Drilling 4"Sch. 80
1) PVC conduit LS 1.00 16,965.27 16,965.27
Sub-total Subcontractor: $ 16,965.27
Prime Contractor Markup(5%): $ 848.26
TOTAL SUBCONTRACTOR: $ 17,813.53
GRAND TOTAL: $ 17,813.53
* HUNTINGTON BEACH ELECTRIC INC
REQUEST FOR INFORMATION 03/11/25
CAUFORNIA REPUBUC
3 .0
NATIONAL CITY,CA
1243 National City blvd 6,„ ,.
National city,ca HUNTENGRIC INC CH
Attn: Josh Johnson
KIMBALL PARK LIGHTING
Upon extensive excavation in the area behind home plate,we have not found any existing 4"conduit as
described and as shown on the project drawings,sheet 2,Note 3.It appears that the cables are directly buried under
the dirt and concrete.
To keep the concrete in tact and minimize disturbance,We recommend approval of a change order to hire
a Horizontal Directional Driller to install a new 4"SCH 80 PVC Conduit from the location of intercept to the
MUSCO Panel.A DIR registered HDD contractor,familiar with this project has supplied an estimate which is
included with this RFI.
(`11-'4ze.. T>. gudep
Eric D. Bridge,PE
Professional Electrical Engineer#E-21037
Huntington Beach Electric C-10#1009482
714-264-9522
www.huntington-beach-electric.com
DEV/CO
• + DEVELOPMENT&ENGINEERING
Proposal/Contract Number:25-0075 Date:03/06/2025
Job Name: Kimball Park Ballfield Lighting Job Address:148 E. 12th St.,National City
Customer Contact:
Huntington Beach Electric
Eric Bridge
17632 Metzler Ln#213, Huntington Beach,CA 92647
714-264-9522
eric(aah u nti ngton-beach-electric.com
PROJECT SCOPE OF WORK:
• Utility Delineation:
o USA Dig Alert:Devco will secure and maintain a valid USA dig alert ticket to attempt to capture all underground utilities that are on the
property(For public utilities only).
o Utility Delineation Private Locator:
Devco will supply a private locator for the private property to attempt to capture all existing utilities that may intersect the directional
bore path.
• Utility Verification via Potholing;
o Potholing Operations:Devco will conduct potholing via 8"core method to confirm the locations of the existing utilities that intersect or
run parallel to the directional bore paths,marked by private locator and USA dig alert.
o Backfilling:After potholing,the potholes will be backfilled with utility sand or a 50/50 mix,compacted,and the 8"cores will be
restored and sealed with concrete sealant as final restoration by Devco.
o Devco will haul and dispose of all pothole mud.
• Excavation and Preparation:
o Bore Pits:Devco will provide labor and equipment necessary to excavate all directional bore pits required for the directional boring
operations.
o Spoils Management:All spoils from the directional bore pits will be stockpiled on the jobsite and used for backfilling.
• Directional Boring:
o Boring Distance:Devco will undertake directional boring at(1)location for approximately 46 LF.
o Devco will supply and assemble roughly 46'of(1)4"BoreGard Schedule 40 PVC conduit for the directional boring operations only.
o Devco will haul and dispose of all directional boring fluid.
• Restoration:
o All bore pits will be backfilled and compacted with native soil,and restored to trench width only.
o All bore pits will be restored to trench width only,and repaved by Devco.
S16.965.27 Lump Sum
dik
143391 Business Park Dr.C-1,Temecula,CA 92590 Ph:(951)221-3633 " www.DeveloomentAndEngineering.com
CSLB#1105687 A&B License DVBE,SB-PW,SB-Micro#2034204 SDVOSB#J3QDZW55B215