HomeMy WebLinkAbout2005 CON Jaynes Corporation - Library Construction Change Order #6CONTRACT CHANGE ORDER C/O Number: 006 TO (Contractor): Jaynes Corporation C/O Initiation Date: January 12, 2005 8530 La Mesa Blvd. Suite 306 Project National City Public Library La Mesa, California 91941 Contract No.: 1028 A Change Order is hereby recommended for the following work in the amount identified in this document: DESCRIPTION OF CHANGE: 1. ASI # 041; COR # 063: Revise Roof Assembly #2 to Coordinate with Structural Design.......$ 31,424.00 REASON FOR CHANGE: This roof area was designed to put the waterproof membrane under a topping slab so that mechanical unit installation and maintenance workers and materials would not damage the membrane and cause leakage into the library below. The topping slab approach also limits noise from the units from radiating down into the building. Architecturally, we are required to slope the topping slab to drain (1/4" per foot) which causes the top surface to be up to 13 inches thick over the structural slab. The structural engineer designed this area of open roof and covered mechanical penthouse for a four inch thick lightweight concrete topping over sloping insulation and the structural slab. This design approach saved a substantial amount of structural steel (both vertical and lateral) over designing for a much thicker slab and also offers the benefit of additional thermal and acoustical insulation for the history room and offices below. ASI No. 41 clarified that the slope would be created by a lightweight concrete topping (four inch maximum) over high density foam (where necessary), over protection board, over waterproof membrane, and over the structural slab. The contractor is entitled to a change in scope on this matter and the City does receive added value for this change. COST RECONCILIATION: $ 31,424.00 Costs were reviewed by the Construction Manager and the City and negotiated to the satisfaction of the City. The foregoing increase in price is in full settlement of all entitlements directly or indirectly arising out of this change. Construction Contract Accounting Summary: The Original Contract Amount $ 11,476,444.00 Net change by previously authorized Change Orders $ 124,433.00 Revised Contract Amount due to previous Change Orders $11,600,877.00 With this Change Order request the Cact amount increases by $ 31,424.00 $ 11,632,301.00 New Revised Contract Amount Change in Con ' - . Time: Zero (0 Contract Co ate: Ap Recomme - . . f. pproval CO M endar days 2005 deb, inc. /—/4 — -- DATE PRE CT ARCHITECT 'eRESENTATIVE DATE Gregory Ny; President (C.A.I.) 3j OWNER/ Ci O National City j Steve Kirkpa ; Director of Public Works/City Engineer Distribution: City Of National City (original w/all documentation) Jaynes Corporation (copy w/all documentation) DEB, Inc. (copy w/ all documentation) Carrier Johnson Architecture (copy w/all documentation) DA 1't; DATE OCT-29-2004 09:20 CONSTRUCTION ADMIN 619 231 4138 P.02/05 AIA Document G710T's —1992 itect's Supplemental Instructions PROJE4',x-'(4iie n addreai�: National'CityiPuW.c alra_fr - • 1401 `4itto ia3 Cit d, Natibha1 CCy Z.X. 9l9 '0 •' O.WNER4Naitie and Ogress): C1014P Nj?,3'10NAt;.CLTY. 1243'.Nattgri4C4, i, d Naiona>ity :_9i95f1_ FROm;vRCHIITE:CT (Naixie4nd address): t?01 Tiir i°►vtheie ; ; 'Sanbicgii: CA `92141= i TO CONTRACTOR. (Nai>ne:.(Md address): Jaysie, e. itpiiratiori General Contractors 85901a-191 a)314 ••4:*...006 l.a•Mcsa,: _F: ; 9Z941' OWNER ARCHITECT CONSULTANT CONTRACTOR FIELD CONSTRUCTION MGR., MARTIN GABEY, D.E.B. ARCHITECTS SUPPLEMENTAL INSTRUCTION NO: 041 DATE OF ISSUANCE: October 28, 2004 CONTRACT FOR: General Construction CONTRACT DATE: ARCHITECT'S PROJECT NUMBER: 4486.01 X X X • The :'fIyUrk'siiaiti rjr.eied out ii:$yFtii dance with the following supplemental instructions issued in accordance with the Conitigti ktcliitieiits without change in Contract Sum or Contract Time. Proceeding with the Work in acctir angeiv?tfrttit'3a instruc.uons indicates your acknowledgment that there will be no change in the Contract Sum of Cons act:Tw'e OESCRtPTto See attachedsketches friteiiirification to roof assembly 2 as coordinated with structural drawings. AM Document G710*" —1992. Copyright ®1980 and 1992 by The American institute of Arifotems. All rights reserved. WARNING: This Ale 4ocument is protected by U.S. Copyright Law and Intematlonef Treaties. Unauthorized reproduction or distribution of this Ale Document, or any portion of it, may result in severe civil and criminal penalties. and will be prosecuted to the maximum oateal possible under the law. This document was produced by AIA software at 15:0327 on 10/28/2004 under Order No.1000107577_4 which Mires on 5/222005. and is no1 for resale. User Notes: (1671458840) OCT-29-2004 09:20 CONSTRUCTION ADMIN 619 231 4138 P.03/05 ATTACHMENTS; (Her_e,ituert listing of documents that support description.) ASTMj:SK1, C4/A8.04 ASt641•'--SK2, A2.03 GC r C . �� t (Prince ante likd tide) 1-"ZekA- eP AIA Document G710ry —1992. Copyright $1980 and 1492 by The American Institute of Architects. Ail rlghta reserved. WARNING: This AIA4 Document le protected by U.S. Copyright Law end International Trestles. Unauthorized reproduction or distribution of this AIAC Document, or any portion of it, may result in severe civil and criminal penalties. and will be prosecuted 10 the mMXlmum extent possdtlo under the law. This document was produced by AIA software al 15:0327 on 10/28/2004 under Order No.1000107577 4 which expires on 3r22/2005, and is not for resale, User Notes: 0671456840) OCT-29-2004 09:20 CONSTRUCTION FaDMIN 619 231 4138 P.04/05 NG 2•.2•.10.8 CA Mn.w women RME WAN (GRIDS x1-44 OW) TS BEYOND RETNF. ROOFING MEMBRANE UP d UNDER FLASHING CONC. CURB-- 6,30'-2" T.O.C. 22 GA. GAL S.M. FLASH OVER W.P. MEMBRANE lJ Q \*/ i!iia!!!!!!! Viv•i•i•i•i11,r•i•� KiKAKOKO _4" MAX. SLOPING LIGHTWEIGHT CONCRETE TOPPING OVER HIGH DENSITY FRAM (WHERE OCCUREU) OVER PROTECTION BO. OVER WATERPROOF MEMBRANE OVER STRUCTURAL SLAB SCALE : 3" = 1'-0" SCALE: 1 1/2" =1 '-0" IIIEMIEEIEEIMIIIPROJECT NO. 4486-01 C4/A8.04 ADDITIONAL NOTES SEE B5/AB.02 22 GA. CALV. S.M. FLASHING ANO COUNTER FLASHING HOT-AIR WELAKAD NO OPRNE WWARIER • 16•nc SINGLE PLY ROOFING — MEMBRANE ROOF OVER LT. WT. INSULATING CONCRETE OVER EPS SHEATHING ON STRUCTURAL CONCRETE DECK CURB A8018. NATIONAL .CITY PUWC LIBRARY CRY oF.NAT1ONAL CITY mitamummum OM 1 SK1 GATE: 10/25/04 50 d 10101 ROOF ASSEMBLY 1: SINGLE PLY MEMBRANE ROOFING (COLOR 1) OVER SLOPING COMPOSITE INSULATING LT. WT. CONCRETE (SEE NOTE 114, THIS SHEET); OVER PROTECTION BOARD, WATERPROOF MEMBRANE AND CONCRETE STRUCTURAL SLAB; THICKNESS VARIES 4" MIN COMPOSITE CONCRETE © ROOF DRAINS ROOF ASSEMBLY 2: 4" MAX SLOPING LIGHTWEIGHT CONCRETE TOPPING OVER HIGH DENSITY FOAM (WHERE OCCURED) OVER PROTECTION BD. OVER WATERPROOF MEMBRANE OVER LOW ROOF FLOOR PLAN SCALE: 1 /8"=1 '-0" ARDIPECIWI *MUG* OMR A1IONAL,CrfYPue ri.rc;U8RARy a1Y.OF NATiO L' CRY PROJECT NO. 4486-01 A2.03 P Oq\ w2, OVATE: 10/25/04 N1WQd NOI1Dna1SNOD 8£17 T£2 619 melanoma ,xwnmmvaua IMI JAYNES CORPORATION ESTIMATE FOR CHANGE ORDER JAYNES CORP. COR LOG # 3057-063 CONTRACT: # 3057 CONTRACT TITLE: NATIONAL CITY PUBLIC LIBRARY DATE: 1216/2004 CHANGE DESCRIPTION: ASI #41 - tapered foam insulation at low roof Delete: Add: 631,424 1. DIRECT LABOR HRS. ($45) Superintendent 0 $0.00 $0.00 Project Management 0 $0.00 $0.00 Carpenter 0 $0.00 -$45.00 Laborer 0 $0.00 60.00 2. INDIRECT LABOR COST (Labor Burden, etc.) SO 3. DIRECT MATERIAL (ie06) 4. DIRECT EQUIPMENT (pump) ($170) 5. SALES TAX MATERIAL & EQUIPMENT COST (7.75% OF LINES 3 AND 4 if not already included Line 3) SO 6. DIRECT WORK SUBTOTAL (LINES 1 - 5) ($1,023) SUBCONTRACTOR WORK COMPANY REMARKS AMOUNT Saddleback Waterproofing 630,752 SUBCONTRACTOR WORK TOTAL: 630,752 CHANGE ORDER TOTALS 7. PRIME DIRECT SUBTOTAL 8. SUBCONTRACTOR WORK TOTAL 9. COC/BUILDERS RISK INSURANCE (0% LINE 7+8) 10. GENERAL CONTRACTOR FEE (15% of LINE 7 and 5% of LINE 8) 11. GENERAL CONTRACTOR BOND (1% of LINE 7+8+9+10) ($1,023) $30,752 $0 $1,384 $311 GRAND TOTAL S31,424 TIME EXTENSION AND JUSTIFICATION WORK DAYS REMARKS: This proposal is urgent to release material for fabrication before the holiday break. For an item of work of this scope, Saddleback will require written authorization that the pricing is acceptable. Jaynes concrete estimate based on 5223 SF to 4" thick + 10% waste = 70.93 CY of lightweight topping. Details In ASI #41 create consistent thickness of 4", so there is little quantity due back as credit. By agreement, 1 . waste will be credited. ACCEPTED BY: Manager (deb, inc.) NAME AN OF PREPARER: (Z�tej01 Daniel Luker, Project Manager (Jaynes Corp.) Dec 03 2004 10:2SFIM SADDLEBACK WATERPROOFING 18582704938 p.1 Saddleback WATERPROOFING Contractors and Consultants CA Lic. 027895 NV Lic. #32087 REVISED - FAX TRANSMITTAL TO: JAYNES CORP ATTENTION: Mr. Daniel Luker FAX : (619 668-4090 SUB: NATIONAL CITY PUBLIC LIBRARY RE: ASI No. 041— Tapered Insulation at Law Roof ****************************1Fi'*k** Fit********kic'k'******************itM*********************** Dear Daniel: Per your request, Saddleback Waterproofing is please to submit an Additive Amount of $ 30,752.41 for additional tapered insulation work to be completed at the above referenced project per ASI #041. We shall furnish labor, materials and equipment to complete the following: System: White Expanded, 25 PSI Foam Scope: The installation of tapered insulation at the low roof as indicated. Material: 25 PSI Foam (436 pieces) _ $ 13,465.00 l/ 15 Instastick Glue x $ 150.00 kit = $ 2,250.00 Labor: Journeyman x (burden include Additional Labor: Misc. Job Expenses: Material Sub -Total: Material Tax: x 7.75% per hour x 176 man hours Material Handling x S 48.00 per hour Management/Supervision Crane x $ 600.00 Tools / Misc. (4% of labor cost) Please see page two for additional information c i . i -dery \ 1144161 fir 1 ' fkk/C -W Page 1 of 2 DATE: December3, 2004 = $ 15,715.00 = 6 1217 912/ _ $ 8,448.00 = S 253.44 =S 168.96 = $ 600.00 = $ 337.92 4901 tvlotena Boulevard, Suite 407 • San Diego, CA 92117 • (858) 270,4928 *FAX: (858) 270-4938 Dec 03 2004 10:26RM SADDLEBACK WRTERPROOFING 18582704938 p.2 NATIONAL CITY PUBLIC LIBRARY CONT... SUMMARY Total Labor Cost = $ 8,870.40 Total Material Cost = $ 16,932.91 Total Misc. Job Expenses = $ 937.92 Subtotal of Costs = $ 26,741.23 OH & P:. 15% NET' Overhead and Profit: _ $ 4,011. 18 TOTAL. CHANGE AMOUNT: = $ 30,752.41 Please call with any questions or if we can be of further assistance. Thank you. Sincerely, SADDLEBACK WATERPROOFING Brent H. Schofield Operations Ilanager Page 2 of 2 4901 Morena Boulevard, Suite 407 • San Diego, CA 921.17 • (858) 270-4928 •FAX: (858) 270-4938 Dec 09 2004 11:38AM SADDLEBACK WATERPROOFING 18582704938 p.1 Saddleback WATERPROOFING Contractors and Consultants CA Lk. 0627895 NV Lk. N32087 To: Mr. Daniel Luker Company: JAYNES CORP. Message: Facsimile Transmittal "From the desk of Brent H. Schofield" Date: 12-8-04 Fax No.: (619) 336-0322 • RE; National City Public Library Dear Daniel: Per your request, please see the below price breakdown for our labor rate. Labor Rate per Change Request Summary: $ 48.00 Breakdown Journeyman Rate: $ 26.28 Workers Comp.: $ 7.72 Payroll Taxes: $ 2.50 Insurance: $ 11.50 Call with any questions or if we can be of further assistance. Thank you. Brent Schofield Operations Manager Attachments Nonc Total number of pages including cover sheet: 1 Office Phone: (858) 270-4928 Office Fax: (858) 270-4938 If you do not receive all pages, please contact the sender immediately at the above listed number. 4901 Morena Boulevard • Suite 801 • San Diego, CA 92117 • (858)270-4928 • FAX: (858) 270-4938 opr eausneet h(eport NC Library Upload Des6l12/110 t Deck' Finish Tapping•Prep Toppry Pr.p/CI.6.5 Tdppny Pop/G.. Scrs•d ' Toop.,6 Scribed ' To9piry _.. _.... T.P.P'n9'Prop 3'020.1 - Tapping_• Con,ri..,. Pl.cs: TOpP^9.1b.. P/.F' Top F.ny/51.6 . M•ih E_i Topping •COnc ele Topping_ • Finish TaketPtpuoey?ty Libor C05{/Unii: 754 00 s' 5 252.00, .r .3a C0 .I 5.223.03 .f 0. 12 Of 39 90 /Tr 43.56 Mr 6:-5 0 12 fir 39 90 M 0.15 hl 43.56 M 1. Is( Mahectai Amount Sub kmoun{ ^.1.. 0-Ol hf 753 1035 cy 10.00 /cy 3950 do 104 70.91 cy .... 4 00 Icy 39 90 M _ 1:I Icy F en T pp.,p SI b c:_nm - 784. :0 al F en T7pny5 b 23.00 al Fen Slop. Slab 're Cr.223 00 .E Topping ""' PP 9' Finish MechlEquipmenI Paas yGyi • Egp9'M.cn Pa. Layout ' Egp2,4.66 P..16 Form: EgpVM.ch Pad Form: EgpVM.ch P.d. 1:' St,. • EgpVMch Pee Scr..a ' Eqp uM.ch P. Ps.Pr•P•tir G•.n 4' Styrofoam (AI/A3. al; Fnen Eqpt P. d' Edy. Fnen Eqpt P. ' Edy. Fni.h. Eqpt Pad • Tap Fnhn Egpl P.d• Top MechlEqulpmeni Pa,.. 319200 Curbs L.ypw•e.,roe lycol' Curbs 3197C0 Form. Ch•mf•r P'•c.: Controls Curb Macs" Conval. Cu. (C3 a_ :4, • P*' - Curs •F,,oh: Caw. Farm' Caro, - ta' (C3'45 ;a; Farm: taro, . 10. Curbs PILS/Vaulla/BOtas • . L•yuul • Elevator Pl Layout• El.0lor Pit Ems. • aa•e Slab B.ckfid • IN•VPI01.26 9•ckG9 • IN I/PiUV•ull Grad. 6 Compac:B••. Grade 6 Compact B.•• Screed • B•.. Slab :Screed • B... SIN B••e Slab Fro,: B..• Slab PM. B4fe SIN P140s: 0•.• SIN v1401. W.S Cercr•t. Place.' Wall Concrete EIs. Block/Out P.C.'. Maw 9bck/Oul Fooh. Elea Block ON Fmh El.91oc1i•Out S E,can0on ' Masa Farm - Bo. 0• o ...... 1sb Form: 9a,. Slab Toting_ • Re6.r T.mp l•I. 150 hl 020 /sf /sr 16. 00 •. 21 13 /.. 5 00 . 21.73 /e 549.00 9 4.50 Al 07 66 If 5.50 Al 1 330 50 of : 0.32 /d 211.45 .f 0 32 /.l 1 ]00.50 .f 0 40 hl 330.50 •f 040 hl 54900 9 141 .11 67.61 If 1.41 Al' 1 330.50 9 1.55 M 212.45 II 1 30 Al /AA 0 01 nl 32 22,467 00 /cn 0 DC /06 _ .Z. 52 a 50 kb. Amount` 4 Daher P: GO 105 387' 33.65 , ... 1.176 a 50 rch 6 50 /cn a 56 64 35. BS M 1,043 .... .............. 21221 43 50 M 0.15 hl 733 782 3917 J 9, 7 0 00 /00 /ch . 930 /cn._ 97 97 "19/ErA TOk11CC5 0 14 5/ 22579�1 0 /s/ 017 a( 06 6571 5a01 1,735, 1•. 6 343 4356 M 22 4359 M : 2470 43 56 ,h 43.56 M 43 50 M 3990 M 39 90 M 4240 ,h 42 40 4v 377 433 87 551 Sal 776 96 4240 Av • 2 135 4240 /Iv 329 Foot, • Reber T.m, lat. ,son. V.0 /Pal W.!1 F0m1.W y Top of WAG F:rmr Way Tcp of Was ern _.a • Block -Col 17.50 cy 3344 cy 4.06 cy 99 00 a/ 2 CO Iv 1.00 hr 53300 0 u 64 cy 7.15 :y 1,197.71 of 43.56 /hr 43 50 Air 4356 Tr - 4356 M 8.156 2 00 /ea 2 00 /.• 1.00 nr 200 Al 002 /sr 0.02 h1 hl 32 5!9 135. 26' 1.00 of I.151 0 05 of - 27. 005 M 0 05 or 0 05 Af 69 11 2241 650 kb L 50 /ch d 50 /ch a 50 to 3 50 /ch a 50 /ch 300 kn 15.00 /ch 6.50 /cn 23 113 14 23 ]7 69 159 3. 50 /ch 19 0 50 /cn a 50 kh 426: 50 943 10 79 ky 3 Icv 3 Icy 457 150 hl 373 7/7037/6/ /sr 17 . 3 9 1 b25 7,018 2520 ;•a a0] 25.20 /.a 25 171 rc ' .......... 721 Of S2 1! O.30 lsl 4341 . - 0.30 h! 74i 043 ht SGS 1 45 hl 2 000 1. 75 Alp.y 75 ni 1.34 ,11 046 n1 43 Se M . 43.56 my 43.55 M • 3,1 50 00 /cy 43 56 dr 7]2 005.00 al 0.35 41 9 42.40 933 CO M 3 50 nl 37 4 1 026.00 If 0.35 ;of 424C M 440 of 4356 ,h 100 •a 87.12 /se - 4356 40 1.00 .. 0711 /•a 43 56 M D 92 /cy 12. 52 ,cy 12.52 /cy 0.79 /sl 65 50 sf 0.79 rad 99. CO .I 0.45 hf 85 50 ./ 99 00 If 15.50 9r 2 02 cy 1. 74 cy 4 33 cy 4.02 cy 1.00 .a 1.00 •0 00 .. 1.00 as 43 25 cy 40 00 al 37 00 .I 40.00 11 37.00 11 320 00 ar 40 CO 1 3: 25 e 1.0 30 •4 16055 a 39 33 /I. 39. 32 M 39 32 nr 4356 M 4356 h 43 54 M 734 h( 4356 M 1 70 Of 42 40 Mr 1.70 Is/ 42 40 M 3, 73 /cy 31 73 ky 9C ^0 /cy 60 00 /cy 77. 15 h• - 5350 /Iv 77.19 lea 33 60 nv 43 56 M 43 56 Or 43 56 .'Iv 43 30 Av 10.90 'e 4240 M 10 50 /es 3. 10 Icy 4240 M 4077 M 5.00 hl 43.50 M 5.^0 /If 4355 1v 293 419 311 43 56 M 3,509 2 0C mr 2 00 /he 2: 022 '8 V2' 012 hl 015 of 150 /6 Au! 0.35 of 10226 5, e7 174 4,9 51 79 e3 5 00 /.a 300 re• kg_ kg_ 144 109 557 512 2,26,0 4 03 61 43 56 M . 4 05 nl 43.55 M 4 a0 .. 40 ..f 4] 37 163 0 02 ;sr 0 02 /.I 005 hl 145 0.05 /al 64- 55 201' 241. 77 4356 nr - 2.50 Al 4359 hr 2. 50 it 1556 _Fr 45.59 hia 43 59 .h a359 4359 'r 77 220 0 25 /ea 0 25 /•• d. 50 /oh 5.50 /ch 0. 50 kh 6.50 /ch a30 /ch a. 50 /Fh d 50 kh a.50 /N 6 50 /ch d 50 kb a 50 /ch 6 90 4, 20 372 231. lad 540 M 43 39 .6v 037 nl 1131 2633�390 11.341- 52.53 /cy 46 40 it,, 0. 73 hl 97 43 555 773 551 90' 145. 1,049 8: 85 00 /ch 372 25 00 /ch 25 00 /ch 8 50 to 3 50 /ch 3 50 "ch 3 50 ich 99 12 5 50 /ch 850 to 3 50 /ch 6 50 /ch 3 50 /ch a 50 /cn x 934 075 /sl - /56 714 /6 4 556 5 39 AI5 532 .... ni.... 13,534 97 79 Sol 29 9 a' 8,50 hh 200 100 hf : 40 lay 1.00 hf 37 162 005 Al 15C065 nl 29 1453 Lot -sr 320 1 302 '52- 1 55 11 52 100 of - 299- I.'5 11 57 44 5.:0 ,.. 055 bf 44 42 40 x 5 00 /.. _.. 5. - 0.15 oaf •• a 53 'ch of 32 ... 6 50 /ch 75 00 Ich 8 50 AN 6 50 /ch 2 2 405 e50 Oh a SC 5 50 kh 85 35C kh_.._ 8 a 50 lcn 6 50 mh ..... 3 50.-cri 98, 97 79 /•• pal 543 1549 kg_.. .. -..... - 3'SI 1513 'cy. .. 61' 035 hf 64 035 /If ]2i 0..3 ref 43 043 isf 41 2.09 Mil 207 2.09 hl 175 33.79 /cy .... e3 y ] 17. M 33 79 ky 92 67 My 92 07 ky 77. 19 /44 59 270 250 77 77 10 /.a T7 12.93 7• : 13 17.95 I•. 47 /c 551 /if 9 31 hl 4. 75 of - 996 of /a 11 14 31 • ,5 .3 51 53 a a SD /cn - .0 ... 51 J3 -.a ...................:...... : 1 IOC I 625 201' L] 150 1751 1 67$ .... 1951 • 153.1 5, P-r 3/172004 '2-'37 IVV (tlb'J( iv FIN,', Spreadsheet Report NC Library Upload .. ,338075 000C • P1.169141012 . ...................................................... .......................... : ...................... 1 00 . .. Fump Se/ 4.9i • Eiol War. 011 Pump • SM-Up • 4211546 0 70 m ....... Pun-p • Sial•Up • ESpee W•1 1.00 ea Pump • SM-Up • Pet. Wall 100 aa Pump • SMUp - Tr, W•11 C 50 4, 6,11, • Sel-Op Wa. 0 50 •• Pump • Set -Up • Bench 1 00 ea Pums• S*14, • Terrace Wal 100 Pum • Y • CAleiSr. 13•• • 14 72 cy Pump • Houn • Corer. Elas• 3.00 Pp.. • 6•144 -Corer eas• 100 Pump • 1, • Pmfestal 0.73 cy Pump • Ho.,. P•dostal 1 CO hr Pump • 64.1.4, - P.dnl.l . . 'r?9 .... Pump ' C.Y_ Pump • 0 Y. - SOG P mp • C.Y. Trash SOO °um • C - Type A Punly•Cli •7 •/3 :Pump • C.V. • typ• C :Pump • Hour.. SOO • Pump ' Pours Pump • Hour. - Chller SOG Pump • Ho, • Tr., SOO Pump • hlours Typ• A Pump • Hours • Ty, 13 P• rn • Hours • Type Pump • 541-146 -SOO Pump • 6M-Up Pump • Sel-Up SOO Pump • SM4_, Trash SOG Pump • Set -Up - Typ. A Pump • Set -Up • Typ• P,rnp • SM-Up . Typ• C Pump • C - Deck MI Pump•CY •MoMFI Pump • Hours - P9 Pump • Houn Poor Pump • Se14./p • Deck PP Pump • - M.in Roof Pump • C.Y. Cock Toppisg Pump • C.Y. Mech. Encl.`Top Psirn • Ho • 174cl Tapping ,Purn • Haws - Mech. Eno,. 7c6 • Purn • 5.-Up • 17,9 7 pomp 616.51 13 S3 c 5 39 cy 07 80 cy 27.19 cy 5 15 cy 24.00 hr 4 00 lar 2 00 Ir 1 00 Pr 10 00 hr 11 00 hr 3 00 hr SOO •• 1.00 ea 1 00 0 50 aa 2 00 1 00 I, 1.00 233 42 cy 202,01 cy 16.00 M 16.00 hr 2 00 ea 2 CO ea 10 31 c 70 93 cy 2 00 he 6 CO hr 1,00 ea Pump • Sral•Up • 141, Ere Top 1061 •• • Pump • • Elm/ Pit : • 6.36 Cy Pump ' C - Elias Pit 5.75 oy Pump 'Ho, eav Pump • Mours • El, MI 2.00 hi Purr, • Set•Up • Elies. Pit 1 00 • Pump ' SM.Up • Elev. Pit 0 50 ea -Pump • Cl• • Stair PI 3 00 cy Pump • C.Y .5,10113 2.00 cy Pprn • CY 5,112 2.00 cy 15, • Hours - Slap 61 Pump • Hours Stag 113 Pun, 'Hours • Star 42 2.00 lir .... 71 ...................................... .................... .................. .................. •. .................. .......... ......... ............... ........... ............... ........... EqufpAmoarrt ' • Other Nice- Otber Amount L Tatat -pPstiLfat.: -• t Total Attp.vgt. .......................... .................................... 265 30 444 • . .. .................... 2 .. .......... iXi .. /55 .......................... 2.9 •. 796 00 ,..4 264, ..... /ea E7 • 268 00 /ea 61 256,00 /ea 57 .................. ,.... ................................................................................................... ..................... „ ..... 73690 ... 263 ........................... 26109 . '•• ........ 251' • zee 00 , 266 266.00 .. 266 226.00 lea 113 22300 /... 226 00 /ea. 226.00 fe• 226.00 /ea I 45 Icy 13300 Air 266 00 hip 1 45 Ky 133 00 669. 113 2:6.00 form 225 226 00 Aa 226 226 00 /.• 21 145 ky /93 133 00 Mr 266266 00 les 1.45 icy 133 100.00 Mr 266,00 /ea 87 260.00 /es ................... : .......... ...i. .............. ................ ?5.: ... ........ !i•I'P. . !Fr. ....... 1 45 /cy . 1.45 icy 103 Icy Id 1.00 icy 1 00 ty 5 100 /cy 63 1 00 •cy 27 260 00 Paa . 268 00 naa 226 00 /e• • 22090 /la 1 00 Icy 133 00 ihr 132 00 Iv 11300 lh 113 CO Ar , 40 Im . i 3 3,, Iv 1 130 113 00 Mr 904 113 00 ihr 904 113 00 Mr 329 113 00 /he 339 3 192 330. 226 113 1 DO 113 113 226 226 21 798 266 133 67 694 ................. ..... '2 14 5 op /cy as 100 (cy 27 1.00 ,cy 5 133 00 Mr 3 192 133 00 lv 332 113 00 As 111 00 thr 113 793 266 00 /ea 793 7.00 266.00 /es 260 22600 ,a 220 123 226 00 /4, 113 22600 /.41 45' 226.00 to. 452 226 30 7.. 758 026 00 Ns 726 226 00 /ea 228 226 DO ee• 226 I 45 Icy ' 346 1 45 /cy 293 I 45 , 293 133 CO /M 2 123 133 00 /A- 266 00 /.. 2116 00 /.. 1 45 ky 1 45 tcy 133 00 Mr 133 OD I. 209 00 .••• 706 00 ,• 1 a0 , 2123 532 532 15 TO3 1 41 /cy 3.10 133 00 IN 7 123 123 00 ,fir 261 00 /ea 266.00 A, 143 /cy 1 55 ,y 066 • 13000 asr 753' 133 OD Me 206 266 00 266 26/1 00 /ea 1 43 /cy 6 1 40 ,y 133 CO ihr 260 133 00 /111. 286 133 00 Mr 266 133 CO Me 20d 260 CO Pm 210 268 00 7e4 203 2 126 532 532 15 103 261 796 266 264 236 00 1. 9 1 47 /cy 133 0416 00 ie• 1 43 icy 1 45 /cy 1 45 /cy 4 133 1 43 icy 145 Pump • Set.Up 41 Pump • 0•1.Up • SI. P3 Pump • 6.41-14 • St. 47 Cono • Polo. ing ..:3350!0 P.ainforcing Steel 3 ; • ..... 236' Sao., C., Reinforcing Steel lflr 'Sand 9.116 F 11 Sand 539 29 cy 2 00 tor 2.00 he 0 25 ea 0 25 ea 0 5C Icy 3 IC I CO es Agar • Sand 7,716a 40 76 13 38 1-• Mr ....... naa 25.0D ich 1,000 DO /ch 130 00 Mr 13300 Mt 11300 osr 268 00 /*a 286 00 /ea 236 256 206 67 67 736 00 ,s 1'3 75 1.000 .0 -; ... ;cy 014 145 oicy 130 CO Ay 3 236 13300 Ihe 288 133 OD Mr 236 DO /e. 296 110 236 DO lot• 256 DO ri • 38-1 o2 icy 9.174 133 38,452 7.2 •58 • 212 1 000 30 I. 1• 000 (212 13 75 icy 9,174 9 174 Page 13 3/17,2004 2:17 PA1 1925 icy COnc ' Ready -Mix ptian 337 1'-, eu,lain9 Conc Mater,ai Cam: 3000 pe - Spot Fly Cork 3000 p.i - Spnl F1g, Con- 3000 psi - Spot Fly Can: 3000 psi- Spot Fry Co,: 3000 poi - Spot F19 Ca,.. 3000 pm - Spot F I9 Coe 3000 peeSpa/ F''y Con'. 1000 p./ - Spol F:g :Can 3000 pm • Spot F l9 Core 3000 pal - P.a•1t.1 Core 3000 psi • Cswnn Conc. 3000pn - 10. B•r.n Conc: 3000 ps,. Grad. 0.•m Con 3000 psi - Spot F,y Core. 3000 psi - G..a. Hu.-. Core: 3000 psi - E•1. Tn B•., Con: 3000 psi - Pal _ W.li F Ig Co,- 3000 pal - E. W.. Flg m- 1000 psi • E1.v Pot _ono 3000 p. • E1sv Pil Con3000 psi . P.1. W. p TaK4wlfGtaan441y 11a4or CosNtlnit'. 243 00 era 13-05 c 6.14 c Icy Spreadsheet Report NC Library Upload iVEa1f•rIaE�Ptf aC:: 1(000 Amo i0, 702 a. 62 Acts 2 133 2,138 3 a' an lcy 2 135 2,136 26 32 cy 19 32 cy 58 37 cy 07 94 cy 130 90 cy • 1E7.56 cy 65.37 cy 0.73 cy 24 00 cy 32 69 cy 26.55 c 0.77 c 75.79 cy 26 20 cy 23.11 cy 4 39 cy 3.33 cy 5.76 cy 35 99 cy Core: 300091 . 50G 616 51 cy Cork 3000 pai - SOG 58.32 cv Core 3000pl- Coen. 00 Coo Conc 3000 pal -Core.1. 5..• Can- 3000 pal • T.mc. Fly ..... .. Conc-c-3 C00 psi - T.n•c• W.r Cone 3000 psi -Cn4•. F.q Come 3000psi-T.a.A Fig .. Can- 3000 p.r - CNI.r SOO • Lon: 3000 pal - CN1.r 50O 12.55 cy 14 72 cy 1003 cy 3.34 cy 24.31 cy 3.139 cy 12 93 2.63 cy 'C0.c'. 3W0p.i-C1.1.r Pad 12.93 cy Con' 3000 pe - Tn.r1 SOG 5 39 cy Ccn 3000 at • Tn.M1 SOG 1.3B cy 2.44 cy : Ccn- 3000pci. Stir 63 1.97 cy Cork 3000 pal • 51a462 1.71 cy Con: 3000pa6 Color- Ent war 6.53 cy Can: 2000 psi - Color • 427 W.3 0.92 cy Corr- 3800psi - Color B . Elipa• W. 23.73 cy Core 3000 psi - Cder •TrssM1 w.l 6.34 cy Can'_ 3000pe- Color . C1dl.r w.6 13.32 cy Con 3000 psi, 1/g1,1 G.•y - Boren 7.60 cy Cone 3000pai LRVI - Ina F:oar C.._a 233. 42 cy re: 3000 pa, COLOR ,Ow, - Tap 10.36 cy Care: 3000p.i L0'W9-Main Poet 202.05 cy Can 3000 pa, L/JWI - Curb 14 04 cy .....7.1, 3000pm LUWI • M.n 9nel 7093 cy C/rc: 3000 psi LOts/1 . Cork 7.13 cy Cenci 3000 poi LAM - 22.30c euil.ln9 Conc Malarial '337500 Co, 3000 pal-Stair6I CONCRETE SITE CONCRETE 337700 5116 Conc Material icy lsgft 235,237 60 10 lcy 1.049 83 10 /cy 49, 60. 10 /cy 2,105 30.10 ky 1,535 30 l0 /cv 4.552 80.10 ky 7316 30. 10 /cy 80. 10 ky 30.10 ky 80.10 icy 30 10 ky 30 10 ky 10,435 15024 5,224 59 1, 922 6 622 J0 10 ky 2.126 a0 10 ky 80 10 ky 60. 10 /cy e1 3.311 2 009 60 10 ky 1.771 30.10 ky 392 30 ,0 Icy 510 80 10 ky 80.10 /cy 47 2.833: 30.10 ky 40 332. 80. 10 Icy : 4,753 60 10 Iry 7 003 60 10 /cy 1. 1I9 80. 10 ky : .C4'. 80 10 ky 263: 60 10 Icy 1 963'. 60. 10 ky : 296'. 60.10 /cy 1 116 • 60 10 ky 60.10 ka 30 10 Icy 30. 10 /cy 60.10 ky 30. 10 ky 30.10 icy 112 50 lcy 12 50 ky 112.50 ky 112 30 k 112 50 ky 211: 1 94C: 432: 107: 106. 154: 137: 733. 104 2,370 713. 2,118 112.50 /cy 654 113 95 ky 27,168 14340 /cy 11395 ky 113.95 /cy 113.95 ky 113.93 icy 11395 /cy 1.515 23 023 1 863 6 032 312 2,141 208 645 324,075 47,915 41,503' 41,387. 30. 10 /cy 50. 10 /cy a0. t0 /cy 30. ID /c 30. 10 Ic 30. 10 /cy 3010 /cy 1,046 491 2 103 1 513 4 552 7 345 10 453 30.10 /cy 15.024 30. 10 lcy- 5 224 50. 10 ky - 59 30-10 /cy 1 922 30.10 Icy 30.10 ky 6 623 3. 135 80.10 /cy _ 61 30. 10 /cy e3i1 60 10 /c J010 /cy 8010 /cy 2,069 771 392 60 l0 /cy 510 30. I0 /cy,_ 60.10 /4.y 50. 10 ky 461 2 313 49 312 60.10 Icy 4 703 30.10 ky 1 005 8010 /cy 1 179 50.10 icy 30.10 /cy 60.10 /cy 30 10 /cy ao 10 ,ey 304 26a 1 995 299 60.10 ky - 211 80.10 lcy 1040 30. 10 ky 30.10 ky 30.10 Icy 40. 10 ky 30.10 Icy 112 50 /cy 112.50 / 11230 ky 112 50 ky 112.20 icy 11230 ky 432 im 194 154 137 735 104 2373 712 2,113 654 113.95 ky 27 163 146.30 /cy 1,315 113.95 /cy 23 023 113.95 ky 16ea 11395 Icy : 8 082 11393 /cy 517 11395 icy 3,54t Icy lsgft 208 645 690,117 Erv,c,m.ntal F.. - Sit. Corer 6r." 1.00 4 Ccm. 2500 psi- Flppo,• 9•,• 1.09 ey Co,: 2300 psi -Lignl Gray' S''•F• - 2.13 cy r 3000 psi -Lignl Pot. 00o• 9a0 cy _aY 2500 psi - D,rvsWy 9.0a cy <. 2500 p.i - OA.S:I. W.0. CCurt 17 .. :.'c. 250C p11 - Crub. 45 31 cy 17, 2500 pi - Ncv: CA, ........ 7 52, py :0 par . Slier ,/ -., , ... 53.53 cy __ 07 •. Color Dan Goa. 23.33 cy 5 ppr,. Lrg IGrv, Tie.' 5 15 cy ._-c 335C pr City Mu S...e a•ie Cana Material 3700'' --\ 5,1' C;on crate Adi us'.nsr-1 31.11 cy 13 10 cy /Cy 393 CO /4 60 33 ky 1'0.31 icy 30 3a /cy 3C.36 :c 30 •1 ky 5033 ky 30.36 Icy 50 33 cy 395 33 235 772 459. 5 5e,' I 3'3 3,83' 1'033 Icy 75/4 110-33 lry 1.100 11a 36 ky 559 ua 27.373 393. 00 /Is 395 10.36 ky 83 310. 33 Icy 235 6030 Icy 777 503J /cy 4e9 30 33. cy 6 363 38 33 /cy 1 310 30 33 /cy 3 612 J0.33 icy 629 33 /cy .....7,5`:4 :2331cy 1,1c0 '3 31 .a 5,0 .. 11 icy Icy a15 27 379 Pan• 3.'7727472.f- City of National City, California COUNCIL AGENDA STATEMENT February 15, 2005 AEETING DATE C,-1. oo-`-t AGENDA ITEM NO. 4 (-ITEM TITLE Resolution of the City of National City approving Change Order Number Six for the library project with Jaynes Corporation to revise the roof assembly around the mechanical equipment in the total amount of $31,424 and authorizing the City Engineer to sign the change order PREPARED BY Stephen Kirkpatrick DEPARTMENT Engineering EXPLANATION 336-4380 The attached change order fully explains the details of this change and the negotiated costs. However in simple terms the building was designed to support four inches of lightweight concrete on top of the waterproofing membrane on the roof around the five air handlers. This concrete was specified to allow maintenance personnel to work around the air handlers without damaging the waterproofing membrane. During construction the of slope around the equipment was identified as an issue by the contractor. Architect Supplement Instruction No. 41 showed that foam needed be installed on top of the waterproof membrane, below the lightweight concrete to create positive drainage of the roof. This foam thickness varies from 0.5 to 9 inches. Each piece of foam is manufactured in the specific shape for this roofing system, which can be seen to be quite complicated. This information, though contemplated, was not shown on the original plans by the architect. Consequently the contractor did not include this foam in the bid. The change order is necessary for the integrity of the waterproofing system. J CEnvironmental Review (-Financial Statement X N/A Approved By: Change order number six is for $31,424. Funds are budgeted for this change order in the project account numbers 241-409-500-598-1583 and 24•-409-500-598-1583. Account No. ance rector STAFF RECOMMENDATION Adopt the Resolution BOARD / COMMISSION RECOMMENDATION N/A ATTACHMENTS ( Listed Below ) 1. Resolution 2. Change Order Number Six Resolution No. 2_0®.S`21 -- jaynesfsix A-200 RESOLUTION NO. 2005 — 22 RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY AUTHORIZING THE CITY ENGINEER TO EXECUTE CHANGE ORDER NO. 6 WITH JAYNES CORPORATION IN THE AMOUNT OF $31,424 TO REVISE THE ROOF ASSEMBLY OF THE NEW NATIONAL CITY PUBLIC LIBRARY WHEREAS, the contract for the Library Construction Project was awarded to Jaynes Corporation on February 10, 2004, by the adoption of Resolution No. 2004- 19; and WHEREAS, Change Order No. 6 is for the revision of the roof assembly around the mechanical equipment for the new National City Public Library, in the total amount of $31,424. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of National City hereby authorizes the City Engineer to execute Change Order No. 6 with Jaynes Corporation in the amount of $31,424 for the revision of the roof assembly around the mechanical equipment for the new National City Public Library. PASSED and ADOPTED this 15th day of February, 2005. Nic ATTEST: Michael Della, City Clerk APPROVED AS TO FORM: George H. Eiser, III City Attorney a a AI r wr.e -; Passed and adopted by the Council of the City of National City, California, on February 15, 2005, by the following vote, to -wit: Ayes: Councilmembers Inzunza, Morrison, Natividad, Parra, Zarate. Nays: None. Absent: None. Abstain: None. AUTHENTICATED BY: NICK INZUNZA City Clerk of the City of National City, California By: Deputy I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of RESOLUTION NO. 2005-22 of the City of National City, California, passed and adopted by the Council of said City on February 15, 2005. City Clerk of the City of National City, California By: Deputy