HomeMy WebLinkAboutProject Professionals Corporation - Strom Water Pump Station Enhancements - CIP No. 25-11 - Change Order No. 1 - 2026 P P C
PROJECT PROFESSIONALS CORPORATION
CHANGE ORDER MEMORANDUM
March 11,2026
To: Stephen Manganiello,TE
Director of Engineering&Public Works/City Engineer
Engineering and Public Works Department
City of National City
From: Josh Johnson
Principal Construction Manager
Project Professionals Corporation
Project: Storm Water Pump Station Enhancements
CIP No.: 25-11
Subject: Change Order No. 1
Change Order No.1 provides for:
Procuring an upsized 200 amp meter pedestal with an integrated distribution section supporting up to 24 circuits
with a shorter lead time.
Supporting Information:
The plans do not call out for any additional distribution but the lead time on this piece of gear is half the time as
the gear shown on the plans. Lead time for the specified equipment came in as 8-10 weeks vs 16-20 weeks.
Time Adjustment:
Zero(0)Working Days added to the contract.
Cost Adjustment:
The additional cost for this change in the scope of work has been agreed upon at a lump sum price of$5,430.60.
The pay method and amount have been reviewed by the Project Manager and are considered fair and reasonable.The
supporting documentation is on file with the project records.
os iJohnson, PPC 3/12/36
rojec anager Date
-4- CALIFORNIA —
NATIONAL CITY
INCORPORATED
Storm Water Pump Station Enhancements CHANGE ORDER NO. 1
CIP NO. 25-11 March 11,2026
Contractor: A.Vidovich Construction, Inc.
15786 Miss Ellie Ln.
Lakeside, California 92040
This Change Order modifies Contractor's and the City's obligations and rights under the abovementioned
contract. This change order is not effective until approved by the City.
Time adiustment:
Zero(0)working days are added to contract time due to unforeseen delays for the delivery of traffic
signal materials and equipment.
Cost of Change Order:
The City and the Contractor agree that the Contractor shall proceed with procuring an upsized 200 amp
electrical pedestal that has distribution section for up to 24 circuits.The scope includes the cost
difference from the bid electrical pedestal to the upsized electrical pedestal to obtain a decreased lead
time.The total amount for all associated work is$5,430.60.
Recommended by Project Manager: ?, Josh Johnson, PPC Date: 3/12/26
By signing this Change Order the Contractor confirms that he/she is completely familiar with and has fairly
negotiated its price,terms and conditions. If this Change Order is approved, Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is
authorized to bind the Contractor to this Change Order.
Agreed and Accepted by Contractor: Date:
(Print Name and Title) SMT STEFANIE TORRES-OFFICE MANAGER 03/12/2026
Approved by Project Coordinator: Gas�,li ga,.;,144545. Date:
Approved by Assistant Director of E&PW: Date:
Approved by City Engineer: ....1,a, 7 Date:
Approved by City Manager: �✓
Date:
(Required for change orders$25,000 and above)
*)-- CALIFORNIA
NATIONAL Crry
C\—tNC�1vV ED
Storm Water Pump Station Enchancements CHANGE ORDER NO. 1
CIP NO. 25-11
DATE: March 11,2026
WORK PERFORMED BY: Mackaig Electric
DESCRIPTION OF WORK: Electrical Gear Upsizingto Reduce Lead Time
ACCOUNTING FOR TIME, MATERIALS,AND EQUIPMENT
MATERIALS Unit Qty Rate Total
200 amp meter pedestal(price difference
1) from bid to upsized unit) Ea 1.00 5,172.00 5,172.00
Sub-Total Materials: $ 5,172.00
TOTAL MATERIALS: $ 5,172.00
Subcontractor Markup(5%): $ 258.60
GRAND TOTAL: $ 5,430.60
QUOTATION PAGE
CED-SANTEE 001 OF 001
CED QUOTE# DATE REV# REV DATE
8406 MAGNOLIA AVE.N.STE.H 1084511 02/25/26 001 03/11/26
SANTEE CA 92071 QUOTE EXPIRES PREPARED BY
TEL:619 562-3004 FAX: - 02/26/2026 EG
CONTACT: EDGAR GONZALEZ SLS INSL
6948 0972
FOB FREIGHT
QUOTE FOR: MACKAIG ELECTRIC SHIPPING POINT PREPAID
ACCT#: LA-66650 MACKAIG ELECTRIC
CUS PO#:
527 MILE OF CARS
13207 LAUREL ST JOB NAME:
LAKESIDE, CA 92040 200A 3PH PEDESTAL
TEL:(619)247-7822
EXT
LN QTY MFR CATALOG# DESCRIPTION PRICE UOM AMT
01 * QUOTING WITH AN ESTIMATED LEAD TIME OF 16-20 WEEKS-PER PLAN PEDESTAL
02 1 MYERS MEUGI6X 200A SERVICE 200A 42K 120/240V 3PH, 4,000.00 E 4,000.00
PEDESTAL 6BS11 304 STAINLESS STEEL
03 1 MYERS PLUS S&P TBD 0.00 E .00
04
05 * OPTION 2:8-10 WEEK LEAD TIME,STRONGBOX
06 1 MISC MPS-32018-65 200A,3PH,18CK,65K,SS 8,800.00 E 8,800.00
07 1 MISC MPS BASE MOUNTING BASE 0.00 E .00
08 1 MISC PLUS S&P TBD 0.00 E .00
MDSE: 12,800.00
TAX: 992.00
TOTAL: 13,792.00
4,800 difference
+372(tax)
=5172 Total
PLEASE NOTE:THIS IS NOT AN OFFER TO CONTRACT,BUT MERELY A QUOTATION OF CURRENT PRICES FOR YOUR
CONVENIENCE AND INFORMATION.ORDERS BASED ON THIS QUOTATION ARE SUBJECT TO YOUR ACCEPTANCE OF
THE TERMS AND CONDITIONS LOCATED AT SALES.OUR-TERMS.COM,WHICH WE MAY CHANGE FROM TIME TO TIME
WITHOUT PRIOR NOTICE.WE MAKE NO REPRESENTATION WITH RESPECT TO COMPLIANCE WITH JOB
SPECIFICATIONS.