HomeMy WebLinkAbout2002 CON ASSI Security - Change Order #1+ 6 CONTRACT CHANGE ORDER NO. 1 DATE: 12/03/02 ORIGINAL PROJECT: Civic Center and Police Facility Security and Fire System Enhancements, Specification No. 02-6 TO: Mr. William Vuono, President ASSI Security, Inc. 18001 Cowan, Suite A Irvine, CA 92614 DESCRIPTION OF CHANGE: dd work item number 8 (shown below) to the contract. No Item Unit Bid Qty Unit Price Original Contract Amount Adjusted Contract Amount 1. Mobilization LS 1 $2,000.00 $2,000.00 $2,000.00 2. Install Security Access Control System LS 1 $92,000.00 $92,000.00 $92,000.00 3. Install Digital Video Recording System LS 1 $18,000.00 $18,000.00 $18,000.00 4. Install Electrified/Finish Door Hardware LS 1 $22,000.00 $22,000.00 $22,000.00 5. Install Head -End LS 1 $9,000.00 $9,000.00 $9,000.00 6. Install Fire Alarm System LS 1 $85,000.00 $85,000.00 $85,000.00 7. Project Close -Out (Training and Manuals) LS 1 $1,300.00 $1,300.00 $1,300.00 8. Automated ADA Access Hardware (3 existing doors) LS 1 $21,620.00 N/A $21,620.00 Total $229,300.00 $250,920.00 DISCUSSION: Line Item No. 8 is added to the contract at the City's request to provide compensation to the contractor for furnishing and installing three complete ADA Facility Entrance Systems similar to the ADA entrance system on the second floor of the Civic Center from the National City Boulevard pedestrian bridge. The new ADA systems will be installed on each of the existing first floor lobby main doors and on the main entrance doors to finance on the basement level. The three systems will include electrified swing hardware with power supply, entrance and exit touch plates, programmable timers, magnetic locks and all labor and materials required to install the hardware and incorporate the systems into the Security Access Control System. Due to current ADA parking and access from the basement level and building access changes on the first floor level the additional ADA pushbutton access systems were determined to be a necessary portion of the current access control system installation. Page 1 • CONTRACT CHANGE ORDER NO. 1 CONTRACT ADJUSTMENT: As a result of this change order the contract price is adjusted as follows: 1. The contract price is increased in the amount of $21,620.00 from the current contract price of $229,300.00 to a new contract price of $250,920.00. 2. The contract time is increased by five (5) working days. The contract completion date was previously established as Monday, January 13, 2003. The new contract completion date is therefore established as Monday, January 20, 2003. This change order shall be considered full compensation for furnishing and installing the materials, labor, tools and equipment, profit, overhead, and all incidentals for performing the work described above. ASSI Security, Inc. will not be entitled to damages or additional payment for delays as described in the 1997 edition of the Standard Specifications for Public Works Construction, Section 6-6.3, for performing the work as described above. RECOMMENDED FOR APPROVAL BY: Michael J. Long, A soda to ' it Engineer Date APPROVED BY: 6/1z_ Mr. \illiam Vuono, President Date ASSI Security, Inc. Mr. Michael Willey, Vice ASSI Security, Inc. Nick Ihzunz , Mayor Page 2 Date ;/570; Dat City of National City, California COUNCIL AGENDA STATEMENT ,JIEETING DATE December 3, 2002 C�°Zc�p2-3� 7 AGENDA ITEM NO. ITEM TITLE RESOLUTION OF THE CITY COUNCIL OF NATIONAL CITY APPROVING AND" AUTHORIZING THE MAYOR TO SIGN CHANGE ORDER NUMBER ONE FOR THE CIVIC CENTER AND POLICE FACILITY SECURITY AND FIRE SYSTEM ENHANCEMENTS PROJECT PREPARED BY Michael Long DEPARTMENT Public Works/Engineering EXPLANATION Change Order Number One is written to provide compensation to the contractor for the purchase and installation of three automated ADA access hardware systems. Two at the main lobby entrance doors and one at the finance lobby entrance doors. The ADA requires that each building access door that is an element of an accessible route shall be handicap accessible. Proposed parking and sidewalk improvements at the Civic Center will make the front lobby area an accessible route and the finance lobby area is currently an accessible route. Given the need for operational compatibility with the access control system currently being installed, the Public Works department is recommending that the City take the necessary steps to provide current and future handicapped access needs. Change Order Number One will increase the construction bid priceof $229,300.00 by $21,620.00 to an adjusted contract amount of $250,920.00. ( Environmental Review X N/A Financial Statement The adjusted contract total of $25043911 d is within the amouont budgeted for is project in account numbers 500-5-98-8011, 630-409-500-5 09-500-598-8032, and 189-409-5000--598-8032. ' A ount No. STAFF RECOMMENDATIQ Adopt the Resolution approving and authoriz' g the Mayor to sign Change Order No. One BOARD / COMMISSION RECOMMENDATION N/A ATTACHMENTS ( Listed Below ) 1. Resolution 2. Change Order No. 1 Resolution No. 2002-174 A-200 (9,99) security RESOLUTION NO. 2002 - 174 RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY APPROVING CHANGE ORDER NUMBER ONE FOR THE CIVIC CENTER AND POLICE FACILITY SECURITY AND FIRE SYSTEM ENHANCEMENT PROJECT (Engineering Spec. No. 02-6) WHEREAS, on August 6, 2002, the City Council passed Resolution No. 2002-1 1 1, approving a contract between the City and Assi Security, Inc. for the Civic Center and Police Facility Security and Fire System Enhancement Project, Specification No. 02-6; and WHEREAS, Change Order No. One has been purposed to provide for the purchase and installation of three (3) automated ADA access hardware systems for the Project; and WHEREAS, Change Order No. One would increase the contract amount from $229,300 to $250,920, a difference of $21,620. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of National City that the Mayor is hereby authorized to approve Change Order No. 1 for the Civic Center and Police Facility Security and Fire System Enhancement Project, Engineering Spec. No. 02-6. PASSED and ADOPTED this 3`d day of December, 2002. ATTEST: APPROVED AS TO FORM: OP George H. Eiser, III City Attorney Nick Inzuzayor Passed and adopted by the Council of the City of National City, California, on December 3, 2002, by the following vote, to -wit: Ayes: Councilmembers Inzunza, Morrison, Natividad, Parra. Nays: None. Absent: None. Abstain: None. AUTHENTICATED BY: NICK INZUNZA Mayor of the City of National City, California City clerk of the City of National City, California By: Deputy I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of RESOLUTION NO. 2002-174 of the City of National City, California, passed and adopted by the Council of said City on December 3, 2002. City Clerk of the City of National City, California By: Deputy