FINAL CONTRACT BALANCE
DATE: May 7, 2013
PROJECT: National City Shade Structure for Fire Department Station No. 34
Specification No. 12-11
TO:
Zasueta Contracting Inc.
P O Box 866
Spring Valley, CA 91976
ORIGINAL CONTRACT AMOUNT:
START DATE:
COMPLETION DATE:
ORIGINAL CONTRACT LENGTH:
EXTENTION OF WORK DAYS:
TOTAL CONTRACT TIME:
DESCRIPTION:
$69,714.00
January 22, 2013
April 26, 2013 (includes downtime clue to change
orders, correctional work, clean-up, inspection, and
document delays)
45 working days
0 working days
45 working days
This Final Contract Balance reports final line item amounts and summarizes all changes
to produce a final contract amount. Please see Attachment "A" to this Final Contract
B al ance,
CHANGE ORDERS AND LINE ITEM ADJUSTMENTS:
Change Order No. 1 provided for an additional drop down side to the shade canopy
structure at Fire Department Station No. 34. This change order resulted in an increase to
the contract in the amount of $6,478.00.
There were no line item adjustments for this project.
CONTRACT ADJUSTMENT:
As a result of the above line item deletions:
1. The final contract price is adjusted to $76,192.00.
2. As a result of the satisfactory completion of said project, a retention amount of
$3,809.60 is set for invoice processing and payment upon the receipt of required
FINAL CONTRACT BALANCE
National City Shade Structure for Fire Department Station No. 34
Specification No. 12-11
signatures and City Council's ratification of this agreement and the Notice of
Completion.
This document and its purpose to balance payment shall be considered full compensation
for furnishing and installing the materials, labor, tools and equipment, profit, overhead,
and ail incidentals for performing the work described above. Zasueta Contracting Inc.
will not be entitled to damages or additional payment for delays as described in the 2010
edition of the Standard Specifications for Public Works Construction, Section 6-6.3, for
performing the work as described above.
Page 2
CITY OF NATIONAL CITY
National City Shade Structure for Fire Department Station No. 34
Specification No. 12-11
FINAL CONTRACT BALANCE
. ATTACHMENT "A"
' origlnat Contract
To Date
No. iItem
Unit 'Quantity
Unit Price
Amount
Quantity (Amount
GENERAL ITEMS OF WORK
1 iProvide and Install Shade Structure
LS
1
69,714.00
69,714.00
1.00 1 69,714.00
CHANGE ORDERS
r
1Iinstal additional drop down canopy
_S I 1
6,478.00
6,748.00
1.00 I 6,478.00
TOTALS:
76,462.00