HomeMy WebLinkAbout2003 CON HMS Construction - Change OrderTraffic Signal Interconect 30th St and Euclid AveCity of National City
Department of Public Works
1243 National City Blvd., National City, CA 91950
(619) 336-4580 (619) 336-4380 Fax: (619) 336-4397
CHANGE ORDER
NUMBER 001
Page 1 of 2
To: Mr. Jeff Sumner, Project Manager
HMS Construction
1225 Linda Vista Drive
San Marcos, CA 92069
Date: February 7, 2003
Project: 30`h Street and Euclid Avenue Traffic Signal Interconnect
Specification No. 99-14
Description of Change: This change order is prepared to describe the additional work, and to
address the new construction completion time.
Discussion: The original quantities of the items No. 2, 3, 5, and 6 were adjusted
(increased/decreased) based upon the actual work done in the field. The attached contract final
balance highlights these items. The work was incorporated into the contract and paid for at the
pertinent bid unit price.
At the intersection of Plaza Boulevard and Euclid Avenue, the existing fiber optic splice closure
did not accommodate the proposed 36 fiber optic cable, and splices as shown on the construction
plans for the above project. In order to complete the interconnection, the existing closure had to
be removed, and replaced with a larger closure. This required also testing of the existing fiber
optic cable, cutting, and re -splicing of all existing terminations in the new fiber optic splice
closure. This change is included in the attached contract final balance (Item No. 14).
Contract Price Adjustment: As the result of the change of condition, the total contract price was
increased in the amount of $6,506.36 from the original amount at $376,334.00 to a new contract
total price at $382,840.36.
Contract Time Adjustment: The waiting time for the purchase and delivery of the items was 25
working days. Therefore, the project was suspended during waiting period and as a result of the
additional work the contract completion time was extended 15 working days. The contract
completion date was originally established as December 31, 2002. The actual final project
completion date would be April 7, 2003.
1
® Recycled Paper
CHANGE ORDER
NUMBER 001
Page 2 of 2
This change order shall be considered full compensation for furnishing and installing the
materials, labor, tools and equipment, profit, overhead, and incidentals for continuing the
work within time as adjusted above. HMS Construction will not be entitled to damages or
additional payment for delays as described in the 1997 edition of Standard Specifications
for Public Works Construction, Section 6-6.3, for performing the work within the time as
adjusted above. Failure of the Contractor to complete the work within the time allowed
by this change order will result in damages being sustained by the City as specified in the
Subsection 6-9 of the Contract Specifications.
Recommended for Approval by:
Daneshfar, City Project Mana
Dat
-0
r-s ac
Jcff gumnor 1C01.-IIV L) S44A)6- Date
traajg(`ti Mzage-r HMS Cons ction
°� Director o PMy
h lic orks /City Engineer D
Resolution No. 2003-120
Date
September 2, 2003
City of National City Resolution Number Date
2
CONTRACT
FINAL BALANCE
DATE:
DATE: 9/2/03
Page 1 of 2
5/30/03
TRAFFIC SIGNAL INTERCONNECT ON 30TH STREET
& EUCLID AVENUE
SPECIFICATION NO. 99-14
BASE BID
PROJECT
NO. 6543
FINAL INSPECTION
COMPLETION
NO.
ITEM
QNTY
UNIT
UNIT PRICE
ORIGINAL
ACTUAL
ACTUAL
AMOUNT
QUANTITY
AMOUNT
1
Electrical Conduit (2" PVC)
20,000
LF
$9.59
$191,800.00
20,000
$191,800.00
2
Pull Box (No. 6)
42
EA
$450.00
$18,900.00
43
$19,350.00
3
Replace Exist. Pull Box With New (No. 6)
5
EA
$450.00
$2,250.00
4
$1,800.00
4
Splice Vault
2
EA
$1,463.00
$2,926.00
2
$2,926.00
5
Fiber Optic Cable (36-Fiber, Single Mode)
20,000
LF
$2.30
$46,000.00
20,106
$46,243.80
6
Fiber Optic Cable (6-Fiber, Single Mode)
900
LF
$12.40
$11,160.00
1,015
$12,586.00
W/Fan-Out Kit
7
Fiber Optic Modem W/C-2 Cable and Conn.
13
EA
$1,737.00
$22,581.00
13
$22,581.00
8
Fiber Optic Modem (Rack Mounted)
6
EA
$1,812.00
$10,872.00
6
$10,872.00
9
Splice Closure (In No. 6 Pull Box)
13
EA
$706.00
$9,178.00
13
$9,178.00
(With Fusion Splices)
10
Splice Closure (In Splice Vault)
1
EA
$3,024.00
$3,024.00
1
$3,024.00
(With Fusion Splices)
-
11
Splice To Existing Fiber To City Hall
1
LS
$3,670.00
$3,670.00
1
$3,670.00
12
Storm Water Pollution Prevention Control
1
LS
$13,173.00
$13,173.00
1
$13,173.00
13
Construction Traffic Control
1
LS
$40,800.00
$40,800.00
1
$40,800.00
Extra Work
14
New Splice Closure (CO#1)
1
EA
$4,836.56
$4,836.56
1
$4,836.56
Total
$381,170.56
$382,840.36
Page 2 of 2
CONTRACT FINAL BALANCE
TRAFFIC SIGNAL INTERCONNECT ON 30' STREET/EUCLID AVENUE
SPECIFICATION NO.99-14.
FINAL INSPECTION DATE: 5/30/2003
PROJECT NO.: 6543
COMPLETION DATE: 9/2/2003
The final total contract price for the bid to date is $382,840.36.
The total time provided for completion in the contract is changed from 80 working days to 95 working days.
The Contractor accepts this Final Balance as full compensation for the work.
Recommended for Approval by:
aneshfar, City Project Mana
Approve
tTrff .Qi,mnpr, go/0AV* „�e1
•r, HMS Constr{tction, Inc.
V
Stephen M. Kir a`trick
Acting Director o/'Public Works /Engineering
Resolution No. 2003-120
L, 2S DDO'
Date
Date
September 2, 2003
City of National City Resolution Number Date
City of National City, California
COUNCIL AGENDA STATEMENT
September 2, 2003
MEETING DATE
AGENDA ITEM NO.
4
ITEM TITLE RESOLUTION OF THE CITY COUNCIL OF NATIONAL CITY APPROVING THE
CHANGE ORDER NUMBER ONE, ACCEPTING THE WORK AND AUTHORIZING THE FILING OF A
NOTICE OF COMPLETION FOR THE 30'H STREET AND EUCLID AVENUE TRAFFIC SIGNAL
INTERCONNECT PROJECT IN NATIONAL CITY, SPECIFICATION NO. 99-14
PREPARED BY Din Daneshfar DEPARTMENT Public Works/Engineering
336-4387
EXPLANATION
See attached explanation.
X
Environmental Review N/A
Financial Statement The final total construction cost is $382,840.36p
pproved By:
This amount is within the estimated budget for the project. Funding is available through
Account No.313-409-500-598-6543. The amount of the final payment (10% retention) is
be due following the recording of project acceptance.
inalce Director
8,284.04, which will
Account No.
STAFF RECOMMENDATION
Adopt the Resolution.
BOARD / COMMISSIO RECOMMENDATION
N/A
ATTACHMENTS ( Listed Below )
Resolution No. 2003-120
1. Resolution 2. Change Order Number One 3. Contract Final Balance 4. Notice Of Completion
A-200 (9/99)
RE: A RESOLUTION OF THE CITY COUNCIL OF NATIONAL CITY
APPROVING CHANGE ORDER NUMBER ONE, ACCEPTING THE
WORK, AND AUTHORIZING THE FILING OF A NOTICE OF
COMPLETION FOR 30TH STREET AND EUCLID AVENUE TRAFFIC
SIGNAL INTERCONNECT PROJECT, SPECIFICATION NO. 99-14
On July 16, 2002 by Resolution No. 2002-101, the City Council awarded a contract to
HMS Construction, Inc. for the Traffic Signal Interconnect on 30th Street from National
City Boulevard to Euclid Avenue and on Euclid Avenue from 30`h street to the City
Limits, Specification No. 99-14. Based upon the estimated bid quantities, the total bid
cost for the project was $376,334.00.
The project included the interconnection of the existing twelve traffic signals. The
purpose of the signal interconnection was to facilitate the communication between the
existing traffic signal controllers in the field and the traffic computer system at the City
Hall.
During the construction phase, certain bid quantities were adjusted to reflect the actual
installed improvements in the field. As the result of the adjusted quantities, the total
contract amount was increased per each pertinent bid unit price in the amount of
$1,669.80. The progress payments included the revised costs.
At the City's request the existing fiber optic splice closure, at the intersection of Plaza
Boulevard and Euclid Avenue, was removed and replaced with a larger closure in order
to accommodate the proposed 36 fiber optic cable, and splices. This change of condition
required testing of the existing fiber optic cable, cutting, and re -splicing of all existing
terminations in the new fiber optic splice closure. The cost due to this change of
condition was $4,836.56.
The revised/additional work that includes the quantities are further detailed in the
attached Change Order Number One and Contract Final Balance.
On June 13, 2003, the final inspection was completed and the work was found to be in
accordance with the approved plans and specifications. The project acceptance process
was delayed due to the discrepancies that were found on the contractor's payroll
submittals. The payrolls had to be corrected prior to acceptance of the project. The
Contractor has recently provided the City with the required documents, and indicated that
the established wage rates for the project have been met.
The purpose of the Change Order Number One and Contract Final Balance is to finalize
the contract quantities and construction completion time, and to address the
revised/additional work.
The total original contract amount for the construction is increased in the amount of
$6,506.36 with a final cost at $382,840.36. The project is funded by the federal
Congestion Management Air Quality (CMAQ) funds.
RESOLUTION NO. 2003 —120
RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF NATIONAL CITY
APPROVING CHANGE ORDER NO. 1, ACCEPTING THE WORK,
AND AUTHORIZING THE FILING OF A NOTICE OF COMPLETION
FOR THE 30th STREET AND EUCLID AVENUE
TRAFFIC SIGNAL INTERCONNECT PROJECT
(Engineering Specification No. 99-14)
WHEREAS, on July 16, 2002, by Resolution No. 2002-101, the City
Council awarded a contract to HMS Construction, Inc. for the Traffic Signal Interconnect
Project on 30th Street to the city limits, Engineering Specification No. 99-14. Based
upon the estimated bid quantities, the total bid cost for the project was $376,334.00;
and
WHEREAS, the project included the interconnection of the existing twelve
traffic signals for the purpose of facilitating the communication between the existing
traffic signal controllers in the field and the traffic computer system at the Civic Center;
and
WHEREAS, at the City's request, pursuant to Change Order No. 1, the
existing fiber optic splice closure at the intersection of Plaza Boulevard and Euclid
Avenue was removed and replaced with a larger closure in order to accommodate the
proposed 36 fiber optic cable, cutting, and re -splicing of all existing terminations in the
new fiber optic splice closure, at the cost of $4,836.56.
NOW, THEREFORE, BE IT RESOLVED that allwork required to be done
by HMS Construction, Inc., Engineering Specification No. 99-14, for the 30th Street and
Euclid Avenue Traffic Signal Interconnect Project has been completed, and the City
Council of the City of National City hereby accepts said work, authorizes the filing of a
Notice of Completion and orders that payment for said work be made in accordance
with said contract.
approved.
ATTEST:
BE IT FURTHER RESOLVED that Change Order No. 1 is hereby
PASSED and ADOPTED this 2nd day of September, 2003.
APPROVED AS TO FORM:
George H. Eiser, III, City Attorney
Passed and adopted by the Council of the City of National City, California, on September 2,
2003, by the following vote, to -wit:
Ayes: Councilmembers Inzunza, Morrison, Natividad, Parra, Ungab.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY:
NICK INZUNZA
Mayor of the City of National City, California
4
City Clerk of the City of National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2003-120 of the City of National City, California, passed and adopted by
the Council of said City on September 2, 2003.
City Clerk of the City of National City, California
By:
Deputy
PLEASE COMPLETE THIS INFORMATION.
RECORDING REQUESTED BY:
CITY CLERK OF NATIONAL CITY
1243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
AND WHEN RECORDED MAIL TO:
CITY CLERK OF NATIONAL CITY
1243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
6/94
Rec.Foml /R25
30062 DOC # 2003-1150576
SEP 18. 2003 4 z 01 PM
OFFICIAL RECORDS
SAN DIEGO CONY RECORDER'S OFFICE
GREGORY J. SMITH., COUNTY RECORDER
FEES: 0.00
I IIIIII IIIII IIIII IIIII IIII III II IIIII IIIII IIIII IIIII IIIII IIh IIII #
INS SPACE FOR RECORDERS USW OKY
NOTICE OF COMPLETION: 30TH STREET AND EUCLID AVENUE
TRAFFIC SIGNAL INTERCONNECT PROJECT (ENG SPEC NO 99-14)
(Please fill in document titles) on the this line)
THIS PAGE ADDED TO PROVIDE ADEQUATE SPACE FOR RECORDING INFORMATION
(Additional recording fee applies)
RESO 2003-120 FILE C2002-35
30063
RECORDING REQUESTED BY
WHEN RECORDED MAIL TO:
NAME: CITY OF NATIONAL CITY
ADDRESS: 1243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
NOTICE OF COMPLETION
CALIFORNIA CIVIL CODE SECTION 3093
NOTICE IS HEREBY GIVEN of the completion on September 2, 2003, of the TRAFFIC SIGNAL
INTERCONNECT PROJECT, SPECIFICATION NO. 99-14
Work of improvement or portion of work of improvement under construction or alteration.
on the premises located at 30th Street/Euclid Avenue, National City, CA 91950
Street Address City State Zip Code
The undersigned owns the following interest or estate in said N/A
Nature of the interest or estate of owner (mortgagor, lessee, etc.)
Said work of improvement was performed on the property pursuant to a contract with
HMS CONSTRUCTION, INC.
Name of Original Contractor
The following work and material were supplied:Electrical, General Concrete/Pavement Work
General statement of kind of labor, services, equipment or materials
The names and addresses of co -owners are: NLA
Joint tenants, tenants in common, or other o
Dated: Septpinhpr 2 , 2003;
Signature of Owner , Ifc'2 bZUIi , Mayor
City of National City, 1243 National City Blvd., National City, CA 91950
I, the undersigned, say: I have read the foregoing Notice of Completion and know the contents
thereof; the same is true of my own knowledge. I declare under penalty of perjury that the forgoing
is true and correct.
Executed on September , 2003, at National City , California.
Signature:
NICK INZUNZA, MAYOR
FORMS/NOC2-8
City of National City
Office of the City Clerk
1243 National City Boulevard, National City, California 91950-4397
Michael R. Dalla, CMC - City Clerk
(619) 336-4228 Fax: (619) 336-4229
September 8, 2003
County of San Diego
Gregory J. Smith
Assessor / Recorder / County Clerk
Post Office Box 1750
San Diego CA 92112-4147
Dear Mr. Smith:
We are submitting the following document in duplicate for recording:
NOTICE OF COMPLETION. 30th Street and Euclid Avenue
Traffic Signal Interconnect Project (Engineering Spec. No. 99-14)
Please note the recording information on the duplicate copy provided, and
return it to the Office of the City Clerk.
Sincerely,
1r
Michael R. Dalla, CMC
City Clerk
MRD/mla
Enclosure
cc: Engineering File No. C2002-35
Recycled Paper
PLEASE COMPLETE THIS INFORMATION.
RECORDING REQUESTED BY:
CITY CLERK OF NATIONAL CITY
1243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
AND WHEN RECORDED MAIL, TO:
CITY CLERK OF NATIONAL CITY
1243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
6/94
Rec.Fo,n /R25
THIS SPACE POR RECORDERS USE O?LI
NOTICE OF COMPLETION: 30TH STREET AND EUCLID AVENUE
TRAFFIC SIGNAL INTERCONNECT PROJECT (ENG SPEC NO 99-14)
(Place fill in document title(s) on the this line)
THIS PAGE ADDED TO PROVIDE ADEQUATE SPACE FOR RECORDING INFORMATION
(Additional recording fee applies)
RESO 2003-120 FILE C2002-35
RECORDING REQUESTED BY
WHEN RECORDED MAIL TO:
NAME: CITY OF NATIONAL CITY
ADDRESS: 1243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
NOTICE OF COMPLETION
CALIFORNIA CIVIL CODE SECTION 3093
NOTICE IS HEREBY GIVEN of the completion on September 2, 2003, of the TRAFFIC SIGNAL
INTERCONNECT PROJECT, SPECIFICATION NO. 99-14
Work of improvement or portion of work of improvement under construction or alteration.
on the premises located at 30th Street/Euclid Avenue, National City, CA 91950
Street Address City State Zip Code
The undersigned owns the following interest or estate in said N/A
Nature of the interest or estate of owner (mortgagor, lessee, etc.)
Said work of improvement was performed on the property pursuant to a contract with
HMS CONSTRUCTION, INC.
Name of Original Contractor
The following work and material were supplied:Electrical, General Concrete/Pavement Work
General statement of kind of labor, services, equipment or materials
The names and addresses of co -owners are: NLA
Joint tenants, tenants in common, or other o
Dated: September 2 , 2003;
Signature of Owner , nzu Mayor
City of National City, 1243 National City Blvd., National City, CA 91950
I, the undersigned, say: I have read the foregoing Notice of Completion and know the contents
thereof; the same is true of my own knowledge. I declare under penalty of perjury that the forgoing
is true and correct.
Executed on Septembers , 2003, at National City , California.
Signature:
NICK INZUNZA, MAYOR
FORMS/NOC2-8