HomeMy WebLinkAbout2003 CON Carrier Johnson Architects - Consulting New Library Change Order 1DESIGN AGREEMENT CHANGE ORDER NUMBER ONE
DATE: September 29, 2003
PROJECT: National City Municipal Library
TO: Gordon R. Carrier
Carrier Johnson
1301 Third Avenue
San Diego, CA 92101
DESCRIPTION OF CHANGE:
This design agreement change order has two components:
1. The first component of the change order is being written to increase the allowed
Reimbursable Expenses section of the design agreement by $3,030.
2. The second component of the change order is being written to increase the
Contract Documents section of the design agreement by $6,500.
Item
Original Agreement
Amount
Adjusted Agreement
Amount
Design Development
$265,260
$265,260
Contract Documents
$518,988
$525,488
Bidding Services
$18,300
$18,300
Construction Administration
$250,320
$250,320
Reimbursable Expenses
$36,800
$39,830
Total
$1,089,668
$1,099,198
DISCUSSION:
The following is a discussion of each component in the same order as listed above:
1. At the time that the design agreement was negotiated it was not known that the
Department of the State Architect would have to review the documents. It was
believed that since the State Office of Library Construction also had an architect on
staff that would be reviewing the plans, the OLC review would suffice. However
we have since found out that the DSA will be providing an additional review and
that the cost of the review is $3,030. Carrier Johnson has submitted the plans as
required and paid the fee. This component of the change order increases the
Reimbursable Expenses section of the fee agreement to cover these costs.
2. The site has changed since the original topographical survey was prepared for the
project. A Avenue has been realigned which alters the southeast corner of the site.
The property was also used as a construction staging area by a number of
construction companies. Each time a company moved on and off the site they
scraped the site and moved earth around. It appears a couple of the companies may
have actually imported soil and spread it around the site as they left.
The grading of the site for the library is complicated. According to the soils report
eight feet of material under the building, and between two and four feet of material
under the parking lot must be removed and mechanically re -compacted in order to
be suitable for construction. In addition, due to the flood plane, the site must be
filled in order to achieve a satisfactory building pad elevation. Due to the
challenges of the grading and the changes that have occurred in the time since the
originally site survey, it has been determined that re -surveying would be prudent.
Having an accurate survey will ensure that those bidding on the project don't have
to make assumptions and can prepare the best bid possible.
DESIGN AGREEMENT ADJUSTMENT:
As a result of this change order the design agreement is adjusted as follows:
1. The price is increased in the amount of $9,530 from the current contract price of
$1,089,668 to a new contract price of $1,099,198.
2. The time is unchanged. The contract completion date was previously established as
Wednesday, June 1, 2005.
This Change Order shall be considered full compensation for furnishing and installing the
materials, labor, tools and equipment, profit, overhead, and all incidentals for performing
the work as described herein.
APPROVED BY:
CITY OF NATIONAL CITY
By:
Stephen M. Kirkpat
Acting Director of
Works/Engineering
CARRIER JOHNSON
By:
Gordon
Princi
By:
Michael Johnson
Principal
er
CARRIER JOIJNSON
ARCHITECTURE
INTERIOR DESIGN
PLANNING
GORDON R CARRIER AIA
MICHAEL C. JOHNSON AIA
WILLIAM C. BOCKEN AIA
DEBORAH P. ELLIOTT IIDA
FRANK A. WOLDEN
1301 THIRD AVENUE
SAN DIEGO CALIFORNIA
92101
TEL 619 239 2353
FAX 619 239 6227
2600 MICHELSON DR
SUITE 400
IRVINE CALIFORNIA
92612
TEL 949 955 2353
FAX 949 955 2377
www.carrierjohnson.com
G.R. CARRIER ARCHITECT
August 29, 2003
Mr. Stephen M. Kirkpatrick
Assistant Director of Public Works/Engineering
CITY OF NATIONAL CITY
1243 National City Boulevard
National City, CA 91950-4301
RE: National City Public Library — Plan Check Fees
CJ Project No. 4486.00
Dear Steve,
ISSUED VIA 1S1 CLASS MAIL
Per your request on August 26, 2003, we have paid the DSA Plan Check
Application Fee of $3,030.00 on the City's behalf. This permit cost is not a Design
Team responsibility but was paid by Carrier Johnson (to expedite the permit
process) on your direction that our fee would be augmented to cover the cost.
Please raise our reimbursable expense limit from $36,800 to $39,830 to account for
this unforeseen cost. This raises our Contract amount from $1,089,668 to
$1,092,698 as a result. Our expenses to date have been tracking on target with the
exception of this fee cost.
We look forward to receiving a Contract Amendment on this matter and the
completion of Bidding Documents in the near future.
Sincerely,
CARRIER JOHNSON
Kevin L. Krumdieck
Senior Associate, Architect
KLK/ppm
cc: Gordon Carrier
Chuck Lockwood
File 4486.00 / 1.0 & 3.1
P: -4486. 00A CorrespondenceVClien[ALetters V03-0829. Plan -Check -Fees doc
i
ARCHITECTURE
INTERIOR DESIGN
PLANNING
GORDON R. CARRIER AIA
MICHAEL C. IOHNSON AIA
WILLIAM C. BOCKEN AIA
DEBORAH P. ELLIOTT IIDA
FRANK A. WOLDEN
1301 THIRD AVENUE
SAN DIEGO CALIFORNIA
92101
TEL 619 239 2353
FAX 619 239 6227
2600 MICHELSON DR
SUITE 400
IRVINE CALIFORNIA
92612
TEL 949 955 2353
FAX 949 955 2377
3450 SACRAMENTO ST.
6614
SAN FRANCISCO, CA
94118
TEL 415 491 2300
FAX 415 921 6698
www.carrierjohnson, com
CARRIER JO;HNSON
September 26, 2003 (f & &U. (4126(03)
Mr. Stephen Kirkpatrick c)
Assistant Director of Public Works ?'
City of National City, Engineering Department
1243 National City Boulevard
National City, CA 91950
RE: City of National City Public Library
Survey Update Additional Services Proposal
Dear Steve,
This proposal is offered to cover additional design services related to updating the
survey. As noted by JEB, the survey is no longer accurate due to the improvements
along NCB, realignment of A street, and miscellaneous grading/ fencing revisions
interior to the site. These have been shown in a piece meal fashion on the
grading and utilities plans but should be shown in a revised survey as well to avoid
contractor bidding irregularities.
Attached is LMA proposal for your review. The cost is $6,500 which
directly on to you without markup due to our limited involvement in
the work. We also recognize this was not anticipated and are trying
cost exposure. We believe this additional work is valuable to the pro
should be done in this manner.
we will pass
coordinating
to limit your
ject and
Please authorize us to proceed as quickly as you can so the work can
and the results coordinated with our bid package. We will use 4486.
our invoices to you. Call if you have questions.
Sincerely,
CARRIER JOHNSON
Kevin L Krumdieck,
Senior Project Manager
get underway
03 to identify
G.R. CARRIER ARCHITECT
99, 25/ 2003 11: 23
519-290-1515
LINTVEDT MCCOLL ASOC
PAGE 02
LIf1TVED ,, fnkCOLL
8 A 5 5 0 C 1 iA T E 5 PLANNING ■ CIVIL ENGINEERING • LAND SURVEYING
IL am AM I I
September 25, 2003
WO 12189
Mr. Kevin Krumdieck
Carrier Johnson
1301 Third Avenue
San Diego, CA 92101
RE: National City Library
Dear Mr. Krumdieck:
Per your request, we have reviewed the request to provide an updated aerial survey for the
National City Library site resulting from the recent A Ave construction, changes in existing site
conditions and improvement to National City Boulevard.
Our scope and fee for this work is as follows:
Snnpo. of Work
Rse tnpngraphir` mapping
1. Provide a new aerial survey topographic survey in AutoCAD format at a scale of 1"=20'
with one foot contour intervals. The new topographic survey data will replace the
previously compiled aerial in the base sheets containing both boundary information and
existing utilities on site and in the adjacent public street that were plotted from records
provided by the City of National City, SDG&E, Pacific Bell, and the cable TV franchise
utilities and adjusted to match field -surveyed locations of surface features. No boundary
review, additional utility research or potholing of existing utilities has been included in this
scope of work $6,500
Please review our proposal and let me know if you have any questions.
Very truly yours,
ack Dullaghan, P.
Associate Enginee
3737 Camino Del Rio South, Suite 200 .San Diego, CA 92108-4008 n(619) 280.3100 .FAX (619) 280.1515
Fo\WINOATA\JOBS\12189 CarrierJohnson NC Ubrary\P3931 NCUbrary\new Air-fee.doc