HomeMy WebLinkAboutExplanation (2)EXPLANATION
Per Resolution No. 2011-09, City Council awarded a contract to MJC Construction in the amount of
$242,007.50 for the National City Parks ADA Access Upgrades and Parks Garden Project,
Specification No. 10-05.
During the course of construction, five (5) change orders and line item increases facilitated the
completion of this project as listed on the Final Contract Balance Sheet. Please refer to attached
"Final Contract Balance" document for a breakdown of line items and contracted work days.
A final inspection was completed and closing documentation was submitted to the City for review
and eligibility of a Notice of Completion. Final acceptance of the project was delayed while waiting
for closing documents from the contractor.,After receiving documents, the Notice of Completion was
filed on July 28, 2011.
The work was found to be in accordance with the approved plans and specifications. Therefore,
Engineering Staff recommends the acceptance of the work and ratification of the filing of a Notice of
Completion for the National City Parks ADA Access Upgrades and Parks Garden Project,
Specification No. 10-05 and authorize the release of retention.