HomeMy WebLinkAboutInnovative Construction Consulting Services, LLC - MLK Community Center - Change Order No. 15 - CIP No.22-06 - 2024 Innovative Construction Consulting Services, LLC
( c P.O. Box 6211
Norco CA 92860
Phone (951) 532-6483
Lic. # 671810
sgill@iccsinc.net
CHANGE ORDER MEMORANDUM
March 26,2024
To: Luca Zappiello
National City Engineering and Public Works Department
City of National City
From: Sean Gill
Project: MLK Community Center
CIP No.: 22-06
Subject: Change Order No.15
Change Order No. 15 provides for:
The city directed the contractor to install panic hardware on the existing electrical room as requested by the B&S
Department. This work was not shown on the approved plans,however,the B&S Dept.would not provide a final
without the additional panic hardware.
Payment for this change order will be at a lump sum price identified.
Supporting Information:
The original plans and specifications did not call for panic hardware,however,during final inspection the B&S
Dept.stated they wanted panic hardware added to the electrical room door and would not final the project until it
was installed.
Time Adjustment:
1 contract day was added to the contract time to coordinate the work.
Cost Adjustment:
The pay method and amount have been reviewed by ICCS and are considered fair and reasonable.The supporting
documentation is on file with the project records.
3-26-24
Ma age Pro
0 je v Date
cyLt
Lai
C.) N -g
..y
t_s'r cc
r 'x-
0
•
- CALIFORNIA —
NATIONAL CrTy
sii;3'1
INCORPORATED
MLK Community Center CHANGE ORDER NO. 15
OP NO. 22-06 March 26,2024
Contractor: E&H General Contracting
The city directed the contractor to install panic hardware on the existing electrical room as requested by
the B&S Department. This work was not shown on the approved plans, however,the B&S Dept.would
not provide a final without the additional panic hardware. All work will be performed at the lump sum
price listed below. This Change Order modifies Contractor's and the City's obligations and rights under
the above-mentioned contract. This change order is not effective until approved by the City.
Time adjustment:
One (1)working days have been added to contract time to complete the T&M work performed.
Cost of Change Order:
There is a cost increase to the original contract amount. $3,385.91
Recommended by Project Manager:Sean Gill Date: 3/26/24
By signing this Change Order, the Contractor confirms that he/she is completely familiar with and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is
authorized to bind the Contractor to this Change Order.
Agreed and Accepted by Contractor: /
y15,.) _ 3 (ZCv `zc7Zel
(E&H General Contracting) Date: [�//
Approved by Project Coordinator: l�lA Date: 3/.�i/�Z J
Approved by Assistant Director of E—&PW:
WI 1 Date:
�
Approved by City Engineer: �s , Date:
Approved by City Manager: G'
Date:
(Required for change orders$25,003 and above)
E&H General Contracting Inc. PROPOSED
CHANGE ORDER
8402 N. Magnolia Ave. Suite B Phone: (619)486-6553 No. 21
Santee, CA 92071 Fax: (619)486-6897
TITLE: Add SDG&E Door Panic Hardware DATE: 03/21/2024
PROJECT: Kitchen Remodel and Flooring Replacement
JOB: 22-105
TO: Attn: Sean Gill CONTRACT/PO: CIP NO 22-06
ICCS, LLC.
PO Box 6211 SUBMITTED:
Norco, CA. 92860 COMPLETED:
REQUIRED:
DESCRIPTION
This PCO is for the cost to Add Panic Hardware on the existing Electric Room at the MLK Community
Center Bldg. The Scope of work is per the Proposal from San Diego Door Controls, any additional items
required or requested will require an additional CO.
E & H cost includes Contracting with New Contractor, labor required to process documentation and
Certified Payroll.
Num Item Description Ref Qty Unit Unit Price Amount
1 SD Door Controls 1.000 2,480.74 2,480.74
2 E&H General Contracting 1.000 712.00 712.00
Item Total: $3,192.74
E&H Overhead (5%) $159.64
Bond Cost (1%) $33.53
Total: $3,385.91
APPROVAL
By: By:
Date: Date:
gait
'* .I�;- - Estimate
•
ESTIMATE# 1039518549
DATE 03/11/2024
5044-5046 Ruffner Street PO#
San Diego, CA 92111
(619) 722-6475
service@sddoorcontrols.com
CUSTOMER SERVICE LOCATION
ICCS ICCS
1800 East 22nd Street 1800 East 22nd Street
National City CA 91950 National City CA 91950
DESCRIPTION UPDATED-SDGE Door Panic Bar&Trim
Estimate
Description Qty Rate Total
Trip Charge 1.00 110.00 110.00
Hot#: 148356 Marks M9900F Fire Rated Rim Panic 36"Silver(1-2 Week Lead Time) 1.00 864.60 864.60
Hot#: 146626 MARMESC600F/26D Marks Storeroom Full Escutcheon Panic Trim- 1.00 248.00 248.00
Silver
20-001 -1-1/4"SDGE AA84 Mortise Cylinder(1 Week Lead Time) 1.00 135.00 135.00
SDGE AA84 Key Copies 4.00 16.00 64.00
FS-260 ASA Strike Cover Plate 1.00 24.00 24.00
EF-86 86 Edge Cover Plate 1.00 26.00 26.00
(Prevailing Wage)Time and labor to remove existing mortise lock on SDGE door and
install fire rated rim panic to door per customer request. Install new panic bar with
outside full escutcheon trim. Install new SDGE AA84 cylinder compatible with fire exit 4.00 160.00 640.00
trim. Install cover plates to mortise lock prep and ASA strike prep on frame. Make
adjustments to new hardware as needed and test and check door for proper working
operation.
Prevailing Wage Admin Fee 1.00 250.00 250.00
Sales Tax(National City) 8.75% 119.14
CUSTOMER MESSAGE Estimate Total: $2,480.74
Estimates are valid for 60 days. Please note that any
service cancellations must be made 24 hours in
advance, otherwise a minimum service fee will apply.
All payments made with credit cards are subject to a
3% processing fee.
Thank you for your business!