HomeMy WebLinkAboutChange Order No. 3El TOYON SOCCER FIELD Specification #07-01 Contractor: OHNO Construction Co. CHANGE ORDER NO. 3 January 11, 2010 Reason/Purpose for this Change Order: The City received grants from the County of San Diego as well as CDBG funds for the construction of the soccer/football field. The specifications were written such that at the very least the basic field could be constructed within the means of funding. Additive bids A - I were included in the specifications for bidding on items that compliment the field. Funding is such that the City can include the additive bid items A - H as listed below. The City of National City and Contractor agree to the following change to the original Contract: The contractor shall construction the following Additive Bid Items in accordance with the contract documents: A) R& R w/Overlay AC service road with 1 1/2" thick AC - $13,000.00; B) Restore decomposed granite path with 2" minimum thickness DG and install recycled plastic redwood header - $40,890.00; C) Install DG and concrete header adjacent to and south of soccer field - $28,000.00; D) Relocate and paint bleachers - $2,200.00; E) Adjust/install irrigation and sod south of soccer field - $45,686.00; F) Clear, grub, and grade area inside dog runs and install 2" of Decomposed Granite. Install 4" high chain link fence. Install ADA compliant self closing/locking swing gates - $27,171.20; G) Install 4", 2500 psi concrete pads for benches and trash cans. Install City provided benches and trash cans - $3,970.00 and H) Install 48" box tree, (Tipuana) - $11,200.00 for a total of $159,117.20. Totals shown here are estimates. Amounts to be paid shall be per the line items costs bid by the contractor in the original bid documents, (see Attachement "A" for breakdown.) Original Contract Amount Net change by previously authorized Change Orders Subtotal Amount of this change order New contract amount 440,642.00 29,704.23 470,346.23 159,161.20 Working days added: 0 Working days subtracted: Percent change in Contract to date 42.86% 629,507.43 Submitted by: . ,/ S- Cit `` - y• er `�y�/ ]',gyp{ Date DPr....1, • er Date liVr C y Engin- - \ \I 3/ It" Date Ma or Ron Morrison Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. ccepted and agreed to by OHNO Construction: Nacn\: Nt`yC t t rt a t th-th Cf, Ord be directed t Date o e on ra or: you o no agree w, ange er you may o procee is work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. d with th 1243 National City Boulevard, National City, CA 91910 Telephone (619) 336-4380 x1rc,URpOB,itg ? EL TOYON SOCCER FIELD Specification #07-01 Additive Bid "A": V TI CHANGE ORDER #3, Attachment "A" 1 :DESCRIPTION::.. R& R w/Overlay AC service road with 1 1/2" thick AC. :UNITS. SF QTY 5,000 UNr PRICE 2.60 EXTENSI.ON..... $ 13,000.00 TOTAL BID Additive Bid "B": $ 13,000.00 # ' DESCRIPTION UNITS QTY : -UNIT PRICE EXTENSION 1 Restore decomposed granite path with 2" minimum thickness DG SF 33,880 $ 0.55 $ 18,634.00 2 Install recycled plastic redwood header LF 1,550 $ 6.00 $ 9,300.00 TOTAL BID $ 27,934.00 4ve DESCRIPTION UNITS QiY UNIT PRICE EXTENSION 1 Install DG and concrete header adjacent to and south of soccer field LS 1 $ 28,000.00 $ 28,000.00 TOTAL BID $ 28,000.00 rove tsio D : 1 DESCRIPTION. Relocate and paint bleachers Additive Bid "E": UNITS. LS QTY.: 1 UNIT PRICE $ 2,200.00 TOTAL BID EXTENSION $ 2,200.00 $ 2,200.00 DESCRIPTION.. UNITS. QN 'UNIT PRICE EXTENSION` 1 Adjust/install irrigation and sod south of soccer field Additive Bid "P: SF 17,240 $ 2.65 TOTAL BID $ 45,686.00 $ 45,686.00 DESCRIPTION. UNITS QTY :UNIT; -PRICE EXTEN:SION.:`. 1 Clear, grub, grade area inside dog runs and install 2" of Decomposed Granite SF 18,968 $ 0.90 $ 17,071.20 2 Install 4" high chain link fence LF 500 $ 18.00 $ 9,000.00 3 Install ADA compliant self closing/locking swing gates EA 4 $ 275.00 $ 1,100.00 Additive Bid "G": TOTAL BID $ 27,171.20 # DESCRIPTION. ;UNITS QTY UNIT PRICE EXTENSION, 1 Install 4", 2500 psi concrete pads for benches and trash cans SF 500 $ 5.00 $ 2,500.00 2 Install City provided benches and trash cans EA 7 $ 210.00 $ 1,470.00 TOTAL BID $ 3,970.00 hive rsio H : 1 DESCRIPTION: Install 48" box tree, (Tipuana) :UNITS. EA QTY:: 7 UNIT. PRICE $ 1,600.00 TOTAL BID ESTIMATED TOTAL OF ALL ITEMS EXTEN:SIQN....: $ 11,200.00 $ 11,200.00 $ 1S9,161.20 All quantities listed are approximate. Contractor will be paid only for work actually peformed and accepted by the City.