HomeMy WebLinkAbout2005 CON Frank and Son - FY 03-04 Resurfacing Project Order #1CONTRACT CHANGE ORDER NO. 1 DATE: 2/16/05 PROJECT: National City Street Resurfacing Project, FY 03-04, Specification No. 03-11 TO: Mrs. Alicia Vasquez, President Frank and Son Paving, Inc. 1019 Third Ave. Chula Vista, CA 91911 DESCRIPTION OF CHANGE: This change order is written to increase work item number's 8, 9, 11, 16, 18 and 22 and add item 27 to the contract (shown below). No Current Contract Adjusted Contract (CO #1) 1 Item Unit Bid Qty Unit Price Amount Bid Qty Unit Price Amount Mobilization LS 1 $10,000.0 0 $10,000.00 1 $10,000.0 0 $10,000.00 2 Clearing and Grubbing LS 1 $15,000.0 0 $15,000.00 1 $15,000.0 0 $15,000.00 3 Unclassified Excavation CY 400 $30.00 $12,000.00 400 $12,000.0 0 $12,000.00 4 Traffic Control LS 1 $20,000.0 0 $20,000.00 1 $20,000.0 0 $20,000.00 R&R Street Section 1.5" AC on 8" Base SF 83,944 $2.70 $226,648.8 0 83,944 $2.70 $226,648.80 6 R&R Street Section 2" AC on 10" Base SF 39,454 $3.75 $147,952.5 0 39,454 $3.75 $147,952.50 7 R&R Street Section 3" AC on 8" SF 4,900 $5.50 $26,950.00 4,900 $5.50 $26,950.00 8 R&R AC Only TON S 2 556 $55.00 $140,580.0 0 2,611.7 $55.00 S143,605.00 9 Pavement Milling LF 26,043 $1.13 $29,428.59 30,119 $1.13 $34,034.47 10 Pavement Fabric SY 66,082 $0.71 $47,050.38 66,082 $0.71 $47,050.38 11 A.C. Overlay TON S 4,625 $47.70 $220,612.5 0 5,172.8 $47.70 $108,675.00 12 Adjust Manholes to Grade EA 40 $350.00 $14,000.00 40 $350.00 $37,573.20 13 Adjust Monuments to Grade EA 7 $550.00 $3,850.00 7 $550.00 $17,447.10 14 R&R Cross Gutter SF 3,788 $7.50 $28,410.00 3,788 $7.50 $13,650.00 15 New Cross Gutter SF 154 $7.00 $1,078.00 154 $7.00 $153,225.00 16 R&R Sidewalk SF 3,696 $6.50 $24,024.00 4,922.5 $6.50 $31,995.80 17 New G-1 Curb LF 85 $16.00 S1,360.00 85 $16.00 $9,300.00 18 R&R Curb and Gutter LF 203 $25.00 $5,075.00 324.30 $25.00 $8,107.50 19 Traffic Striping LS 1 $13,000. $13,000.00 1 $13,000.0 $2,500.00 20 Reinstall Traffic Loops EA 19 $260.00 $4,940.00 19 $260.00 $4,940.00 Page 1 CONTRACT CHANGE ORDER NO. 1 21 New Driveway SF 432 $6.00 $2,592.00 432 $6.00 $2,592.00 22 R&R Driveway SF 386 $8.00 $3,088.00 2,901 $8.00 $23,208.00 23 Under sidewalk Drain D-27 EA 1 $1,300.00 $1,300.00 1 $1,300.00 $1,300.00 24 Storm Drain Cover D-25 EA 1 $600.00 $600.00 1 $600.00 $600.00 25 Fill Material CY 12 $150.00 $1,800.00 12 $150.00 $1,800.00 26 Retaining Wall SF 260 $85.00 $22,100.00 260 $85.00 $22,100.00 Extra Work Item 27 Extra work due to Base/sub- base betterment of soil conditions LS 1 $4,000.00 $4,000.00 1 $4,000.00 $4,000.00 Totals $1,023,439.77 $1,096,073.76 DISCUSSION: Line Item 27 has been added to the contract at the City's request to provide compensation to the contractor for extra work needed to remove and replace base/sub-base material due to encountering expansive soils which could not be compacted properly. The work will include labor, equipment, excavation, backfill, removing and replacing a section of cross gutter and removing and replacing 3" of asphalt on 8" base. The requested work will ensure that the current street improvements currently being done will provide quality and durability to our pavements. CONTRACT ADJUSTMENT: As a result of this change order the contract price is adjusted as follows: 1. The contract price is increased in the amount of $72,633.99 from the current contract price of $1,023,439.77 to a new contract price of $1,096,073.76. 2. There is no increase in contract time due to this change order. Therefore the contract completion date established as Friday, February 25, 2005 remains the same. 3. This change order shall be considered full compensation for furnishing and installing the materials, labor, tools and equipment, profit, overhead, and all incidentals for performing the work described above. Frank and Son Paving, Inc. will not be entitled to damages or additional payment for delays as described in the 1997 edition of the Standard Specifications for Public Works Construction, Section 6-6.3, for perfoiuiing the work as described above. Page 2 CONTRACT CHANGE ORDER NO. 1 RECOMMENDED FOR APPROVAL BY: Albert riego, Ass Engineering APPROVED BY: Ms. Alicia Vasque , Pre dent Frank and Son Paving nc 1 ngineer Dat ank Vasquez, Vice Presi. nt Frank and Son Paving, Inc. Date Date Stephen M. Kirkp : tri '`k City Engineer Date Page 3 FRANK & SON Pa6inglnc' • ■ ■ • ■ ■ ■ a • ■ •a (619) 422 %322 COMPANY Frank & Son Paving, Inc. PROJECT Street Resurfacing Project FY 03-04, SPEC. 03-11 CONTRACT # ATTENTION ALBERT GRIEGO DATE 1/28/05 DATE PERFORMED NOV. 22-JAN. 28 NOV. 22-JAN. 28 NOV. 22-JAN. 28 NOV. 22-JAN. 28 NOV. 22-JAN. 28 NOV. 22-JAN. 28 Nov. 23,2004 DESCRIPTION #8 R&R AC only (3") #9 Pavement Milling #11 AC only #16 R&R Sidewalk #18 R&R Curb & Gutter #22 R&R Driveway "6" Avenue LABOR: EQUIPMENT: Nov. 29,2004 Dee. 03,2004 cceptable subgrad 5 hours 1.5 hours 5 hours 1.5 hours 5 hours 1.5 hours 5 hours 1.5 hours 2.5 hours 5 hours 5 hours 5 hours NOTE: All work performed and described above is outside of the original contract price. Please submit change order to my attention to process. LTC. #62545 1019 Third Ave. Chula Vista, CA 91911 (619) 422-8322 FAX (619) 420-9020 QUANTITY 55.68 tons 4,076 L.F. 547.76 tons 1,226.43 S.F. 121.30 L.F. 2,515 S.F. between E. 18th & E.19th (Una (2)Traffic Tech. (2) Over time Traffic Tech. (2) Operators (2) Over Time Operators (3) Labors (3) Over time Labors (1) Teamster (1) Over Time Teamster (1) Foreman Skiploader 10-12 Ton Roller C.W.T. (Stanby Time) E. 20th Street from "C" to "D" Ave.(Remove existing subgrade replace with LABOR: (1) Foreman 1 hour $ 44.04 (2) Operators 1 hour $ 44.04 (2) Traffic Tech 1 hour $ 30.33 (2) Labors 1 hour $ 30.33 EQUIPMENT: Skiploader 1 hour $ 25.00 10-12 Ton Roller 1 hour $ 40.00 Dump Truck 1 hour $ 75.00 Tool Truck 1 hour $ 70.00 AC Paver PF 180 1 hour $ 150.00 Superior Ready Mix (Stanby time) 1 hour $ 20.00 Pavement Recycling (Stanby time) 1 hour $ 1,262.53 UNIT PRICE 55.00 1.13 47.70 6.50 25.00 8.00 TOTAL $ 3,062.40 $ 4,605.88 $ 26,128.15 $ 7,971.80 $ 3,032.50 $ 20,120.00 e, deeplift of caly pumping) $ 30.33 $ 303.30 $ 45.49 $ 136.46 $ 44.04 $ 440.40 $ 63.63 $ 190.88 $ 30.33 $ 454.95 $ 45.49 $ 204.69 $ 30.33 $ 151.65 $ 45.49 $ 68.23 $ 44.04 $ 110.10 $ 25.00 $ 125.00 $ 40.00 $ 200.00 $ 295.00 $ 1,475.00 E. 20th Street from "C" to "D" Ave.(Remove existing subgrade replace with LABOR: (1) Foreman 1 hour $ 44.04 (2) Operators 1 hour $ 44.04 (2) Traffic Tech 1 hour $ 30.33 (2) Labors 1 hour $ 30.33 EQUIPMENT: Skiploader 1 hour $ 25.00 10-12 Ton Roller 1 hour $ 40.00 Dump Truck 1 hour $ 75.00 Tool Truck 1 hour $ 70.00 AC Paver PF 180 1 hour $ 150.00 Superior Ready Mix (Stanby time) 1 hour $ 20.00 Pavement Recycling (Stanby time) 1 hour $ 1,262.53 TOTAL: 44.04 88.08 60.66 90.99 25.00 40.00 75.00 70.00 150.00 20.00 1,262.53 44.04 88.08 60.66 90.99 25.00 40.00 75.00 70.00 150.00 20.00 1,262.53 $ 72,633.99 AEETING DATE City of National City, California COUNCIL AGENDA STATEMENT March 1, 2005 AGENDA ITEM NO. 7 ITEM TITLE Resolution of the City of National City approving Change Order Number 1 for National City Resurfacing Project FY 03-04 in the amount of $72,633.99, Spec. No. 03-11 for costs attributable to deteriorated conditions in pavements, sidewalks, curbs, gutters, and driveways and the replacement of expansive soil base material, and authorizing the City Engineer to sign the change order PREPARED BY Alberto Griego DEPARTMENT Engineering EXPLANATION 336-4386 The City of National City is currently doing the overlay and resurfacing of several streets in the city. Engineering is recommending that bid items #8, #9, #11, #16, #18 and #22 be increased due to finding added deteriorated conditions in pavements, sidewalks, curb and gutter, and driveways. Engineering is also recommending the approval of $4,000 in added labor and equipment time due to replacement of expansive soil base materials. These circumstances were encountered on G Avenue from E.18th Street to E. 19th Street, on E. 20th Street from C to D Avenues and on E. 20th Street from J to L Avenues. The total amount of Contract Change Order Number 1 is $72,633.99, increasing the current cost of the project from $1,023,439.77 to $1,096,073.76, which is below the total estimated cost of the project of $1,237,988.07 which included contingencies, materials testing, inspection and surveying. ( Environmental Review Financial Statement X N/A Approved By: t' This amount is within the estimated budget for this project. Funding is �t// available through Account Number 109-409-500-598-6035 and 307-409-500-598-6035. Account No. STAFF RECOMMENDATION Adopt the Resolution. BOARD / COMMISSION RECOMMENDATION N/A. ATTACHMENTS ( Listed Below ) 1. Resolution 2. Contract Change Order No. 1 Finance Director Resolution No. -Loos--LE° 3. Change Order from Frank & Son, Inc. cc103-11 A-200 (9 99) RESOLUTION NO. 2005 — 40 RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY AUTHORIZING THE CITY ENGINEER TO EXECUTE CHANGE ORDER NO. 1 WITH FRANK & SON PAVING, INC. IN THE AMOUNT OF $72,633.99 FOR COSTS ATTRIBUTABLE TO DETERIORATED CONDITIONS IN PAVEMENTS, SIDEWALKS, CURBS, GUTTERS AND DRIVEWAYS, AND THE REPLACEMENT OF EXPANSIVE SOIL BASE MATERIAL (ENGINEERING SPECIFICATION 03-011) WHEREAS, the contract for the National City Street Resurfacing Project was awarded to Frank & Son, Inc. on August 17, 2004, by the adoption of Resolution No. 2004-163; and WHEREAS, Change Order No. 1, in the amount of $72,633.99, is necessary to cover costs attributable to deteriorated conditions in pavements, sidewalks, curbs, gutters and driveways, and the replacement of expansive soil base material. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of National City hereby authorizes the City Engineer to execute Change Order No. 1 with Frank & Son, Inc. in the amount of $72,633.99 to cover costs attributable to deteriorated conditions in pavements, sidewalks, curbs, gutters and driveways, and the replacement of expansive soil base material. PASSED and ADOPTED this 1st day of March, 2005. ATTEST: Mi el Dalla, ity Clerk ca APPROVED AS TO FORM: George H. Eiser, III City Attorney Passed and adopted by the Council of the City of National City, California, on March 1, 2005, by the following vote, to -wit: Ayes: Councilmembers Inzunza, Morrison, Natividad, Parra, Zarate. Nays: None. Absent: None. Abstain: None. AUTHENTICATED BY: NICK INZUNZA 4flf City Clerk of the City of iational City, California By: Deputy I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of RESOLUTION NO. 2005-40 of the City of National City, California, passed and adopted by the Council of said City on March 1, 2005. City Clerk of the City of National City, California By: Deputy