HomeMy WebLinkAboutFinal Contract Balance SheetFINAL CONTRACT BALANCE DATE: February 15, 2011 PROJECT: National City Marina Gateway Streetscape Project, Specification No. 08-16 TO: Koch -Armstrong General Engineering, Inc Mr. Chris Armstrong, President P.O. Box 1190. Lakeside, CA 92040-0906 ORIGINAL CONTRACT AMOUNT: START DATE: COMPLETION DATE: ORIGINAL CONTRACT LENGTH: EXTENTION OF WORK DAYS: TOTAL CONTRACT TIME: $1,916,282.35 December 9, 2009 November 10, 2010 (includes downtime due to multiple change orders, correctional work, clean-up, inspection, and document delays) 120 working days 68 working days 188 working days DESCRIPTION OF CHANGE: This change order is written to balance and finalize the amounts for said project. Please see attached Final Clean-up Change Order No. 27. CONTRACT ADJUSTMENT: As a result of these change orders, the contract price is adjusted as follows: 1. The final contract price to date is adjusted to $1,967,988.85. 2. As a result of the satisfactory completion of said project, a retention amount of $157,420.82 shall be initiated for invoice processing and payment upon the receipt of required signatures and City Council's ratification of this agreement and the Notice of Completion. This document and its purpose to balance payment shall be considered full compensation for furnishing and installing the materials, labor, tools and equipment, profit, overhead, and all incidentals for performing the work described above. Koch -Armstrong General Engineering, Inc. will not be entitled to damages or additional payment for delays as described in the 2009 edition of the Standard Specifications for Public Works Construction, Section 6-6.3, for performing the work as described above. CALIFORNlA - TIO C.ry Ia NCORPORATED MARINA GATEWAY STREETSCAPE Specification #08-16 Contractor: Koch -Armstrong General Engineering, Inc. FINAL CLEAN-UP CHANGE ORDER 11 27 January 7, 2011 Reason/Purpose for this Change Order. This change order summarizes all line item extensions and change order modifications for this project. The City of National City and Contractor agree to the following change to the original Contract: The Contractor and City agree that the quantities listed on Attachment "A" are the final field -confirmed quantities for this project. The Contractor and City agree that Attachment "B" provides accurate calculations for the modified lump sum dollar totals for Change Orders 3, 8, and 10. $ 1,916,282.35 Net change by previously authorized Change Orders......... 51,706.50 Subtotal Amount of this change order New contract amount Working days added: 0 Working days subtracted: 0 Original Contract Amount 1, 967, 988.85 Percent change in Contract to date 2.70% 1,967,988.85 Submitted by: P -Oj Date Date c < ariager I ro A ` yec�i y.: City gineer Date !City Manager, required for Change Orders4$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Accepted and agreed to by Koch -Armstrong General Engineering, Inc.: 44/4 C r Frank Herrera, Project Manager 1-19-Zoil Date Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380 CITY OF NATIONAL CITY MARINA GATEWAY STREETSCAPE Specification 08-16 FINAL CLEAN-UP CHANGE ORDER, Attachment "A" 1/15/11 Original Contract FINAL QUANTITIES Delta No. Item Units Quantity Unit Price Amount Quantity Amount 1 Mobilization LS 1 16,900.00 16,900.00 1.00 16,900.00 - 2 Temporary Erosion Control LS 1 5,700.00 5,700.00 1.00 5,700.00 - 3 Demolition LS 1 154,300.00 154,300.00 1.09 168,336.90 14,036.90 4 Remove Striping LF 600 2.00 1,200.00 600.00 1,200.00 - 5 Tree Removal EA 29 200.00 5,800.00 29.00 5,800.00 - 6 Remove and Dispose of Railroad Flasher Sign. EA 1 1,200.00 1,200.00 1.00 1,200.00 - 7 Removal of Railroad (including rail, ties, and t LF 1000 28.00 28,000.00 1,062.00 29,736.00 1,736.00 8 Railroad Switch Removal and Modification EA 1 1,200.00 1,200.00 1.00 1,200.00 - 9 Base Subqrade for Ballast Removal (2' Depth; YD^3 664 35.00 23,240.00 689.60 24,136.00 896.00 10 Fill Soil for Ballast Removal (3' Depth) YD^3 324 26.00 8,424.00 324.00 8,424.00 - 11 6" Curb & Gutter per G-2 (Type G) LF 950 22.00 20,900.00 1,001.00 22,022.00 1,122.00 12 6" Curb & Gutter per Mod. G-2 (Type G) LF 1160 27.00 31,320.00 1,175.00 31,725.00 405.00 13 6" Curb per G-1 LF 210 16.00 3,360.00 238.00 3,808.00 448.00 14 4" Sidewalk per SDRSD G-7 SF 26792 4.00 107,168.00 26,772.00 107,088.00 (80.00) 15 Curb Ramps per Mod SDRSD G-27 EA 6 1,200.00 7,200.00 6.00 7,200.00 - 16 Curb Ramps per SDRSD G-29 EA 1 1,700.00 1,700.00 2.00 3,400.00 1,700.00 17 Cross -Gutter per National City Std Dwq Mod (SF 3391 5.50 18,650.50 2,699.00 14,844.50 (3,806.00) (3,272.50) (15,289.20) 35,639.55 (736.00) 6,866.40 (193.20) 18 AC Overlay SF 4602 2.50 11,505.00 3,293.00 8,232.50 19 4.5" AC on 6" CTB SF 12657 3.60 45,565.20 8,410.00 30,276.00 20 6.0" AC on 6" CTB SF 16279 4.35 70,813.65 18,176.00 24,472.00 4,360.00 106,453.20 17,440.00 21 4" Concrete (Plaza) SF 4544 4.00 22 Seal Coat SF 14250 0.20 2,850.00 48,582.00 9,716.40 23 Cleveland & 23rd Intersection Pavement (6" E SF 6890 4.60 31,694.00 6,848.00 31,500.80 24 7.5" Porous Concrete (NW Corner of Harrison SF 967 15.00 14,505.00 882.00 13,230.00 (1,275.00) (141,024.00) - 25 Turf Cell Pavers SF 8814 16.00 141,024.00 - - 26 Structural Soil Sections CuFt 1000 5.00 5,000.00 1,000.00 5,000.00 27 Alley Apron SF 445 5.00 2,225.00 451.00 2,255.00 30.00 28 Driveway LF 3769 6.00 22,614.00 4,908.00 29,448.00 6,834.00 29 Metal Beam Guard Rail LF 70 69.00 4,830.00 78.00 5,382.00 552.00 30 Street Lights (includes Conduit, Wiring, Meter EA 27 5,600.00 151,200.00 27.00 151,200.00 - 31 Street Name Sign, per SDM-102 EA 7 320.00 2,240.00 - - (2,240.00) - 32 8" CL 235 PVC Water Main LF 674 63.00 42,462.00 674.00 42,462.00 33 8" CL 200 PVC Fire Service w/ Valve (1-27', 2 EA 3 4,080.00 12,240.00 3.00 12,240.00 - 34 6" Fire Service w/ Valve (32') EA 1 2,700.00 2,700.00 1.00 2,700.00 - 35 2" Copper Water (Laterals) EA 5 3,200.00 16,000.00 5.00 16,000.00 - 36 1" Copper Service Water EA 2 2,400.00 4,800.00 2.00 4,800.00 - 37 6" PVC Sewer (Laterals) LF 130 47.00 6,110.00 130.00 6,110.00 - 38 3/4" Gas Pipe LF • 14 116.00 1,624.00 - - (1,624.00) (3,250.00) - 39 1" Gas Pipe LF 65 50.00 3,250.00 - - 40 18" Steel Casing LF 41 106.00 4,346.00 41.00 4,346.00 41 8" Steel Casing LF 100 32.00 3,200.00 - - (3,200.00) - 42 8" Valves EA 6 2,100.00 12,600.00 6.00 12,600.00 43 Fire Hydrant Assembly EA 1 6,000.00 6,000.00 1.00 6,000.00 - 44 Relocate Fire Hydrant Assembly EA 1 5,000.00 5,000.00 1.00 5,000.00 - 45 Remove & Relocate Street Sign EA 11 160.00 1,760.00 11.00 1,760.00 - 46 Remove & Relocate Depot Parking Sign EA 1 200.00 200.00 1.00 200.00 - 47 Traffic Sign EA 8 200.00 1,600.00 10.00 2,000.00 400.00 48 Remove & Salvage Street Signs EA 14 30.00 420.00 8.00 240.00 (180.00) 49 Street Striping (0-4000) LF 2057 1.50 3,085.50 2,057.00 3,085.50 - 50 Pavement Markers EA 76 7.00 532.00 76.00 532.00 - 51 Thermoplastic with Glass Beads SF 260 4.00 1,040.00 260.00 1,040.00 - 52 Blue Pavement Marker EA 2 100.00 200.00 2.00 200.00 - 53 Depot Feature Up -Lighting & All AppurtenancE LS 1 15,800.00 15,800.00 1.00 15,800.00 - 54 Vehicular Sliding Gate & All Appurtenances In LS 1 21,000.00 21,000.00 1.00 21,000.00 - 55 Concrete Mowcurb (SDRSD # L-4) LF 300 15.00 4,500.00 250.00 3,750.00 (750.00) - 56 Stone Pilasters EA 3 2,500.00 7,500.00 3.00 7,500.00 57 Mailbox w/ Post EA 1 800.00 800.00 1.00 800.00 - 58 Steel Fencing LF 320 66.00 21,120.00 317.00 20,922.00 2,000.00 (198.00) - 59 Single Swing Access Gate EA 1 2,000.00 2,000.00 1.00 60 Double Swing Access Gate EA 3 4,000.00 12,000.00 3.00 12,000.00 - 61 Boardwalk sr 3922 zwzm 94,128.00 62mmmwalk Cross Over LS z 5,e00.00 5'500.00 1z0 5,500.00 uxos Paving at Tree Pits sr zmo /.so 4.050.00 2,391-00 3.586.50 w63.50) v^os Paving atDepot Display Yard sr zzuuo 3.40 174,392.00 20,532.00 69,808.80 *o.000.00 w583.20> oo Cast Iron Tree Grates e^ o 5,000.00 45'000.00 9.00 ao Tree o»nnmmo(including Conduit, Wiring mpsx or sz».00 49'76/.00 96.00 *9.2*8.00 m13.00` ar Barrier Protection Per soomsStd. 3481./ Ls z 5'240.00 s'z*o.00 1.00 5.2*0.00 ao Water Quality Planter Box (Cleveland Avenue' Ls / z'000.00 z'000.00 m Gravel Water Quality Feature Ls / »'000.00 »'000.00 1.00 3.000.00 m Misc. Utility Removal mAbandonment Ls / 6,000.00 o'000.00 1.00 6,000.00 n Adjust Existing Underground Dry Utility munt Ls z 30.00 »ouo 1.00 xo.00 72 Landscape mIrrigation Ls z »zz'000.00 »/z'000.00 0.91 28*.925.10 rx Temporary Traffic Control Ls / 17,000.00 o'000.00 1.00 17.000.00 r* Conduit mWiring for Existing Pylon Depot u«l Ls / z'000.00 z'000 oo 1.00 2.000.00 ro Install Bench Mark per soxsom'// EA z z'000.00 z'000.00 2.00 2.000.00 ro Remove Existing zo^vcpSewer Main and xe�u^ uzs 60.00 r».soo.00 865.00 51,900.00 6,300.00 (21.600.00) rr Remove m^vcpSewer Main and Replace wit u` zoo o».00 o'mo.00 100.00 m Remove mReplace Existing w*#uou s^ / s'000.00 s'000.00 1.00 5.000.00 m Remove mReplace Existing m* #uor s« / s'000.00 s'000.00 1.00 5,000.00 oo Remove mReplace Existing m*#uoo s^ / s'000.00 s'000.00 1.00 5,000.00 o, Remove uReplace Existing m* °oos sx z s'^oo.00 5'000.00 ,.^o v»^n.on o2 Remove mReplace Existing w*#yz7 s^ / s'000.00 s'000.00 1.00 5,000.00 oo Cut mzz^xzz^xu^Tee Connection ooBay rs^ z s'000.00 s'000.00 1.00 5,000.00 o*zz^ Butterfly Valve e^ z ».yzs.00 r'uso.00 2.00 7,850.00 oo Wet Tap atState o+o».00z»mStreet s^ / z'000.00 z'000.00 1.00 1.000.00 oo Steel Casing u^ »s »z.so 1,137.50 11.50 373.75 mm.ro> nmmternativ umPoumusConcrete SF 8814 18.00 158,652.00 8,623.00 155,214.00 (3,438.00) 48A Additional Striping LS z /,000.00 1,000.00 1.00 1,000.00 Change Orders 1 Relocate Chain Link Fence Ls z 3,785.67 3,785.67 1z0 3,785.6 2 Wet Tap Night Work LS z 4,740.75 4,740.75 1.00 4,740.75 o Concrete Header Ls z »r'r»r.00 »r'r»r.00 1/0 **212.85 8,475.85 * Remove/Dispose mRCP Pipe Ls z 6,545.57 o'pm.sr 1/0 6.545.57 onaoordo"s materials/remove concrete Ls / r'ouo.or r'ouo.or 1.00 7,980.07 o Abandon Septic Tank Ls z 934.95 934.95 1-00 vx*-oo r Delete Boardwalk, Replace Sidewalk Ls / (78'440.00) (78.440.00) oor/ete Acid Etch Ls z (11.978.46) (1/'978.46) 1.01 (12.141.*8) nox.on vsoos Conduit Repair Ls / o./oo.so 6,/06s6 1/0 6.106.56 m Replace crowith cmo Ls / (/3'248.46) (/3,248.46) 0.81 (10.747.44) e/01ue 11 Concrete Boardwalk Crossover Ls / o*c@Railroad Tracks LS / 9,237.80 9,237.80 1z0 9,237.80 mm&x»c@ East Side mCleveland* Ls z z»'oss.*o 23'653.40 ° woelav Sewer Pump Turn ons Ls z /4'919.98 »*'o/y.yx 1/0 14,919.98 15 Water/Fire Services Re-route Ls z /4,169.94 14,169.** //m 14,/69.9* 16 Delay Sewer Main Delay for Gas Ls z m'zwo.yo 18'249.99 1.00 18.2*9.99 /rxmx Permeable °yo^pcc Ls / 2'940.60 z'o*o.00 1.00 2.9*0.60 18 Credits: Laousqvmn~ us / (»o'rru.00) (so'rru.00) � 19 Replace Unsuitable Material ,/cmo Ls z 2'7/6.94 2'7/6.94 1.00 2.716a* eo Demo and dispose o,wall Ls / z'soz.m 1.592.43 1u0 1.592.*3 z, Demo and dispose orcMowall Ls / /'zoo.uo /.zoa.uo 1.00 1.206.89 o Induction Lights Ls z 2'462.79 2'462.79 1.00 2.*62.79 23 Water Quality Planter Box Ls z /5.946.55 /5'946.55 1.00 15,946.55 2* Delete Line Item #ou* Ls / (z.000.00) (z.000.00) ~ 2o Asphalt Improvements (Mso Ls z 14'5/6.69 14'5/6.69 1.00 14,516.69 eowmee/stopo Ls / z'ez.ro /'oozro 1.00 1.692.79 CAL{F.ORNIA NATIOTWA CITT mcpgppgATED MARINA GATEWAY STREETSCAPE FINAL CLEAN-UP CHANGE ORDER, Attachment "B" Specification #08-16 Change Order 3 Unit 7.5"x 12" reinforced concrete header LF Estimated Quantity Actual Quantity I Difference Unit Price Price Difference 1260 1543 283 29.95 $ 8,475.85 Original Total: $ 37,737.00 Difference: $ 8,475.85 Modified Total: $ 46,212.85 Explanation: Pursuant to Change Order #3, the Contractor was to install a 7.5" x 12" concrete header abutting porous concrete sections found in the original contract to ensure the stability of these sections. The City and Contractor negotiated a lump sum price of $37,730.00 based on an estimated 1260 LF at $29.95/LF. The contractor actually installed 1543 LF of concrete header, resulting in an additional $8,475.85 due the contractor for work performed. Change Order 8 Unit Acid Etch SF Estimated Quantity Actual Quantity Difference Unit Price Price Difference 30714 31132 418 0.39 $ 163.02 Original Total: $ 11,978.46 Difference: $ 163.02 Modified Total: $ 12,141.48 Explanation: Pursuant to Change Order #8, the Contractor was to provide a credit to the City for the removal of acid etch for all 4" sections of concrete (Line Items 14 and 21). The credit was based on the estimated square feet of 4" concrete (30,714) at a rate of .39/sq ft, resulting in an estimated credit of $11,978.46. The actual number of square feet of 4" concrete installed was 31,112 which increased the credit to the City by $163.02, resulting in a total credit of $12,141.48. Change Order 10 Replace CTB with CMB Unit Estimated Quantity TON 1247.5 Actual Quantity Difference I Unit Price Price Difference 1012 -235.5 10.62 $ (2,501.02) Original Total: $ Difference: $ Modified Total: $ Explanation: Pursuant to Change Order #10, the Contractor was to replace the installation of CTB in Line Items 19, 20, and 23 with CMB for each of those line items. The credit was based on the estimated tonnage of CTB required (1,247.5) at unit price of $10.62 per ton. This resulted in an estimated $13,248.46 credit to the City. The actual number of tons placed was 1,012 which decreased the credit owed to the City by $2,501.02, resulting in a total credit of $10,747.44. 13, 248.46 (2,501.02) 10,747.44