CHANGE ORDER MEMORANDUM
August 29,2025
To: Stephen Manganiello,
Director of Engineering&Public Works/City Engineer
Engineering and Public Works Department
City of National City
From: Josh Johnson
Senior Project Manager
Project Professionals Corporation
Project: Las Palmas Pool Modular Buildings
CIP No.: 24-18
Subject: Change Order No.4
Change Order No.4 provides for:
Proceeding with an additional inspection and inspection report for the second foundation concrete pour involving
the stem wall portion rebar and embed plates.
Payment for this change order was determined by agreed upon lump sum.
Supporting Information:
The project was initially bid with a concrete masonry unit(CMU)stem wall foundation which only required
one concrete/rebar inspection before stacking the CMU blocks.With the project approved foundation being
a full concrete stem wall this required two concrete/rebar inspections.One for the footing of the stem wall
and one for the stem wall.
Time Adjustment:
Zero(0)working days are to be added to the contract.
Cost Adjustment:
The additional cost for this change in the scope of work has been agreed upon at a lump sum price of 2,000.00.
The pay method and amount have been reviewed by the Project Manager and are considered fair and reasonable.The
supporting documentation is on file with the project records.
os Johnson, PPC 9/8/25
Pr jest Hager Date
+9-- CALIFORNIA --
ALTI ONAL CITAP
O ORA
INCORPORATIlro
LAS PALMAS POOL MODULAR BUILDINGS CHANGE ORDER NO.4
CIP NO.24-18 August 29.2025
Contractor: Blok Modular Constructors,Inc.
404 N.2nd Avenue Ste C
Upland,CA 91786
This Change Order modifies Contractor's and the City's obligations and rights under the abovementioned
contract. This change order is not effective until approved by the City.
Time adjustment:
Zero(0)working days are be added to the contract.
Cost of Change Order:
The City and the Contractor agree that the Contractor shall proceed with providing an additional
inspection and inspection report for the second foundation concrete pour involving the stem wall
portion rebar and embed plates.The total amount for all labor,material,equipment and all other
associated work is$2,000.00.
_Recommended by Project Manager: Johnson, PPC Date: 9/8/25
By signing this Change Order the Contract confirms that he/she is completely familiar with and has fairly
negotiated its price,terms and conditions.If this Change Order is approved,Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit,etc. and that there will be no further compensation. All of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is
authorized to bind the Contractor to this Change Order.
,,.,ry spied by Fred Renton
Agreed and Accepted byContractor: DN.,:.us.
( 8 P Fred Rienton �'",deepp�,.da'Vc.pge,aa-•Date: —
Print Name and Title) bd na Canmuctvs nc.,cr,—Rem
^..etc.2025.09.0215:17:45-071V
Approved by Project Coordinator: /g6/w.44, Date:
Approved by Assistant Director of E&PW!ill Date:
Approved by City Engineer: ,,,r6".- 2 Date:
Approved by City Manager: Date:
(Required for change orders$25,000 and above)
CALIFORNIA -
NATI.oAL ciTir
rNCa p V ED
LAS PALMAS POOL MODULAR BUILDINGS CHANGE ORDER NO. 4
OP NO. 24-18
DATE: August 29,2025
WORK PERFORMED BY: Blok Modular Constructors,Inc.
DESCRIPTION OF WORK: Additional inspection and report
ACCOUNTING FOR TIME,MATERIALS,AND EQUIPMENT
Unit Qty Wage Total
1) Site visit,Inspection and report HR 8.00 200.00 1,600.00
2) Round trip flight/car/parking LS 1.00 400.00 400.00
Sub-Total: $ 2,000.00
TOTAL: $ 2,000.00
GRAND TOTAL: $ 2,000.00