HomeMy WebLinkAboutProject Professionals Corporation - Las Palmas Pool Modular Buildings - CIP No. 24-18 - Change Order No. 3 - 2025 P P C
PROJECT PROFESSIONALS CORPORATION
CHANGE ORDER MEMORANDUM
June 16,2025
To: Stephen Manganiello,
Director of Engineering&Public Works/City Engineer
Engineering and Public Works Department
City of National City
From: Josh Johnson
Senior Project Manager
Project Professionals Corporation
Project: Las Palmas Pool Modular Buildings
CIP No.: 24-18
Subject: Change Order No.3
Change Order No.3 provides for:
Proceeding with the approved modifications to the snack shack,including but not limited to,extending the
counterspace and replacing the existing larger windows with smaller window units.
Payment for this change order was determined by force account.
Supporting Information:
During the modular building submittal review process,the above items were identified as necessary
enhancements to the snack shack ensure the delivery of a fully functional and complete product suitable for
its intended use.
Time Adjustment:
Zero(0)working days are to be added to the contract.
Cost Adjustment:
The additional cost for this change in the scope of work has been agreed upon at a lump sum price of$557.77.
The pay method and amount have been reviewed by the Project Manager and are considered fair and reasonable.The
supporting documentation is on file with the project records.
ii""'Josh Johnson, PPC 6/17/25
P oject anager Date
CALIFORNIA --
NATIONAL CL y
J; 1
tNCO tponATE.D1
LAS PALMAS POOL MODULAR BUILDINGS CHANGE ORDER NO.3
CIP NO.24-18 June 16,2025
Contractor: Blok Modular Constructors,Inc.
404 N. 2nd Avenue Ste C
Upland,CA 91786
This Change Order modifies Contractor's and the City's obligations and rights under the abovementioned
contract. This change order is not effective until approved by the City.
Time adjustment:
Zero(0)working days are be added to the contract.
Cost of Change Order:
The City and the Contractor agree that the Contractor shall proceed with the approved modifications to
the snack shack,including but not limited to,extending the counterspace and replacing the existing
larger windows with smaller window units.The total amount for all labor,material,equipment and all
other associated work is$557.77.
Recommended by Project Manager: G os Johnson, PPC Date: 6/17/25
By signing this Change Order the Contract r confirms that he/she is completely familiar with and has fairly
negotiated its price,terms and conditions.tf this Change Order is approved,Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit,etc. and that there will be no further compensation. All of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is
authorized to bind the Contractor to this Change Order.
Agreed and Accepted by Contractor: ar+a sired w Fed w
ca Fred Rienton,�..,��°""'°"°"°".c Date:
(Print Name and Title °'B1pMMNpd'"`""nidai1G'°"'�e0
Approved by Project Coordinator: e;e„ � Date:
Approved by Assistant Director of E&PW: r Date:V
•
Approved by City Engineer: 7 Date:
Approved by City Manager: I
Date:
(Required for change orders$25,000 and above)
•
Prime Contract Change Order (CO)
Project Information Prime Contract Change Order
Project# MOD0044 Contract# MOD0044-001
Title 8 Las Palmas Pool Modular Buildings Project,CIP 24 CO# MOD0044-005
Address 1800 E 22nd St Issue Date 20-May-2025
Subject Casework extension and Window size change
City,State,Zip National City,CA 91950
Country
Owner/Customer Prime Contract Company
Contact Josh Johnson Contact Fred Rienton
Company City of National City Company Blok Modular Constructors,Inc
Address 1243 National City Blvd. Address 404 N 2nd Ave
Ste C
City,State,Zip National City,CA 91950 City,State,Zip Upland,CA 91786-4793
Country Country United States
Phone 619.336.4360 Phone
Fax Fax
You are directed to make the following changes to this Contract:
All other terms and conditions of the Contract Documents shall remain in effect.
Original Contract Price $713.000.00
Net change by previous Change Orders $33,131.04
Contract Amount Prior to this Change $746,131.04
Amount of this Change Order $557.77
Revised Contract Amount,induding this Change Order $746,688.81
The Contract time due to this Change Order is to be determined at a later date.
Response:❑ Accept❑ Do Not Accept
City of National City Blok Modular Constructors,Inc
Company Company
By Date By Date
Page 1 of 2
•
•
Prime Contract Change Order (CO)
Pro.osed Items
Item# Item Description Quantity Unit Unit Price Total Price
1 ADD LAMINATE BASE CABINET&EXTEND SOLID SURFACE 1 Lump 1,428.00 1,428.00
COUNTER(APPROX 30")LEAVING 35-1/2"FOR FUTURE FRIDGE sum
(FRIDGE NOT PROVIDED).RELOCATE EXISTING RECEPTACLES
AND VALVE BOX TO ACCOMMODATE NEW LAYOUT.
2 REPLACE(1)4030&(1)4040 WITH 3010 WINDOWS(FIXED DUAL -1 Lump 982.00 -982.00
GLAZED CLEAR LOW E With BLACK VINYL FRAME).HEADERS AT 90" sum
AFF.
3 Sales Tax 8.75% 0.0875 Perce 446.00 39.02
ntage
4 Mark up 15% 0.15 Perce 485.03 72.75
ntage
Subtotal=$557.77
Tax=$0.00
Total=$557.77
Page 2 of 2