PROJECT PROFESSIONALS CORPORATION
CHANGE ORDER MEMORANDUM
April 11,2025
To: Stephen Manganiello,
Director of Engineering&Public Works/City Engineer
Engineering and Public Works Department
City of National City
From: Josh Johnson
Senior Project Manager
Project Professionals Corporation
Project: Las Palmas Pool Modular Buildings
CIP No.: 24-18
Subject: Change Order No. 1
Change Order No. 1 provides for:
Contractor incurred costs associated with the removal of bid line items 9, 10, 11 and 12 from removing Modular
Building E from the scope of work
Bid item 9—Provide designs for the masonry stem wall foundations for modular building E
Bid item 10—Provide,deliver,install and commission Modular building E
Bid Item 11—Coordinate, permit and certify all utilities necessary for modular building E
Bid item 12—Coordinate and certify installation of all stem wall foundations for modular buildings E
Payment for this change order was determined by force account.
Supporting Information:
The Las Palmas Pool Modular Building contract was initially awarded with Modular Building E included in the
scope of work. However,this component was subsequently removed from the project when the splash pad
portion of the Las Palmas Park Improvements was not awarded due to budget constraints.At the time of this
change,the modular building contractor had already incurred costs related to the design of both the modular
structure and its associated footings.These completed designs have been retained by the City for potential
future use.
Time Adjustment:
Zero(0)working days are to be added to the contract.
Cost Adjustment:
The additional cost for this change in the scope of work has been agreed upon at a lump sum price of$12,038.75.
The pay method and amount have been reviewed by the Project Manager and are considered fair and reasonable.The
supporting documentation is on file with the project records.iN""` Josh Johnson, PPC 4/15/25
rojeManager Date
�- CALIFORNIA ^�
NA IONAL CIT
mcoapoRATE
LAS PALMAS POOL MODULAR BUILDINGS CHANGE ORDER NO.1
CIP NO.24-18 April 11,2025
Contractor: Blok Modular Constructors,Inc.
404 N.2nd Avenue Ste C
Upland,CA 91786
This Change Order modifies Contractor's and the City's obligations and rights under the abovementioned
contract. This change order is not effective until approved by the City.
Time adjustment:
Zero(0)working days are be added to the contract.
Cost of Change Order:
The City and the Contractor agree that the Contractor incurred costs associated with the removal of bid
line items 9, 10, 11 and 12 from removing Modular Building E from the scope of work.The total amount
for all labor,material,equipment and all other associated work is$12,038.75.
Recommended by Project Manager: /bosh Johnson, PPC Date: 4/15/25
By signing this Change Order the Contractor confirms that he/she is completely familiar with and has fairly
negotiated its price,terms and conditions. If this Change Order is approved,Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit,etc. and that there will be no further compensation. All of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is
authorized to bind the Contractor to this Change Order.
u6 rM sated M Fred Renton
Agreed and Accepted by Contractor: DN:G.US,EAred.denernQObbrgdmm,
Fred Rienton ea �,m k Mwdlarcane ..CR red Date:
(Print Name and Title) F °
--_-_2025.04.15u:aaoo7oa
Approved by Project Coordinator: a K`"' Date:
Approved by Assistant Director of E&PW:1 q o tf i z (` r�Q�y Date:
.)%
Approved by City Engineer: ? Jl' 'S Date:
Approved by City Manager: Date:
(Required for change orders$25,000 and above)
CALIFORNIA
�a�I°NAL CITY
o o J
INCORPORATED
LAS PALMAS POOL MODULAR BUILDINGS CHANGE ORDER NO. 1
CIP NO. 24-18
DATE: April 11,2025
WORK PERFORMED BY: Blok Modular Constructors,Inc.
DESCRIPTION OF WORK: Removal of Building Efrom Contract
ACCOUNTING FOR TIME, MATERIALS,AND EQUIPMENT
Unit Qty Wage Total
1) Modular Building "E" Foundation Design LS 1.00 2,500.00 2,500.00
2) Modular Building"E" Design LS 1.00 5,000.00 5,000.00
Sub-Total: $ 7,500.00
Markup(20%): $ 1,500.00
TOTAL: $ 9,000.00
Bond for$110,500 at 2.75% $ 3,038.75
GRAND TOTAL: $ 12,038.75
Acumen Engineering Design LLC
12008 N 144th Ave
Surprise,AZ 85379 USA
+18015719877
athena@acumenaz.com
IN`vv�CE 40062
Blok Modular Constructors,Inc DATE 02/04/2025
Blok Modular Constructors,Inc. TERMS Net 30
404 N 2nd Ave Suite C
Upland CA 91786
MOD0044 Fred Rienton 241210
Design Design Engineering 12.50 200.00 2,500.00
Engineering
Generate Concrete stemwall
Design (above grade)for(1) 10x24
modular building.
Provide electronic 75% plans.
Project: Las Palmas Pool
SUBTOTAL 2,500.00
TAX 0.00
TOTAL 2,500.00
BALANCE DI F $2,500.00
1cr.
5301 W. Madison St. Invoice
PHOENIX Phoenix, AZ 85043
(602) 447-6460 Date Invoice#
MODULARPhone:Fax: (602) 447-6477 01/10/25 PMI-6542 1
WWW.PHOENIXMODULAR.COM
Bill/Ship To: Bill/Ship To:
BLOK MODULAR CONSTRUCTORS, INC. BLOK MODULAR CONSTRUCTORS, INC.
404 N. 2ND AVE, SUITE C 404 N. 2ND AVE, SUITE C
UPLAND, CA 91786 UPLAND, CA 91786
P.O. NUMBER TERMS REP SHIP VIA F.O.B.
MOD0044-002 REC JK YOUR TRUCK OUR PLANT
Quantity Item Code Description Price Amount
1 CUSTOM PMI-6542-1024 $ 5,000.00 $ 5,000.00
10X24 OFFICE UNIT E
RELEASE OF PROJECT DESIGN/
ENGINEERING
Thank You for Your Business! NET INVOICE: $ 5,000.00
FREIGHT: $ -
SALES TAX: $ -
TOTAL: $ 5,000.00