Loading...
HomeMy WebLinkAboutResolutionRESOLUTION NO. 2014 — RESOLUTION OF THE CITY COUNCIL OF THE C1TY OF NATIONAL C1TY INCREASING THE CONTRACT WITH CLAUSS CONSTRUCTION IN THE NOT TO EXCEED AMOUNT OF $845,000 FOR THE 2020 AND 2100 HOOVER AVENUE SITE REMEDIATION AND DEMOLITION PROJECT, SPECIFICATION NO. 13-01, AND AUTHORIZING THE MAYOR TO EXECUTE ANY AND ALL CHANGE ORDERS IN EXCESS OF $50,000 UP TO THE NOT TO EXCEED LIMIT WHEREAS, the Westside Infill— Transit Oriented Development (WI-TOD), also known as the Paradise Creek Affordable Housing Project, is a 201-unit affordable housing development on the east side of Paradise Creek, and the expansion of Paradise Creek Educational Park on the west side of the creek; and WHEREAS, Paradise Creek Housing Partners, LP (the "Developer") and the Community Development Commission ("CDC") entered into a Disposition and Development Agreement titled Transit Oriented Infill Affordable Housing and Paradise Creek Enhancement Project, dated June 21, 2011 ("DDA"). The DDA is an enforceable obligation of the Successor Agency to the Community Development Commission as the National City Redevelopment Agency. Pursuant to the DDA, National City is required to deliver the WI-TOD project site clean and free of contaminants; and WHEREAS, on February 4, 2014, the City Council adopted Resolution No. 2014- 16, awarding a contract in the amount of $858,609 to Clauss Construction for the 2020 and 2100 Hoover Avenue Site Remediation and Demolition Project in order to deliver a clean site for the WI-TOD project, consistent with the DDA. City Council also authorized a 25% contingency for unforeseen conditions; and WHEREAS, in accordance with the PMP, the City's Environmental Consultant, E2 ManageTech, Inc. (E2), conducted site investigations of the WI-TOD site for review and approval by the California Department of Toxic Substances Control (DTSC) both prior to and subsequent to the date of bid and commencement of work under the Remediation Contract. An addendum to the PMP that incorporated the supplemental information obtained from the site investigations was approved by Council on April 1, 2014; and WHEREAS, after approval of the PMP addendum and commencement of work under the contract with Clauss Construction, the DTSC determined that the data obtained from additional site investigations and confirmation sampling of the excavated locations required the City to excavate, characterize, and dispose of additional soils on the eastside of Paradise Creek in order to obtain regulatory closure. Based on testing and characterization of soils recently excavated from the west side of Paradise Creek, additional excavation and disposal will be required to obtain regulatory closure; and WHEREAS, the approved contract amounts, including contingencies, under the current contract with Clauss Construction are insufficient to complete these remaining items of work, which are required to obtain regulatory closure. Since the quantities for specific items of work will exceed the bid quantities by more than twenty-five percent (25%), the Contractor and City are currently re -negotiating lower bid prices for these items as afforded by Section 3-2.2.2 of the Greenbook for Public Works Construction; and Resolution No. 2014 — Page Two WHEREAS, competitive bidding for the additional work described above is not required because the improvements are of the same nature and character as the work performed under the original contract and because bidding would not be in the public interest and would not produce an advantage for the following reasons: • A competitive bidding process for the change order improvements would result in increases in consultant costs and staff time for the City to administer an additional bidding process and manage a new construction contract; • The City and Contractor are negotiating unit prices equal to or lower than those obtained during the prior public bidding process for specific items of work; • A competitive bidding process would result in significant delay and compromise the City's ability to complete the improvements and obtain regulatory compliance in a timely manner in order to turnover the WI-TOD site to the Developer; and WHEREAS, in an effort to continue site remediation efforts in a timely manner in order to obtain regulatory closure of the WI-TOD site prior to turnover of the site to the Developer, the following actions are requested: • an increase to the contract with Clauss Construction in a not to exceed amount of $845,000 (see attached Engineers' Estimate), for a new contract amount, including the original 25% contingency, of $1,918,261.25; • authorize the Mayor to execute any and all change orders in excess of $50,000 up to the not to exceed limit. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of National City hereby approves an increase to the Contract with Clauss Construction in a not to exceed amount of $845,000 (see attached Engineers' Estimate), for a new contract amount, including the original 25% contingency, of $1,918,261.25 for the 2020 and 2100 Hoover Avenue Site Remediation and Demolition Project. BE IT FURTHER RESOLVED that the City Council hereby authorizes the Mayor to execute future change orders in excess of $50,000 associated with, and not to exceed in total, said increase in contract amount. PASSED and ADOPTED this 7th day of October, 2014. Ron Morrison, Mayor ATTEST: APPROVED AS TO FORM: Michael R. Dalla, City Clerk Claudia Gacitua Silva City Attorney /./. _CACIFORNIAczi+- N U5r;&C = iNCORPOpi tral? 2020/2100 HOOVER AVENUE REMEDIATION AND SITE DEMOLITION Specification No. 13-01 Engineer's Estimate September 25, 2014 Item No. DESCRIPTION Projected Costs to Obtain Regulatory Closure AOC 1 1 Remove and dispose of contaminated soils at the previous vehicle lift location and dispose of at Otay Landfill, California (AOC-01), Copper Mountain Landfill, Arizona (AOC-01), and U.S. Ecology Landfill, Nevada (AOC-01). 99,666.50 2 Import, mix, place and compact unclassified fill at the previous lift location 47,740.25 3 Excavation, mix, replace and compact clean overburden at the previous vehicle lift location 13,072.00 AOCs 2, 8 1 Remove and dispose of miscellaneous contaminated soil as directed by the Engineer to Otay Landfill, Chula Vista, CA (AOC 2 & 8), Copper Mountain Landfill, Arizona (AOC 2 & 8), and US Ecology Landfill, Nevada (AOC 2 & 8) 187,500.00 AOC 5 1 Remove and dispose of contaminated soil on the parcel West of Paradise Creek to the Copper Mountain Landfill, Arizona (AOC-05) 418, 600.00 2020 Hoover Avenue 1 Clearing and Grubbing 2020 Hoover Avenue including uknown concrete slab 122,100.00 AOCs 6, 7 1 (Contingency 353,240.00 Projected Cost to Complete: Original Contract Amount: Remaining Costs to Complete: 1,241,918.75 396,844.00 845,074.75