HomeMy WebLinkAbout2005 CON Jaynes Corporation - Library Construction Change Order #10CHANGE ORDER C/O Number: 010
TO (Contractor): Jaynes Corporation C/O Initiation Date: June 1, 2005
111 Elm Street 4th Floor Project: National City Public Library
San Diego, California 92101 Contract No.: 1028
A Change Order is hereby recommended for the following work in the amount identified in this document:
DESCRIPTION OF CHANGE:
Twenty -Three calendar day Time Extension to the project duration.
Original contract duration: 395 Calendar Days
Revised contract duration: 442 Calendar Days
REASON FOR CHANGE: Accumulated Rain days exceeded the allotted number of Rain days
contained in the original project construction schedule. All the requested rain/delay days had significant
impact on critical path construction activities with in the overall construction schedule. The time extension
has a "No Cost" impact to the General Contract dollar amount.
Rain Days: October 19, 20, 27 and 28, 2004
November 11, 2004
December 7, 8, 9, 28, 29, 30 and 31, 2004
January 3, 4, 5, 6, 7, 10, 11, 12, 13, 14, 17, 18, 19, 20, 21 and 27, 2005
COST RECONCILIATION: NO COST ($0.00)
Costs were reviewed by the architect and City and negotiated to the satisfaction of the City.
Construction Contract Accounting Summary:
The Original Contract Amount $11,476,444.00
Net change by previously authorized Change Orders $ 278,088.00
Revised Contract Amount due to previous Change Orders $ 11,754,532.00
With this Change Order request the Contract cost is not effected by any costs. $ 0.00
New Revised Contract Amount $ 11,754,532.00
Change in Contract Time: 23 Calendar days
Contract Completion Date: Many 23, 2005
Recommen d Jpr Appro y:
PR.JECT ARCHITECT / Carrier Johnson
ICe�I..I4u.inli. Proeer rehiteet-
App ove / / /
"l�^J-•
CONTRACTOR/ Jaynes Corporation
Rick Cohen; Senior Viceside
Ch
OWNER/ City Of/Na'jional City
Steve Kirkpatric
DATE
cs—
ector of Public Works/City Engineer
Distribution: City Of National City (original w/all documentation)
Jaynes Corporation (copy w/all documentation)
DEB, Inc. (copy w/all documentation)
Carrier Johnson Architecture (copy w/all documentation)
DATE