HomeMy WebLinkAbout2004 CON Marcotte & Hearnes - Change Order #4 Fire Station #34CHANGE ORDER C/O Number: 4 TO (Contractor): Marcotte + Hearne Builders C/O Initiation Date: May 25, 2004 11696 Sorrento Valley Rd. Ste 200 Project: National City FireStation34 1029 San Diego, CA 92121 Contract No.: A Change Order is hereby recommended for the following work in the amount identified in this document: DESCRIPTION OF CHANGE: 1. All work associated with the modifications as they relate to adding brass slide pole from mezzanine to first floor. Scope of work included in this approval is outlined in Jeff Katz Proposal Request No. 004 dated May 2, 2004 with amendments to sheets X-22, X-23 and X-33 dated May 4, 2004. $13,231 REASON FOR CHANGE: Scope of work required by City not shown on original documents COST RECONCILIATION: Costs were reviewed by the architect and City and negotiated to the satisfaction of the City. Construction Contract Accounting Summary: The original Contract Amount $6,974,585 Net change by previously authorized Change Orders $20,223 The Contract Amount prior to this Change Orders $6,994,808 With this Change Order request the Contract cost is increased by $13,231 New Contract Amount $7,008,039 Change in Contract Time: 0 days Contract Completion Date: Recommended for Approval by: CO STRUCTI N MANAGER / R&S PR EC AR HTTECT / Jeff Katz Architecture Approved by: , Zoo f DATE DATE NO uilders DATE 6 / q OWNER/ City Of Nnal City DATE Distribution: CI Of National City (original w/all documentation) MH Builders (copy w/all documentation) Rudolph and Sletten, Inc. (copy w/all documentation) Jeff Katz Architecture (copy w/all documentation) PROPOSAL REQUEST Distribution: x Steve Kirkpatrick x Howard Mills x Wayne Powderly x Jason Sanders x David Porter PROJ ECT: National City Fire Department Headquarters, Station 34 National City, California OWNER: City of National City 1243 National City Boulevard National City, CA 91950 TO: Marcotte + Hearne Builders, Inc. 11696 Sorrento Valley Road, Suite 200 San Diego, Ca. 92121 PROPOSAL REQUEST NO. 004 DATE: May 2, 2004 ARCHITECT'S PROJECT NO: 011101 CONTRACT FOR: General Construction CONTRACT DATED: February 17, 2004 Please submit an itemized quotation for changes in the Contract Sum and/or Time incidental to proposed modifications to the Contract Documents described herein. Proposal shall be submitted in accordance with Article 26 of the General Conditions. Cost proposal shall be submitted Architect and Construction Manager no later than May 10, 2004. THIS IS NEITHER A CHANGE ORDER NOR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED HEREIN. 1. Description: Modify the Wash Room and Laundry Room area as indicated to incorporate a slide pole. Revisions also include modifications to the layout of the restrooms and Firefighter Association Storage on the second floor. Reference Documents: ASI-04, Drawings X-06 thru X-33, dated 04/28/04 ARCHITECT: Jeff Katz Architecture 7290 Navajo Road, Suite 106 San Diego, CA. 92119 CONSTRUCTION MANAGER: Rudolph & Sletten 10955 Vista Sorrento Parkway, Suite 100 San Diego, CA 92130 MED. STOR. HALL 12Q 127 1,15Hi WNX rnI 10 I (12gA) 17 Il 12E3 CPT O M C RETE B E L UND 123 1 1 CT STAIR 1*2 TURNOUT STORAGE (I22A) 122 HA STOR. 121 ( ovyLp NOTES: 0 PROVIDE 2 I/2° m BRASS SLIDE POLE, BY MCINTIRE BRASS WORKS, PROVIDE WITI-I CUSTOM LANDING MAT, FLOOR AND CEILING FLANGES (MCINTIRE BRASS WORKS, 611-541-1019) Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com 11 HALL CP IIb EL 115 CT REFERENCE SHEET 42.1 FOR NOTE NUMBER DESCRIPTIONS Notional City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 01 1 101 DATE: TITLE: 04/28/04 FIRST FLOOR PLAN ASI-04 SCALE: 1/8" = 1'-0" SHEET NO. X-06 • 212 *IM `04Fir e Gm NOTES: 0 PROVIDE I-1/2" DIA., GALVANIZED PIPE GUARDRAIL AND GATE, WITH SPRING HINGES (STANLEY, 420164-RD2060-R 5/S°) SEE X-13 FOR ADDITIONAL INFORMATION ® SECURE GUARDRAIL TO WALL WITH END CAP ® REVISE DOOR (21&S) TO BE 3'-0° x 6'-S" REVISE HARDWARE GROUP TO "14. REFERENCE SHEET 42.2 Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: TITLE: 042804 SECOND FLOOR PLAN ASI-04 SCALE: 1/8" = 1,-0" SHEET NO. X-07 • MEDICAL — STORAGE 121 \rn WAS x HALL 129 1/I S'-4' HALL 125 OM STAIR li • 1 6'-4° I,3'-2 L AUN RY 1-0° 4'-4° T-4° 4 10' TURNOUT STORAGE 122 STC 121 16'-6° T UT 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.j effkatzarchitectu re.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 1--1411111G, 1 REFERENCE SHEET A2.3 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 042804 ASI-04 TITLE: FIRST FLOOR DIMENSION PLAN SCALE: 1/8 = 1'-0" SHEET NO. X-08 MEZZANINE \ \ ELECT. 221 STAIR 4'-2° 13'-2° 5'-2' RESTROOM 216 12'-6' 4'-10° 4' - ° 12'-6° FIRE FIGI-ITEk ASSOC. 218 JAN. 220 S'-5° in ° 'r G RESTROOM 214 ' 3' 2't I g° /rY RESTROOM 213 11'-4 NALL 210 , I-IAL L 205 REFERENCE SHEET A2.4 Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarch itecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: TITLE: SCALE: 04/28/04 SECOND FLOOR ASI-04 DIMENSION PLAN 1/8" = 1'-0" SHEET NO. X-09 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com 12'1 S'-eY O ®e O 12q S'-6° 120 S' -O' 126 S'-0°„ 0 I 0 I a 1 A 123 9'-m° National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 PROJECT NO.: DATE: 042804 TITLE: REFERENCE SHEET A2.6 Architect Supplemental Instructions 011101 FIRST FLOOR AS I -04 RCP SCALE: 1/8" = 1'-0" SHEET NO. X-10 © 8'-6° 16 ►2 8'-0' re0 0 Or 1 n 1 O 1 O I 214 O • 0 8'-6' O ®O 9'-0' 0 A © X 2 IS I XX © A O © • 8'-0° 0 O N O z O 220 S'-0° 0 A z 9'-6' 0 f \j A 211 8'-6° 215 8'-6° 8'-0° 211 A O 0 210 8'-6' © O 205 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com r A 8'-0° © 8 -O° •. • 215 S'-0' z •uuui•I •u.•.1111 8'-0' 20q j 8'-6° ID 205 O A O National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 8'-0° 201 © © ..I.I.E MMMEMMM 8'-0° rl 1 12061 REFERENCE SHEET A2.1 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 042804 TITLE: SECOND FLOOR ASI-04 RCP SCALE: 1/8°' = 1°-0" SHEET NO. X-11 0 0 0 SIM J N 1/2" 5" J 0 ®o 0 6 1/2" ENLARGED PLAN 8 SHOWER CURB SIM 0 SIM 6 I/2" CURB - J l\ CURB - Z j, 5 I/2" CURB - AA REFERENCE SHEET A2.9 Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: TITLE: 04/28/04 CURB PLAN ASI-04 SCALE: 1/8" = 1 —0" SHEET N0. X-12 FIRE POLE HEAD MTG. REFERENCE STRUCTURAL DRAWINGS BRASS FIRE POLE FIRE POLE FOOTING REFERENCE STRUCTURAL DRAWINGS r NOTES: 0 PROVIDE I-I/2° DIA., GALVANIZED PIPE GUARD RAIL AND 3'-O° WIDE GATE WITH AUTOMATIC CLOSER. CD SECURE GUARDRAIL TO WALL WITH END CAP. PAINT ALL RAILINGS PT-5 ® PROVIDE 4X BLOCKING AS REQUIRED. REFERENCE SHEET A4.3 Jeff Katz Architecture 7290 Navajo Rd, Suite 106 -San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: SECTION ASI-04 SCALE: 1/4" = 1-0" SHEET NO. X-13 RECESSED FIRE EXTINGUISHER CABINET FE DOOR (L188) TO WALL BEYOND SPEAKER - REFERENCE ELECTRICAL DRAWINGS REFERENCE DOOR SCHEDULE. TYP. S'•0' I11111111111 MAP BOARD —� FRAME. SEE DOOR CONTROLS REFERENCE ELECTRICAL DRAWINGS NOD noon 111111111111111 DOOR - REFERENCE DOOR SCHEDULE. TYP. DOOR - REFERENCE DOOR SCHEDULE. TYP. CERAMIC TILE WAINSCOT, SEE /\ DOOR - REFERENCE DOOR SCHEDULE. TYP. CONCRETE CURB GTPSIP7 WALLBOARD NOTES: 0 REDUCE ROOF DRAIN SUPPORT STRUCTURE TO PROVIDE MINIMUM 1'-0" AF.F. 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 BRASS FIRE POLE REFERENCE SHEET A5.11 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: APPARATUS BAY ELEVATION SCALE: ASI-04 1/8" = 1'-0" SHEET NO. X-15 IL W1 2x50 9" CONC. THICKENED SLAB w/ #5©18" O.C. T&B 2'-0" 2" THICK x 32' DIA. LANDING PAD BY POLE MANUF. q * EXP. 12-31-06 *` `S>q1RUCT13C e C OF CA-\F HSS5x5x5/16 HS5x5x5/1b 8 8 HSS5x5x5/16 HSS6x6x3/8 \ I 6' 6' I 6x6 POST c 6x6 I. RAISE fl Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 unenu ieff4atvarrhiterturl rnm Cy National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: Partial Foundation Plan SCALE: 1 /8"=1 '-0" ASI-04 SHEET NO. X-16 3 RINGERS ?TYP. SIM. NO WALL ABOVE FLOOR )WN 6x6- POST AF _, Wa MEMOD I Ill 11 S4.3 6-3 4x12 IGL Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com Notional City Fire Department Headquarters Stotion 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: Partial Floor Framing ASI-04 SCALE: 1 /8"=1,-0" SHEET NO. X-17 BM. -TO -BM. CONN., TYP. I I I I I I IL i Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: Partial Roof Framing ASI-04 SCALE: 1 /8"=1 — 0" SHEET NO. X-18 POLISHED BRASS POLE SLOPE WIDTH 2'-0" PER PLAN POLE BASE/FLANGE BY POLE MANUF. ANCHOR BOLT PER POLE MANUF. SPECS. RUBBER LANDING PAD BY POLE MANUF. (2) #6 EA. WAY T&B FIRE POLE FOOTING DETAIL N.T.S. C1� Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.ieffkatzarchitecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: Fire Pole Footing ASI-04 SCALE: N.T.S. SHEET NO. X-19 POLE CEILING FLANGE BY POLE MANUF. HSS3x3x3/16 AT DIAGONAL BRASS POLE PL 1/2x6x6 3/16 PL 1/2x6x6 w/ (4) BOLTS PER POLE MANUF. SPECS. NOTE: PROVIDE DISIMILAR METAL BETWEEN POLE FLANGE AND STEEL SECTION A —A Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 696-9178 www iaffkat7architecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 MiE: Fire Pole Support Det. ASI-04 SCALE: N.T.S. SHEET NO. X-20 12"x6" DOOR LOUVER V!/ MIN. 50% FREEAREA 406 (2-WAY) —5"0 5"e (3-WAY) 1 - 1 14"a HAL 2101 i I _ t 3506E ' io ej Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com National City Fire Deportment Headquarters Station 34 333 E. 16th Street National City. CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 atTE: 04/28/04 TITLE: 1ST FLOOR HVAC CHANGES ASI-04 SCALE: 1 /8"=1 •-0" SHEET NO. X-21 1/2" -'1-1/2'i 1-1/2" WC-1A v v v v v v "7 14 1/2" HW UP TO LAV ON 2ND FLOOR. 27 1" HW & CW DN. TO WASHING MACHINE, PROVIDE S.O.VS. 28 SHUT-OFF VALVE ABOVE CEILING. PROVIDE ACCESS PANEL. (PAINT TO MATCH). Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.1 011101 DATE' 05/04/04 TITLEI PARTIAL PLUMBING ASI-04 1ST FLOOR PLAN SCALD 1/4' = 1'-0' SHEET NO. X-22 7290 Navajo Rd, Suite 106 -San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarch itectu re.com Notional City Fire Department Headquarters Stotion 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: TITLE: 04/28/04 ASI-04 2ND FLOOR HVAC CHANGES SCALE: 1 /8"=1 —0" SHEET NO. X-22 -•) a -3/4" 'CO I7)OAL RAGE 2 1 /2" 1/2" HALL 128 TURNOUT STORAGE 22 STOR 121 TURNOUT >- 3/4" ELiG ELEV EQUIP i ll3_ 150, ALL 124 1 1-1/4" 1" HALL 1 112 rD Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzerchitecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NW 011101 DATE; 05/04/04 TITLEI PLUMBING OVERALL ASI-04 1ST FLOOR PLAN SCALD 1/8' = 1'-0' SHEET NO. X-23 2i6F, I 1-7 r WC-1A 711 " 4" v 4" "1-1 /4"I WC-1A -1 4" WCO L-- (1/2" r- 3/4" TURNOUT --2" SHEET NOTE 14 1/2" HW UP TO LAV ON 2ND FLOOR. s —1 A 1-1/4" 1-1/4" Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com Notional City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplenental Instructions PROJECT NO.= 011101 DATE: 04/28/04 TITLE: 1ST FLOOR PLUMBING CHANGES ASI-04 SCALE: 1/4'=1'-0' SHEET NO. X-23 SHEET NOTES Cli) 3/4" G. UP TO ROOF. H C S 0 3/4" HW UP TO SERVICE SINK ON 2ND FLOOR. 3/4" - 2-1 /2! 4" 2" TP TP TUG 7 „ (S) JIP ....__T_.t-21vr2ul 1117LJ 1 -1/4" 1" I r L -1 /2" OM GI I \ 1111 \ 1-‹ Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com National City Fire Deportment Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: 1ST FLOOR PLUMBING CHANGES AS1-04 SCALE: 1 /8"= 1 ' -0" SHEET NO. X-24 Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jefikaizarchitecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: 2ND FLOOR PLUMBING CHANGES ASI-04 SCALE: 1 /4"=1 '-0" SHEET NO. X-25 Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatza rch itectu re.com Notional City Fire Department Headquarters Stotion 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: 2ND FLOORPLUMBING CHANGES ASI-04 SCALE: 1 /4"=1 —0" SHEET NO. X-26 i TYP. TYP. I4a 4 14b V° Clabc 0 �. Qr E I2c l I4a A. a ....., :............... E2-6I6L 12b I2b V _I2fr h E2-33 141 YP. 3 12k E2-6s C 0 • / Ilk ; -6 j ALL. • E2-33 URNOUT I3b A .1. .1. .) I3a 13b I3a 3er 13e TUR1c'UT .I 'el" ED 3a LlE2-33 Ilb of A. 3 HAZEL 0 4ler I.0a 3 STOR. I3aT- tl►3r W 3e Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeflkafzarchitecture.com Notional City Fire Deportment Headquarters Stotion 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: FIRST FLOOR PARTIAL LIGHTING PLAN SCALE: 1 /8 = 1.-0" ASI-04 SHEET N0. X-27 MED. s- 3 E2-28,30 23 GFI STOR. 121 21 REPORT SITING RO. TURNOUT TORAGE TURNOUT Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jefikataarchftecture.com National City Fire Deportment Headquarters Station 34 333 E. 16th Street Notional City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: TITLE: 04-28-04 FIRST FLOOR ASI-04 PARTIAL POWER PLAN SCALE: 1/8" = 1-0" SHEET NO. X-28 RLF-'ORT 'N RO. 1;4I0 t0► o®[1 ANITOR TURNOUT STO LAUNDRY 123 STAIR TURNOUT Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jefikatzarchitecture.com Notional City Fire Department Headquarters Station 34 333 E. 16th Street Notional City, CA 91950 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: FIRST FLOOR PARTIAL SIGNAL PLAN ASI-04 SCALE: 1/8" = 1-0" SHEET NO. X-29 3' 0 25e ere. 3 1 la E2A-4 • E'EsTROOMI 0O 0 lb I Ct ® o E2A-2b ba• �3 la 0 Ma TYP. TYP. TYP. TYP. BE TYP. Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkafrarchftecture.com GH 550G • 3 E2A-2k 21S lab REi.TRO -7E 214 ab ab JAN j 1c HA�A' 4 • 210 • E2A-2d E2A-2d • la Sj 0 • E2A-2k .41►ab IJVNK I! r/ ■11 1i411 -�►ab -g►ab E2 4 TYP. �i • OSj 2A-2d 5a�R E2A-4 g E2 -6 National City Fire Deportment Headquarters Station 34 333 E. 16th Street National City, CA 91950 20S C Sj 0 E1 V 3'NK �►ab TYP. -tl►ab p ■ B9 A A Architect Supplementol Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: SECOND FLOOR PARTIAL LIGHTING PLAN SCALE: 1/8" = 1.-0" ASI-04 SHEET NO. X-30 Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeifkatzarchitecture.com National City Fire Deportment Headquarters Station 34 333 E. 16th Street Notional City, CA 91950 BUNK ROOM 84 2A- BUNK ROOM +84 2A-3 BUNK ROOM 20+84 a 2A-5 BUNK ROOM +84 2A-1 Architect Supplemental Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: PARTIAL SECOND FLOOR POWER PLAN SCALE: 1 /8"=1 '-0" ASI-04 SHEET NO. X-31 Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jetlkalzarctiitecture.com Notional City Fire Department Headquarters Station 34 333 E. 16th Street Notional City, CA 91950 Architect Supplementol Instructions PROJECT NO.: 011101 DATE: 04/28/04 TITLE: PARTIAL SECOND FLOOR SIGNAL PLAN SCALE: 1 /8"=1 '-0" ASI-04 SHEET NO. X-32 Jeff Katz Architecture 7290 Navajo Rd, Suite 106 - San Diego, CA 92119 Office (619) 698-9177 - Facsimile (619) 698-9178 www.jeffkatzarchitecture.com National City Fire Department Headquarters Station 34 333 E. 16th Street National City, CA 91950 Architect Supplemental Instructions PROJECT Na.l 011101 DATE' 05/04/04 TITLE] PARTIAL PLUMBING 1ST FLOOR PLAN SCALE' 1/4' = 1'-0' ASI-04 SHEET NO. X-33 LOOe [OLLL ON Xa/Xl] LL:SL ItlJ 17oot/LZ/90 4 May 21, 2004 Attn: Howard Mills Rudolph and Sletten 10955 Vista Sorrento PKWY, Ste 100 San Diego, CA 92130 Fx 858-259-8282 MARCOTTE t HEARNE BUILDERS, INC. JU.1.7rc c.p, aV- cznre Imo ! '-��.c-➢ '��� o Via Facsimile RE: . National City Fire Station #34 Marcotte & Hearne Job No. 04-003 Subj: Marcotte & Heame Change Order Request No. 006r Dear Sir: The contract adjustment required as a result of: PR #4 — Added sliding pole and revised layout of adjacent rooms. Change Order Request No. 006r is $13,231 The incorporation of this revision into the contractual scope of work will require working days not included in our current schedule. The job schedule will be adjusted accordingly to show the effect of this revision on the final project completion date. The terms (cost and schedule Impact) of this change order request are subject to review and a re -quote if not accepted within 14 days of its issuance. We HAVE proceeded with this revised work. Please issue an authorization and/or a change order. If you have any questions or comments pertaining to this matter, please contact the undersigned. Very truly yolyrs Quotation Accepted By: Wayne Powderly Representing; Project Manager Date: CC: Stephen Kirkpatrick, National City, 619-336-4397 Jeff Katz Architecture, 619-698-9178 Project File 11696 Sorrento Valley Rd., Ste. 200, San Diego, CA 92121 Tel. 658493.4101 Fax: 658-793.4102 6T/Td Wciii:170 i7ae TZ 'hpW EOT7 £62_ 8S8: 'ON Xdd 2N21H3H a1100d3W : WO?Jd Zooli [01.LL ON Xa/Xll LL:9L Iiid b00Z/LZ/90 JOB NO. 04-003 COR NO. 006r MARCOTTE & HEARNE BUILDERS CHANGE ORDER REQUEST BREAKDOWN National City Fire Station #34 PR #4 - Added sliding pole and revised layout of adjacent rooms. SUBCONTRACT NO. DESCRIPTION SUBCONTRACTOR QUOTE Added ceramic tile Valley Flooring $326 Added guard rail with gates, steel connection and pole installation, and credit access ladder. Richardson $4,462 Door and hardware revisions F&H Supply $1,148 Door and hardware revisions TL Summers $288 Add concrete footing Big Horn $443 Mechaincal revisions UMEC $0 Millwork revisions We're Innovative -$555 Electrical revisions Sadler $2,614 Supply Brass Pole McIntire Brass $3,750 SUBTOTAL 5%OH+P 1% Bond Premium 2,476 $624 $13,100 $131 Change Order Total $13,231 6S/Zd WdTT:iB VOOZ TZ 'heW EMI:. EEL 858: 'ON XHd BNHUEH 21103eldN : WOZId Howard N. Mills From: Wayne Powderly [wpowderly@mhbuilders.com] Sent: Friday, May 21, 2004 3:45 PM To: Stephen Kirkpatrick; Howard N. Mills; Jeff Katz Subject: Review of PR #4 cost proposal Jeff, Howard, the following is in response to your 5 review comments on COR #6: 1) I asked to UMEC to send me sketches of before and after PR#4 to show the additional material he quoted. He responded with the e-mail below saying that he had only reviewed the clouded items on the sketches, which is what I did also!. The adds, and credits outside the clouded areas, cancel each other out so there'll be no cost from UMEC. 2)If we delete the requirement for the cylinder, threshold and door bottom, we' can reduce F&H's cost by $48.26. The $70 upcharge is for the machining of the door for the added exit device, which itself costs $1,068. 3) TL Summers is our door installer and his added costs are for the installation of the added hardware between group 3 and 14. You are correct about his incorrect mark up, I will reduce it by $7.50. 4) Sadler Electric has 5.4 hours for the increased LF of conduit(60 lf) and wiring (240 lf) needed for the new locations of the light fixtures. The quantity of fixtures did not change but the locations did. The rest of their cost was from their subs for the added smoke detector, speaker and strobe. 5) We're Innovative's price is a credit because the length of the counters had been reduced. I'll revise the COR per the above and fax it out to the team. Give me a call if you have any questions, thanks. Original Message From: Alex Best [mailto:abest@umec.com] Sent: Friday, May 21, 2004 10:09 AM To: wpowderly@mhbuilders.com Subject: Re: [Spam] FW: [Spam] Review of PR #4 cost proposal Wayne, In reviewing the plans again, I found that there is a register outside of the clouded area that was removed. The changes made did not come with any kind of narrative. If it was outside of the cloud, I did not spend any time on it. Seeing that a new outlet was not added and simply relocated would have very little cost impact. Please void our change order proposal and consider it a no cost change. In order to avoid any future confusion, I would like to recommend that change directives be issued with some narrative as the changes taking place. This would save everyone a lot of time. Any luck on getting full size plans for the changes made to date? Respectfully, Alex Best Operations Manager Special Projects Group University Mechanical & Engineering Contractors 1 NOD32 1.719 (20040416) Information This message was checked by NOD32 Antivirus System. http://www.nod32.com NOD32 1.770 (20040521) Information This message was checked by NOD32 antivirus system. http://www.nod32.com Cool [OLLL ON xa/xll LL 9L Ian troO /lZ/Co 05/17/2004 16:05 6196979451 RICHARDSON STEEL INC PAGE 01/03 _RICHAIZDSON ST' � �y YNC• Proposal#:050604- A25 RISC Certified Fabricator Page 1 of Z 9102 Harness St. • Spring VaIle , CA 91977 • Lie. No. 756989 • Phone (619) 697-5892 • Fax (619) 697-9451 ESTIMATOR:_BOB CARSON DATE: MAY 17, 2004 PROJECT: NATIONAL CITY FIRE STA. #34 (PRftQ04) SPEC... SECTIONS: METALS PER CONTRACT DOCUMENTS (DATED): ASI-04 (04-28-04) DRAWINNs: X-06 THRU X-33 ITFmS ERECTED: 1. FIRE POLE SUPPORT 2/X-20 ✓' ' 2. FIRE POLE (SUPPLIED BY OTHERS)*** tST g1,Lr l ak) O'NL.'( L- 3_ GUARD RAIL & GATES X-13 + 2. & + t 4s2 ***FIRE POLE TO BE INSTALLED PRIOR TO FRAMING OF POLE ENCLOSURE, TOTAL BID: $5061.70 £ram Ae ��22> /4.,z(-6/'1; *NOTE; SEE EXCLUSIONS LISTED ON FOLLOWING' PAGE, **NOTICE: DUE TO RAPIDLY ESCALATING STEEL PRICES, THIS PROPOSAL W.Q.I, BE SUBJECT TO REVIEW AFTER 30 DAYS. 1 61/2d WdTI:170 1700E T2 'heW EMI? 26L 858: 'ON Y,dd aINU3H 31100NHW : WONA VOofj [OLLL ON ka/XI] LL:9L Ind boot/LZ/90 05/I:7/2004 16:05 6196979451 RICHARDSON STEEL INC PAGE 02/03 :..RICIIARDSON STEEL, INC. 2425 AISC Certified Fabricator Proposal#: 050604 Page a of 2 IIIMINIMMIN 9102 Farness St. • Spring Valley) CA 91977 • Lin No. 756989 • Phone (619) 697-5892 • Fax (619) 697-9451 PROJECT: NATIONAL CITY FIRE STA. #34 (PR4004) GENERe�L EXCLUSIONS; Any Items or work except listed above not included; the 1k/flowing items are specifically excluded, but do not neceaaarity comprise of all eaclnded items, YEKE �it��ADDER (�gy' D11A7 7 Rough hdwe, i.e. boils for wood angles or Setting of anchor bolts, leveling nuts or templates Costa for tests thick ahrmng channels and t►Iatl less tbar chick ripe sleeves & backup plates for other trades Sleet studs appurteaaacea Non ferrous maeerlal Removal bracing rods and tables Grouting or drypacklag �' permits bolts other trades Wood palters Cutting or drilling of our work to accommodate othertrades Ro•l botches Nam t nikrs ds pa�auaang in penalties or aquidated damages applied to Royer ear dato wood latiri1g11or1 GI■ss stop■ 6enatrirstiag or iiemr-oleaneag of steel Wore p■Intlng Pickup devices for precast C•rpentry/Glnlaes hardware Special Insurance p panels Access panels Cost of bonds Field welding concrete mbar to ttractnral steel Demolt loa Mad mad One plumbing of/columns suppor6iag wood Commie re roe Field touch-up of Amp rimer pilot k'rlme patatlnp of one seers with any primer other than our Grating and frames Owe drilling for rail p p p A i+-C.D. approved low V.D.C. shop primer in current use PaintiStructural tterl calc'e FE: General Contractor shall adhere to RISC Code of Standard Practice. Richardson Steel, Inc. shall not be responsible for of gelv General Contractor's failure to comply with AISC Standards. This Proposal le valid for 30 days from date submitted at top ofpage #1. • TERMS OP PAYMENT - All terms of payment are granted subject to the Seller's Credit De fade oat or before the BPof the following month for pin partornt labor p Payments shall be ninety percent (90%) of the value of material and labor provided during the preceding calendar month, retention to be reduced from ten percent (10%) to five of the structural steel has been erected g percent (5%) after fifty peacoat (50%) the remaining five percent (5%) shall be paid within thirty-five (35) days after completion of the Seller's portion of structural steel work for structural steel, and thirty-five (35) days after completion of die Seller's portion of xtiiscellaneoue work for miscellaneous steel. On F.O.R. work, terms shall be net thirty (30) days fbr the contract value to each shipment, This proposal shall be tdca-. ; -..ad Into arty contract or subcontract for proposed Iro work aid shall not be amended.Accepted: p p EWER TITLE RI'C.1L#RDSON STEEL, INC. SELLER SIGNATURE TITLE 2 6T/bd WdTT:t'G bOCE TE 'hr'W z1T17, £EL 858: 'ON Xdd 9N&H9H 911OJ'lUW : WOZId 900E [OLLL DN xa/xi] LL:9L Iid 1700t/LZ/90 05/1.7/2004 16:05 6196979d51 RICHARpsoN STEEL INC PAGE 03/03 Fick NO. :79Z4162 M. 17 2004 i31: eeprh p2 National City Fire .5tatk n #34 IWarcottte + Hearne Builders Inc. Suboontruct0r Change, Order Break Down ,An lysIs CORD 1� c o ti� F r.7-b Materials: 1.)eaaription Unit Cost Item 1—` el 0 R7Y (incl. Tax) total item/ item 32 W` Cr' Z34F 2 .a Item d— Item 5 SUdTC) AL'A' bq, Equipment; QN - Unit Coat Item 1 DeBcrlption . HOURS (Incl. Tax) Total Item m— .4.'_'ia(S tea= Item 3 /art u ohs Item4 Item 5 SUBTOTAL'S" Labor: Prev, Wage Class T ypo i} c nii<�ar FbRtrh FIB Brae Rate Total Clads Type _Rain `� cr �1$ 37 �`y 70 Class 1ype • Class iypo`14aJ 6� . SUBTOTA Commercial General Liability and Properly Manage Insurance Worker's . 3ornpensetion Insurance Social Security end Unemployment Taxes 7 SUBTOTAL "D" SUBTOTAL A+R+C+D.p Subcontractor Mark Up 16%i6 Total Subcontractor Change Order S4op u.s.2 OR'IC 440.2 — prTo^ tcsrAL, SUQ1'OTAL. ,.a,. /45,3 6I/Sd WdET:170 1700E TE 'heW E0T17 262. BSB: 'ON Xdd 3NaJ3H aLLOO1HW: Weld sooT1 [oLLL ON Xa/Xll LL:sL Iaj boot/LZ/90 ' May'06 04 08:30a VALLEY FLOOR COVERING E19 449 0540 p . 1 :i.'t�kawi� 4'tveYYkl�:'yi1.�=sh_nmlcw:4il VALLEY FLOORCOVL'RING INC. 1 591 CUYAMACA ST. EL CAJON, CA 92020 LJC # 492930 Fax Transmittal Forma TO: //IA 17/ AT1N: FAQ PHONE: (619) 449-5222 FAX (619) 449-0540 rfROM: DENNIS CURTI$ DATE: 575(0t( NUMBER QFlAGEs ma_ await PAGE MESSAGES: .�-r I: ri : (�0 At ((All? FaE. P re, ¢ S cs'S 1hF� ed� �f �. rnnMnrrmT-.r•v,.x<r.u.,n.WA::. •rrn�. Y.Y�a'n•r. •>. • • 6I/9d WdET :PO bOOE 'LE 'F a4 EOTV £6L 698: 'ON Xdd 3NaH3N 3i100Nb4 : WOdd LOOIJ [oLLL ON Xa/X.L] LL:94 I8J 17oot/1.Z/90 .05/OU,20U4 U8:49 FAX 1 I001 F.&L3. COMMERCIAL, SUPPLY 5325 ELBORN BLVD #322 SACRAMENTO, CA 95842 PHONE: 916-344-2538 FAX: 916-334-8662 NAME / ADDRESS MARCOTTS & HEARNF BUILDERS 11696 SORRENTO VALLEY RD SUITE 200 SAN DIEGO, CA 92121 ITEM WOOD DOORS HARDWARE HARDWARE HARDWARE HARDWARE HARDWARE HARDWARE HARDWARE HARDWARE PROPOSAL REQUEST # 4 - NATIONAL CITY FIRE STATION # 34 CHANGE HARDWARE GROUP FROM # 3 TO#14 REPLACE 3/0 X 7/0 DOOR WW/ 3/0 X 6/8 - MACI{INING CHARGE FOR CONCEALED VB. DEVICE / DELETE L9050R X 17 X 26D MORTICE ✓ LOCK Grp t. 3 ADD-9947TJF X 36" 26D EXIT DEVICE ✓ ADD-994L X 26D TRIM ADD-20-061 MORTICE CYLINDER IC CORE ADD•7501 X 689 NORTON CLOSER ADD- 270D X 36" AL THRESHOLD ✓ z. ADD-290DV X 36" DOOR BOTTOM ADD-S/1SD-17' SMOKE SEAL ✓ Sales Tax QTV Estimate DATE ESTIMATE NO. 5/6/2004 605 COST PROJECT TOTAL 1 1 1 1 1 1 1 I 1 TOTAL S1,200.24 6T/Ld WdET:ba baaE "GE 'FEW MTV £6L 8S8: 'ON XHd 3NdH:3H 811OO&JW: WOSd FROM :MARCOTTE HEARNE FAX NO. :858 793 4102 May. 21 2004 04:12PM P8/19 h.S'ZE Jir'£r iL88=6 L9FVOI .LSVLEZ .LOZ'OE8 .L00'06T- .L00.0L 1V1O1 %SL-L PVT 98'b 0S'6 9!It 1 09T£ SS'L£Z °TOES 00'061- 00'0L 1SO0 1H1O1 027)12 uo xuysaVS • 'was allor Is I-1188S-aav }AIOLLOf 11OOQ u9£ X Aa:06Z-Qay arrirex O IOHS3NHJYi V „9£ x QOLZ -clay 2I 1 O'I3 MO,LHON 689 X i0>:L-aav LOO DI IIMIDI'I,A.a 21aLLHOW I90.OZ-ciay WRLL an X `Iv66-fray :L7xAaa .IJX 1 a9Z .,.9£ X 1rIL666-a v 13aroad SO9 i P00Z/9/g 'ON 31VWI183 3.L 'Q e;eurgs3 1 aDI.LTTO14 a9Z X LT X ZI0S06'x 3.L r hQ &luAau 11A TITIVJOMor 1i0611 11J2iVH0 ONi7A11HOyT�1T - 8/9 X 0/£ /MA11IOO(1 O/L X 0/£ 21OV iJTh E # NOW 4110119 IUIVMLTUVH aDNIVHz £ #I NOLLV.LS AIM A Lt0'IVAIOLLVAI.1' # ISNatralf '1VSOaOH41 NOLL *1083a `IUVA% lJVii sxlooa aooA+ WRIT f/t Ika UM VD `OJaIa NYS 00z aims €DIAZTWA 04.1\i1IHHOS 96911 SnI3airatt RNHV813 BLL.LO02TVLit BMW/ /3INMN Z998-17 E-916 :)(vd 85SZ-170£-9 E6 :ffi•IOHET Zti8S6 'O,LINIalAIF LDvS ZZE7 GA'I JV2IOIiSI'I; SZ£S AMdf1S TVIMIHMAIOD B'9 J TOO!J 7 IVf 17T:TT i'00/6C/s`iL) 05/21/2004 FRI 18:11 [TX/RX NO 7710] F1008 FROM :MARCOTTE HEARNE FROM :MARCOTTE HEARNE '0N 113HS ..C)— L • � I TND5 Nb"id 1ofllu atoms :'r114 lU-ISY ' b IWZ1,0 21DM 1,01 L LO t'ON iDWOOd 232°R2fJt=7=i 11:44ew.tddns u:011140Jy r v 189M9 8dNaa(3dabr FAX NO. :858 793 4102 FAX NO.: :859 793 4102 0S6L6 'V3 'A1!O IDUORDN' ;a0a1S 4i9L £C£ 'c uollDys eLial,aOnbpnaH }ueu4JDdaQ auI9 410 IDuo(yDN May. 21 2004 04:13PM P9/19 May. 05 2004 11:27AM P4/30 woz-eJnweX uranwerminm 9Lia-ee® Cow) apwlw inn -1L 66-eee (no) mato e bt6 Y3'0%e10 IN8 • ea" owe 'PM OBANT4 DIRE It Ol 44110b10 MIb'fflQlsPdH cV61n2N r I i8-.9 3e Ol (�BIL) 2lOOd 851A901 .Had GNo H.UM 1I'd2tIOSM10 3sr a N01.1.V14bIOiti lDIaOIJ lddir alOd EI-X 996 (INN ai-C779air;e f^'b9I,CL)° '+kW1NC191 83°ANIH 4JNIZ1d4 Min 11170 CINV 11tr614:lalV'PI9 9.dl.d G9XIN7n1VCI 'Vic] .t✓rI 2dlnQaJd IQ 'WUJ.ON z o o ICI T YN,i ni.:un *nnz:ion,cn: 05/21/2004 FRI 16:11 [TX/RX NO 7710] 2009 • OLO 2 [OLLL ON Ha/X11 LL:SL INJ 1700Z/L2/90 FROM : TL 5111 DEU FRX NO. : 619 445 s� May. 09 2004 12:47PM P1 T.L. SUMMERS DEVELOPMENT "-� LIG: 8484092 • P-0. BOX 1498 • ALPINE. CA 91993 • TEL.. (019)445-3208 • PACIE1R (619)530-7O18 LETTER OF TRANSMITTAL T�a4� tV 6,..4 c....41 Ft-) 4 -- ik,.-- i' 1-- wE Arts 68N171NQ you (j .Aeadrad 11 Unties seperef w c'Vwr Ma ..._.-- ., .. ,. . the R/1Wwlr+g items: 1_1 swap drawings 1:7 Trines I-1 P. (.1 6areptes 0 SPa1.MLaeNms 1 Copy of Wet Clrarrge order THESE ME MANS JI1T.ED as checked baby; 0 For approval 0 Approved as srlllr+fi u d, 13 Resubmit super* ke approval (!•man your we I:i Alrprovad as noiad 0 Submit cgples (or dlsW(11 YOn 0 As requested ln1 flattened far Carr etiorrj! 11 now" .............__... currecred rrrrrge (i For review end aorrrnard 0 _ (_j P111H1IS nEUUDNED AFIVIR LOAN•TOOS 1"3 Fon INDS DUE t1EMARKS . 1,1 19 • ••• ••=m.n !A `• l 6T/0ld Wd£T:170 b00E 'GE 'heW ZOTb £6L 858: 'ON Xdd 31•NUEH 3110DNUW : WONd FROM :MARCOTTE HEARNE FAX NO. :858 793 4102 May. 21 2004 04:13PM P11/19 a . ttne-7-619 ;IV ATUVREIWINI Sit 11Vi 3Stri '1101189 NI MISSDISNW/ 03A2I33H 3AVN MA 41 wimp '33SSMEWN AO 2sn BFLL 104 ---svitaissIwsmvu Sin Ni GOMM VOI4WHOdki :1JVW A IN Ar503 9NIVNIANO3 ••••.•••••••• •11•711K. ppwrvi...mpea. • ,_)01 riW'rfire14— ;SAWN 96n-cv47-6/9 WV4 ----CCAT=T614ist •••,7 Onflork.., :1MMAS --- ;w01 \jj ;Avdwoa, 446 AlVa VeSEI2PS4.14,6i.5); rgiel,k1 VO -_LINI.cAlY • 0PL XO 21150V9Vit.:Orl ;7,fatanta=1-7=aaa_-_a===rma-unar.aaapantallt-7=-.....-....,.:4"."-7,----,.,•4.4,,,IC47T."'".4"51"'=." • ^. Td WdbE:20 1700Z 60 'AvW • 1 Nd 013.01,3G SelaiMn S 8EZE Stp 6T9 : 'ON Xdd nsa wns WONd' 05/21/2004 FRI 16:11 [TX/RX NO 7710] ZOil 1,1)f4j [oLLL ON xa/xll.11:sl Iad 17OOZ/lZ/90 hlay'10 04 08:20a lgharn construcion ramp. 7005817614 p.i : 762 Poinsettia Ave. San Marcos, (A 92069 BIGHORN Construction co. Lk. # 597866 FAX COVER R SHE : E T DATE: s'to, 014 TimE:„ TO: CO: • PHONE: FAX: PHONE: FAX: Number of pages including cover sheet' (760) 727-8837 FAX (760) 727-8330 6T/ETd Wd£Z:PO 1700E ZE 'FEW EOIb £EL 8S8: 'ON XHd 3NNH3H 311O0?HW: WOdd 6100 [OLLL ON X8/X1] I8J 1700Z/LZ/90 • rial10 04 09:20a ighorn construoion comp. 7609917514 • • 762 &ins=la Ave. San,Marccis. CA 92069 • . 5-10-04 BIGHORN'. canstructkin ca. # 597866 =.0•M=E=1,==24Pl.nc.=,.......1=3116.1.140[3=aab..= (760) 927-8837 FAX (960) 727-8330 12 • 2 To: Marcotte & Hearne Builders Attn: Wayne PoWderly Re: National City Fite Station #34 Subjeet: Proposal Request #4 •Add Footing for Fire.Pole Add Curb at New Walis tv // ti40.10-136"--c6- 'Wiz, • Pole Base/Flange/ Anchor Bolt supplied and installed by Pole Manufacturer. Backhoe .5 hr. at $85.00 = 42.50 Concrete 1 cy at $83.00 83.00 Labor: 4 hrs. at $65.00 260.00 385,50 15% 57.80 443.00 Total Add: •$443.00 Sincerely, Drew Olwell 6T/2Td WcIPT:VO 1700E TE E0T17 26L 8S8: 'ON XUA 3NNH3H 3.1.103eldW: W0e1J t?t0 J [OLLL ON Xa/H1] ll:9l INJ 1200Z/lZ/90 `Mati•12. 2004 10:14AM WE'RE INNOVATIVE 760-789-6381 No.6410 P. 1 in C (. o 6! a t i #/ 5r r:.u.y/,on (;ui;i)rgi.s eviz i mom! License * 799267 CONTRACT CHANGE REQUEST DATE: May 12, 2004 TO: Marcotte + Hearne Builders, Inc. 11 696 Sorrento Valley Rd Ste #200 San Diego, CA 92121 VIA: FAX: (868)793-4102 ATTN: Wayne Powderley C/O REQUEST NO: 2 FROM: Robert Merrill Pertain, Sales Mgr. RE: #40247 National City Fire Station #34 Upon execution by all parties, or receipt of your executed form, the above referenced subcontract is hereby modified as follows: PR #4 - Floor Plan change In laundry and rest rooms #213, 214, 216 Laundry room #123 cabinet 4' to 5' & location move Rsstrooms tops 14' from 18' & 1 - 2' 6" cabinet under longer top in #216 (S555.001 Total Amount this Change Request: ($555.00) RECAP OF CONTRACT AMOUNT Original Contract Amount Was: 127,g31.0i! Previous Change Order(s) Total: $22,534.81 Plus This Change Order: ($665.00) New Subcontract Amount Is Now: 6149,910.61 AGREED AND ACCEPTED When this change order is signed by both parties it constitutes their agreement: ^� 1 ] That the amount of this change order Includes all time and compensation for the work described harem, including overhead and profit , design, Payment & Performance bands, and time extensions. 21 That the subcontract price Is adjusted as shown above and that nu further adjustment in that price by reason of the c.•hange(%) provided herein shall be made; and 3) That all the terms and conditions of the subcontract, except as modified by this and any prior change orders, shall remain in full force and effect and apply to all work as so changed. Marcotte -w Hearne Builders, Inc_ Wi = /Tit rI�7, ative Your Authorized Signature Date • ur Aut oriz dSignature Date Robert Merrill Pertain, Sales Mgr. Printed Name & Title Printed Name & Title 136 loth Street. Suite L Ramona, CA 02065 (760] 769-6370 FAX 17601789-6361 6Ti17Td WdtT:ttO 1700E TZ '6pW MTV £6L e 9 : 'ON XHd 2NNH3H 2llO02:1JW: WOthi c'.oli [Ora ON xa/xl] tt:sL zaa vooz/ez/so McITIE B:1S WORKS, INC. 14 itORACE STREET+NOIVIERV1LLE, MAS MG'J-tTJSETTS 021434TRd,:617-347.r8198NAX:6I7-947.4466 • 0 Thank you for your requ..!;;t for quotation for a.Model 19 Stationary Slide Pole. We are pleased to quote as fbllows: MODEL 19 STATIONA I•1Y SLIDE POLE d•t`hard drawn, highly polished brass(up to 24 feet) with an outside diameter of 2 %2 hes •'with, a' 5/32,inch wall thickness, with floor flange, coiling liver ovcr: socket and landing mat $ 33lad plus 'freight up to 24'. d t $200,for first foot over 24' plus $I00 each additional foot. Price.ie POB Somerville, Massachusetts. 3340 The above price is good Ivr 90 days lifter the'date of this letter and is for material only, no 2021) installation or erection labor supplied: Payment terms IT BOND RD: 1/3`d with putd rase order, 1/3rd at time of shipment, 1/3rd thirty days after shipment, We ship freight prepaid and invoice you for same. Please provide us with the bonding information, !umbers, etc. NOT L ONDED:I/3rd will! purohase order, 2/31ds at time of shipment. We will ship freight COD for the freight charges. What is the required deli'.':ry date? Please sign where irrdioalcd below and return u copy to us, If you have any further questions, do not hesitate to contact us. Very tru 6.7 yours, Mcintir4Brass Works, tn.! F. A: b(hs Customer Acceptance pl 3500 ,ts'yre,t.,rh�.r �5��' ��"' ,e_I .4„, 'n.i:%1"-'r'7 �'� ✓Ir�Ca .. ..416541•;4.i'-*""""4-'` ./a`iyC'•-l• „"11.14'.• A .-4-42 J Td Wd9tr:SO VHOe Tt 'hpW 618T LbS 2_19 : '0N BNOHd ,,4;1„0„..44, (732;,46,_, 9b11NJO11 aILs�w : woa� 6T/STd Wa7T:170 1788E TE 'hew E0T17 £62_ 8S8: '0N Xdd 2N?H3H S11OOaUW: WOad 9,LOf1 LOILL ON X2!/Xll L1.9L I89 1700Z/12/90 SADLER ELECTRIC, INC. 1935 Friendship 6rive. Suite F, El Cajon, CA 92020 L.IC #, 323 556 PNbNE (619) 449-1266 FAX (619) 449-4372 From the desk of Craig Small FAX MEMO To: Wayne Powderly Company, Marcotte + Hearne Builders, Inc. Ph (858) 793-4101 Fax (858) 793-4102 Project: Sadler Job # 266 National City Fire Department Headquarters Station No. 34 Subject: Proposal Request No. 004 bate 5/12/04 Number of pages including this cover sheet: 4 Thank you, CraiSmall Chief Estimator, x-105 1 0.461 Fes. 6 f +,, f\ \ (U o-)' . �— b2e.,51-0,19 ,, okras c ET/9Sd Wd17S:17O 1700E SE 'FEW EOS17 26L SS8: 'ON Xdd 2NNl33H D110ONdW' WOad p 24I0IJ [oLLL ON xa/x1] LL.9L Iad 1700Z/LZ/90 MIDRIB E1111.1 �1. ANC. tate. ala41 iorjcea. National City Fire Department Headquarters, Station 34 PROPOSAL REQUEST NO. 004 SAMERJOB #266 DESCRIPTION OF CHANGE IN WORK: Fire Pole Add, Changes in floor plane PROPOSAL NOTES; 1) This proposal affects quantities of various light fixture types. Delays In decisions whether or not to accept may affect prof eot schedule, ITEM DESCRIPTION 5/12/2004 MATL MATL LABOR LABOR QTY. UNIT $ EXTEN UNIT HRS HRS EXT 1/2" EMT conduit w/fittings (power & lighting) 80 $0.55 $33.00 0.05 3-00 #12 THWN CU wire 240 $0,07 $18,80 0.01 2.40 1/2" EMT conduit w/fittings (pa/speaker) 20 $0.65 $11.00 0.05 1.00 Install speaker backbox 1 0.50 0.50 3/4" EMT conduit w/rittings (fire alarm) 20 $0,70 $10.00 0.08 1.20 4sq deep box for added strobe light 1 $6.00 S8,00 0.60 0.50 3rd Tier Subcontractor(s) SlmptexGrinnefl quote (pa/speaker) $340,00 ustaLlnk Comm quote (fire alarm) Totals $1,471.00 Subtotals all items Sales Tax 7.75% Material Leber hours $81,80 8.60 $6.34 Labor Rate: Including Insurance, $43.45 $8.60 $373,87 Taxes & Fringes Sadler Electric Work Subtotal $481,81 3rd Tier Subcontractor Quote(s) $1,811,00 Proposal Subtotal before Markups $2,272.81 Markup 16,00% $340,92 Proposal Total $2,514,00 6t/LZd NdST:PO 1700E 'GE 'AEU MTV £6L 858: 'ON XHd ENbt8H 81lOONNW: NONA FROM :MARCOTTE HEARNE FAX NO. :858 793 4102 May. 21 2004 04:15PM P18/19 Amidump MUNN NW :Rq 144,04ddy Wnlblm ro 'w0 anw+ow'aauoiwe=As4roia*1W is p�w0uµ�a++ 614 w1moi c2011/JIIaP 9JuwJ'tpJNe tuuulad'844eWd til0AMIoa[rpNNgrP'Aupirwra •01I1064I ul' 404pedimolinpQ004JeIPura.COEdn.u,aatiolaurawJ8u14+01nd'waPN lx1 Poltdaell 4 lea Muumuu tikim Ans LA.!? .!? %0 n-Qr4014pnicsti0 AC#hKpW 'WWI L 1* taX00004 54I6Iwrya� }mowing idr8erQaJD�eadrkoLogppellogiulPun•pinoj.j 0 aals�mb3a SX I3 ` VNnui TVLOi 9113NV140 019'0144 !Not AJOLlJudn$ 91 at'Of 00[4 x 51ioa CLuNaeulaug 41 0704 Obi x I ysop OuI{dwq 1t 00'13t YEIS x auiwuzaal4 et 0rpa4 46Un WauLdinb3Io14J. GI cans op04 amt cusps. Op'4di 1'PlfNll L p10LuoIWIwWI t1 xo. sal0410,113IOW Pt 00W1J09401 019NO 6 y l [ I41 RIaiDW Puo mgol do Ammuirle mffalingewninrapiew 4ustudlnte IO4OJ. L xoLMpg 9 WaWdrb l 0 Joga1Iolai 1 acss s+0N 0001 U WaJad = omri 94M our wpudpUnos 8 11511e4DVX I044L 10 NON ,00t/LrI9 1LV 'vtt ad Rad Ja:41:4ds wuouppo 4[p4i I puo (pin im ;WOOS sulBod - imp MOM( a'H Nis. igwetnwtrior pc001i43 'Melva op xxXiw4440 10I14*lr Jad7 1 Wso oac(lSOi 731013./VS0 NOd OO10'0PL89e U Ms. LZ6 v0.05;Ia min 'PS uehtin JIB MI6 jute eelDupW MAG1l91UL4uoy7 E01E0 10PSid fl NNI2EX3"k3VI5 987:09W.828 EEE:90 von/ET✓40.. 05/21/2004 FRI 16:11 [TX/RX NO 7710] fj01' May. 21 2004 04:15PM FAX NO. :858 793 4102 FROM :MARCOTTE HEARNE Datatirds.0 )iiricathrom 17131 Hotel Circle South. Suite 10/ Rona (619} 291-1430 Fax M9)2914435 CORM= TITLE Camel Cliernt Sepalmort NeedeenineSialben24 PROPOSAUESTRIATE FOR Comm' stanwscATHA NIEBRACT RI2FORAuESEMATE FOR.CONTRAOT NOSIFICATTOPI CONTRACTIBLE MI OF WORK MUSE CONTRACTOR asit plcvsniS*1 for RsOnspiES at Mathis! Clry.Fsa Cep- MeMislion COMMIACTIM 40300031C314fla- • rInssr0 Ileeftsters, SiSlieSS4 °FREE doss sods deeds AsYslia. MEM clowsioacairmt01030400. 1201)01MTER 1.1 L ARON 1.001" C037 0115L CCBT MATERIAL EQUIP RENT Tam INr cow Roe TOTAL CC ..41' PHASE Cast proem! Iselisdreitg a( Nsimai Oty Faenapt MEMO= al one Arnie &HEWS *ohs. Meta isssagesin mewl *anew panaxcarnaacion VARA t LMEETORIBBe_s 0. SAUESIAXCIM MOMS 11. IINEVIVIONt 4.INARIMCQTRIBL ANC FII1N2B MEWS . SERIAL suurbeir IL SAUISIBUSURNOL HIPMBIT 1321A1MMITOIRENSPIF MEI MRS-TM EIIVISES & BRIPENPIL ISCRIPES11-4 IL FEW moms 5111019131.. 110211111111111 &II PRAE ENNA= aFIZE OFIRE3 it OPE= ?JAMUL% OE SALES TAXON 614PaiTALI la 1300ECTLABOR 14. INSWZANCE:TAWESAIMPOGESEPEMS 15. RENTAL EOUStfiENT . 84124 TAX emonaraLszerman woo NI OREM PRIME CONTRACTOR:MIMS .i-i!V!! SOUPMENTOMMERIBS1MettlEINEMO EXPENSES W?iti Tom, TOTPA 1 TOTAL 15 SUBTOTAL MOUSES 52) L ABOR MATERIAL EQUIPMENT MN OF WORE SUBACONTRACTOR heasurigattitskria aly r9m 1744441343411 pg01074001000401014/7a0 lastamic4104$0344 040404" &Bast res Amines (awn envied C:rslesele4stob41 - ofFennesmsonel U COY UNIT TOTAL war Tom. UNIT COST Con COST COST RATE . a 70.00 420.00 f 14 15.DO 21010 t MOO 30.011 376.00, 3713.4:0 a.sa MIN 029 15i10 3 3109 3600 MOO 111/00 rSO Olin KM OM 12.00 ocpcy CONTMCTOR ro-EALS SOFAS 1 TOM COST ma _ to3:ati warn:mew MEIEUMMWS OFUEZ OF1.1031 INA1410111RACTORI BORK • 72ei. efts& II MR a=0. 3E056 or uts is MIS igN 40.031: 040.00 17240 4 ya, 14 F1E121 OVERHEAD tO.iFLINlI4 .20. SUBTOTAL tge NM Aid ri) 21. NONE OFFICE MEMBER 22 PEWIT 22, SO/COM (ADD LIMN so • 221 SUNS REININEE: ISM Or..41 psuposai is RN Co Helots -malts Leroy and Same Wm sad imbhilion of one CAW (Inlet as per omit asermt drawings. FlinsEcOtins.ACTONS wcI raxst1ax4 23. MISCCN1RACTOREIRCHIN 1911221 LINEA as. SUBTOTAL taw UHEB 24 & 27. FSMIE OVEFHFAO ON SUISCOressiCTON 2s. PANES MIR OFFICE ONIEFtrEAD 2g. mimes PROFIT 90. 41JERU'UlL (AOC IAMB 21) at PRIME CONTRACT/me ECHO MOM 92. Ttf COW LAM LIND/ 3/ L31) Cr WE 25 Cr LINE CI [ME WI Dr urie TSIE EMMEN AM) IMBRIUM& PEEVE C011111ACTOR Sadarigusak, Asc. PPOUICTibvinCER. EcIamals SUFSCOMINACTOR SOME DMUS* CasstpuOstroas. .:!..:ft:•71it!s SG/WM a -rim OFTNEPARER: Rank V. Moo' 1 7,471.1Wcit. 4r1;.10 1A7tte CAUF/MAO DAYS 0 0) cat 21 sucuslypTunwwon munewea GRIZ-t£14-GIS DATE 64121114 le ffi 0 0 CIL X co 0 - 0 CC Li- Tzt C•1 LC)