HomeMy WebLinkAboutExplanationEXPLANATION: On October 19, 2010 a contract was awarded to Koch Armstrong General Engineering, Inc. by resolution No. 2010-236 for the total construction cost of $90,993.60 (Base Bid) to perform the City's Drainage Improvements project for the FY 2010-2011. The project included the removal and replacement of concrete curbs, cross gutters and pedestrian ramps, installation of new curbs, gutters and alley aprons to alleviate drainage problems at various locations in National City. A final inspection was conducted and completed work was found to be in accordance with the approved construction documents. On February 7, 2011 the Contractor submitted the final closing documents for project acceptance. It is recommended that the work be accepted in the total final contract amount of $75,684.62. The purpose of the attached final contract balance report is to finalize the contract quantities and construction completion time. With the total final cost, the construction was completed under the original contract amount by $15,308.98.