2005 CON HMS Construction Inc - Change Order #2 Calmoor Traffic Signal
CONTRACT CHANGE ORDER NO. 2 HMS CONSTRUCTION, INC. DATE: 6/21/05 JUN 1 3 2005 PROJECT: Sweetwater Rd. at Calmoor St. and Fairlomas Drive, Specification No. 03-10 TO: Mr. Michael High, President HMS Construction, Inc. 1225 Linda Vista Drive San Marcos, CA 92069 DESCRIPTION OF CHANGE: This change order is written to add item number 9 to the contract (shown below). Current Contract Adjusted Contract (CO #1) No Item Unit Bid Qty Unit Price Amount Bid Qty Unit Price Amount 1 Mobilization LS 1 $1,500.00 $1,500.00 1 $1,500.00 $1,500.00 2 Traffic Control LS 1 $2,000.00 $2,000.00 1 $2,000.00 $2,000.00 3 Remove Concrete SF 750 $8.00 $6,000.00 750 S8.00 $6,000.00 4 Access Ramp EA 6 $1,340.00 $8,040.00 6 $1,340.00 S8,040.00 5 Traffic Signal Installation LS 1 $100,890.00 $100,890.00 1 $100,890.00 S100,890.00 6 Traffic Stripping LS 1 $5,900.00 $5,900.00 1 $5,900.00 $5,900.00 7 Traffic Signing LS 1 $860.00 $860.00 1 $860.00 $860.00 8 Removal and Replacement of Block Wall LS 1 $4,970.00 $4,970.00 9 Modified footing for traffic sdignal locations I and J LS 1 $7,999.28 $7,999.28 otals $125,190.00 $138,159.28 DISCUSSION: This increase in contract price is due to change in footing construction due to existing storm drain pipes found underneath the southwest sidewalk. This change order will modify the footings for traffic signal locations I and J. The footings will be a pad footing measuring 6 by 6 feet for location I and a pad footing measuring 7 by 7 feet for location J. This change order will modify the block wall to provide a minimum of 48" of space and replacement of sidewalk. CONTRACT ADJUSTMENT: As a result of this change order the contract price is adjusted as follows: 1. The contract price is increased in the amount of $7,999.28, from the current contract price of $130,160.00 to a new contract price of $138,159.28. Page 1 CONTRACT CHANGE ORDER NO. 2 2. The contract time is increased by Ten (10) working days. A Notice to Proceed was given previously on Monday November 8, 2004, to do out of sequence work such as installation of conduit for traffic loops prior to installation of street and sidewalks by others. The time utilized was 10 working days. The remaining working days, including the increase in time is now Thirty (30) working days. This change order shall be considered full compensation for furnishing and installing the materials, labor, tools and equipment, profit, overhead, and all incidentals for performing the work described above. HMS Construction, Inc. will not be entitled to damages or additional payment for delays as described in the 1997 edition of the Standard Specifications for Public Works Construction, Section 6-6.3, for performing the work as described above. RECOMMENDED FO''PROVAL BY: Alberto Griego, A "soci e gineer Date APPROVED BY: Mr. Michaigh, Presid HMS Construction, Inc. &A1/0 Date /( 370 5 Mr. Ronald Schneider, Vice President D to HMS Construction, Inc. Stephen M. Kir at4ick, Cr ngineer Date Page 2 uiwuN/zuua rn:u 6:Za i'AA uu n115 uonstruction a...n.ran 1• iguu1/UU; vuc, 05/25/2005 WED 10:33 FAI 760 73: -158 HMS Construction t001!002 HMS CONSTRUCTION INC. ELECTRICAL & GENERAL SNGINEERITC CONTRACTOR #F. QUEST FOR CHANGE ORDER #2 'PAGE of 1 PROJECT / SWEET'WATER ROAD AND CALMOOR STREET/ FAIRLOMAS ROAD EAST TRAFFIC SIGNAL INSTALLATION. PER PLANS PROVIDED BY YOU. PER YOUR BEQUEST. BID DATE: May 25, 2005 PHONE 619-3364386 ATTN: Alberto Griego FAX 619-336-4397 $$ID ITEMS OUOTED TOTALS 1.) Added cost for new pole bases/footings, cages, rebar and all associated materials, labor and equipment needed per your demil provided. S7,999.28 INCLUDES: REBAR, CONCRETE, ITEMS LISTED ABOVE. LABOR. EQUIPMENT AND MATERIALS, TOTAL THIS QUOTATION: $7,999.28 By use of this otirtwte *will be ossahed to the sub-cenvxt as Wad # 1. Mid yule nciciae can be hcld 30 days. THIS FAX 1S CONSIDERED PRIVATE MAIL AND MAY NOT BE TRANSPERRED TOQTABR PARTIES WITHOUT PERMISSION PROM SENDER. IF YOU .RECEIVE THIS COMMUNICATION IN ERROR, PLEASE CONTACT US IMMEDIATELY_ ELY_ TANK YOU! HMS CONSTRUCTION INC.1225 UNDA VISTA DRIVE, SAN MARCOS. CA. PHONE (760) 736- 3093, PAX (760) 731- 6158, LIC. NO# A, B, C-10-765590 IF YOU SHOULD HAVE ANY QUESTIONS PLEASE CALL! THANK YOU, ROBERT TONES ESTIMATOR Copy/ to file HMS CONSTRUCTION COST PROPOSAL Contract No.:_04153 Date Performed: Dated Report: 5/25/05 REPORT 82 Work Performed By:_HMS CONSTRUCTION Description of Work ADDER FOR INSTALLATION OF MODIFIED TRAFFIC SIGNAL BASE INCLUDEING NEW REBAR AND CAGE WITH MODIFIED FOOTING PER DETAIL. Equip No. EQUIPMEIIT Hour Hourly Rate Extended Amounts IP_R.No. LABOR Hours Hourly Rite Extended Amounts UTILITY TRUCK 16.00 22.00 352.00 UTILITY TECH er. 0.00 0.00 UTILITY TRUCK 16.00 22.00 352.00 n.. 16.00 25.00 400.00 COMPRESSOR 16.00 14.52 232.32 UTILITY TECH or. 0.00 0.00 BACIGIOE 18.00 36.25 580.00 .ee. 16.00 25.00 400,00 0.00 0.00 SUPERINTENDANT O.r. 0.00 0.00 0.00 0.00 e■.. 16.09 45.00 720.00 - 0.00 0.00 ..r. 0.00 0.00 0.00 0.00 pe.. 0,00 0.00 0,00 0.00 o.r. 0.00 0.00 0,00 0.04 .e.. 0.00 0.00 0.00 0.01 o.t- 0.00 0.00 0.00 0.01 .... 0.00 0.00 SUBTOTAL 1,516.32 I at• O.OW, 0.00 .eo 0.00 0.00 i 4 s + sw-rau. 1.520.00 MATERIAL ANDIOR WORK DONE BY SPECIALISTS DESCRIPTION No. Unit Unit Cost Extended Labor Surcharge • (See Special Provisions} Subsistence No. © 36% 547.20 CONCRETE (YARDS) 5 139.00 695.00 REBAR 1 526.00 526.00 S CAGES 2 865.00 1,730.0D Travel Expense No. ril S 0.00 Other 0.0D - TOTAL COST OF LABOR 0.00 A 2,067.20 SUBTOTAL- 2,951.00 TOTAL COST OF EQUIPMENT, MATERIALS AND WORK ' 1 B 4,467.32 7.75 % SALES TAX (SEE CONTRACT) WORK 228.70 20 % MARKUP OM LABOR COSI /(A) (B) ( C SUBTOTAL ( D ) 413A4 Contractors Reptesentathe ACCEPTED FOR PROGRESS PAYMENT 15%MARKUP OREQUIPMENT 704A0 10 % MARKUP OW SUBCONTRACTED 1.5%BOND AND LIABILrTYINSURANCE 7,881.07 ResidenlEngineer 118.22 was oo.eunc.smst ,xcnwsu Resident Engineer TOTAL 7,999.28 City of National City, California COUNCIL AGENDA STATEMENT MEETING DATE June 21, 2005 6 AGENDA ITEM NO. ITEM TITLE Resolution of the City of National City approving Change Order Number Two to HMS \ Construction, Inc. for Sweetwater Rd. at Calmoor St. and Fairlomas Drive Traffic Signal Installation, Spec. No. 03- 10, in the amount of $7,999.28 for modification of foundation due to existing storm water pipes encountered under sidewalk and authorizing the City Engineer to approve and sign the change order. PREPARED BY Alberto Griego DEPARTMENT Engineering EXT. 4386 EXPLANATION See attached Explanation. CEnvironmental Review X N/A MIS Approval Financial Statement Approved By: /t "jQ �✓` The total budget for the project was estimated to be $156,487.50. Funding is available' $gtft24ccount Number 109-409-500-598-6161 and 307-409-500-598-6035 for this change order Account No. STAFF RECOMMENDATION Adopt the Resolution. BOARD / COMMISS 071 RECOMMENDATION N/A C loalf-3if d ua A.001/L2 ATTACHMENTS ( Listed Below) Resolution No. �. Resolution 2. Contract Change Order No. Two 3. Proposal from HMS Construction, Inc. HMS2 A-200 (Rev. 7/03) RE: Resolution of the City of National City approving Change Order Number Two to HMS Construction, Inc. for Sweetwater Rd. at Calmoor St. and Fairlomas Drive Traffic Signal Installation, Spec. No. 03-10, in the amount of $7,999.28 for modification of foundation due to existing storm water pipes encountered under sidewalk and authorizing the City Engineer to approve and sign the change order. Explanation: On August 3, 2004, by resolution No. 2004-141, the City Council awarded a contract in the amount of $125,190 to HMS Construction, Inc. for the Sweetwater Rd. at Calmoor St. and Fairlomas Drive Traffic Signal Installation, Specification No. 03-10. During excavation for the footings of traffic signal locations I and J, three storm drain pipes 66 inches in diameter were encountered at a depth of 6 feet 2 inches. The standard footing depth for each traffic signal is 8 feet. Engineering staff is recommending the approval of a change order to HMS Construction, Inc. in the amount of $7,999.28 for the modification of the standard footings to a 6 by 6 foot pad footing for traffic signal I and a 7 by 7 foot pad footing for traffic signal J per structural calculations provided by Tetra Tech, Inc. the engineering consultant. The total amount of Contract Change Order Number Two is $7,999.28, increasing the current cost of the project from $130,160 to $138,159.28, which is below the total estimated budget for the project of $156,487.50. RESOLUTION NO. 2005 — RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY AUTHORIZING THE CITY ENGINEER TO EXECUTE CHANGE ORDER NO. TWO WITH HMS CONSTRUCTION, INC. IN THE AMOUNT OF $7,999.28 FOR MODIFICATION OF THE FOUNDATION DUE TO EXISTING STORM WATER PIPES ENCOUNTERED UNDER SIDEWALK FOR THE SWEETWATER ROAD AT THE CALMOOR STREET AND FAIRLOMAS DRIVE TRAFFIC SIGNAL IMPROVEMENT PROJECT WHEREAS, the contract for the Sweetwater Road at Calmoor Street and Fairlomas Drive Traffic Signal Improvement Project was awarded to HMS Construction, Inc. on August 3, 2004, by the adoption of Resolution No. 2004-141; and WHEREAS, during excavation for the footings of traffic signal locations I and J, three storm drain pipes sixty-six inches (66") in diameter were encountered at a depth of six feet two inches (6'2"). The standard footing depth for each traffic signal is eight feet (8'); and WHEREAS, due to the storm drain pipes, modification of the standard footings to a six-foot by six-foot (6' x 6') pad footing for traffic signal I, and a seven -foot by seven -foot (7' x 7') pad footing for traffic signal J is required. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of National City hereby authorizes the City Engineer to execute Change Order No. 2 with HMS Construction, Inc. in the amount of $7,999.28 for the modification of the standard footings to a six-foot by six-foot (6' x 6') pad footing for traffic signal I, and a seven -foot by seven -foot (7' x 7') pad footing for traffic signal J at the Sweetwater Road at Calmoor Street and Fairlomas Drive Traffic Signal Improvement Project. PASSED and ADOPTED this 21st day of June, 2005. ATTEST: Nick Inzunza, Mayor APPROVED AS TO FORM: Michael R. Dalla, City Clerk George H. Eiser, III City Attorney CONTRACT CHANGE ORDER NO. 2 DATE: 6/21/05 PROJECT: Sweetwater Rd. at Calmoor St. and Fairlomas Drive, Specification No. 03-10 TO: Mr. Michael High, President HMS Construction, Inc. 1225 Linda Vista Drive San Marcos, CA 92069 DESCRIPTION OF CHANGE: This change order is written to add item number 9 to the contract (shown below). Current Contract Adjusted Contract (CO #1) No Item Unit Bid Qty Unit Price Amount Bid Qty Unit Price Amount 1 Mobilization LS 1 $1,500.00 $1,500.00 1 $1,500.00 $1,500.00 2 Traffic Control LS 1 $2,000.00 $2,000.00 1 $2,000.00 $2,000.00 3 Remove Concrete SF 750 $8.00 $6,000.00 750 $8.00 $6,000.00 4 Access Ramp EA 6 $1,340.00 $8,040.00 6 $1,340.00 $8,040.00 5 Traffic Signal Installation LS 1 $100,890.00 $100,890.00 1 $100,890.00 $100,890.00 6 Traffic Stripping LS 1 $5,900.00 $5,900.00 1 $5,900.00 $5,900.00 7 Traffic Signing LS 1 $860.00 $860.00 1 $860.00 $860.00 g Removal and Replacement of Block Wall LS 1 $4,970.00 $4,970.00 9 Modified footing for traffic sdignal locations 1 and J LS 1 $7,999.28 $7,999.28 Totals DISCUSSION: $125,190.00 This increase in contract price is due to change in footing construction due to existing storm drain pipes found underneath the southwest sidewalk. This change order will modify the footings for traffic signal locations I and J. The footings will be a pad footing measuring 6 by 6 feet for location I and a pad footing measuring 7 by 7 feet for location J. This change order will modify the block wall to provide a minimum of 48" of space and replacement of sidewalk. CONTRACT ADJUSTMENT: As a result of this change order the contract price is adjusted as follows: 1. The contract price is increased in the amount of $7,999.28, from the current contract price of $130,160.00 to a new contract price of $138,159.28. Page 1 138,159.28 • CONTRACT CHANGE ORDER NO. 2 2. The contract time is increased by Ten (10) working days. A Notice to Proceed was given previously on Monday November 8, 2004, to do out of sequence work such as installation of conduit for traffic loops prior to installation of street and sidewalks by others. The time utilized was 10 working days. The remaining working days, including the increase in time is now Thirty (30) working days. This change order shall be considered full compensation for furnishing and installing the materials, labor, tools and equipment, profit, overhead, and all incidentals for performing the work described above. HMS Construction, Inc. will not be entitled to damages or additional payment for delays as described in the 1997 edition of the Standard Specifications for Public Works Construction, Section 6-6.3, for performing the work as described above. RECOMMENDED FO' ' PROVAL BY: Alberto Griego, A soci gineer Date APPROVED BY: Mr. Michael High, President Date HMS Construction, Inc. Mr. Ronald Schneider, Vice President Date HMS Construction, Inc. Stephen M. Kirkpatrick, City Engineer Date Page 2 U-U/U /ZUU .rnu 5:ei rAi 1UU (j.1 61.0 nnm construction. VJI LJI VJ ai. JJ011 05I25/2005 1'ED 10:33 FAX 760 73' 158 35 Construction HMS CONSTRUCTION INC. ELECTRICAL a G]BNEEJtL RNGlNEtRtrN; coma ro& VEST FQ,ESAN ;UMDER #2 1 PAGE or 1 PROJECT / SWEETWATER ROAD AND CALMOOR STREET/ FAIRLOMAS ROAD EAST TRAFFIC SIGNAL INSTALLATION. PER PLANS PROVIDED BY YOU. PER YOuUR REQUEST. Bro DATE: May 25„ 2005 PRONE 619-336.4386 ATTN: Alberto Griego FAX 619-336.4397 ND ITEMS SILIQI D TOTALS 1.) Added cola fbr new pale bases/footings, cages, rebar and all associated materials, Iabor and equipment needed per your detail provided. S7,999.28 INCLUDES: ItEBAR, CONCRETE, ITEMS LISTED ABOVE. LABOR., EQUIPMENT .A.ND MATB [AJ.S. 110T.AL THIS QUOTATION:, $7,999.28 Ey1 use adds esdrta,ui it will be eftehed to the sub comma es exhibit q 1. Thu quote, ermine can be held 30 days, TIES FAX IS CONSIDERED PRIVATE MAIL AND MAY NOT RIR TRANSFERRED TOOTHER PARTIES WITHOUT PERMS:MON PROM SENDER. YOU RECEIVE THIS COMMITNICA.TIONINERROR, PLEASE OC)NTACr US NdMEDIIATELY. THAN![ YOU! EMS CO TRUCTION iNC.1225 LINDA VISTA DRIVE, SAN MARCOSS, CA. PHONE (760) 736- 3093, PAY (760) 731- 6158, LIC. NO8 A, B, C-10-765590 IF YOU SHOULD HAVE ANY QUESTTONS PLEASE CALL! THANK YOU, ROBERT JOKES ESTIMATOR Copy/ to file TluuI/uoi . . waaq 40010002 nma Uonstrucl;ion Ub/Uy/LUUO TAU b:13 t'JA IOU 131 Oi00 HMS CONSTRUCTION COST PROPOSAL C,onsac No,: 04153 Date Performed: Date of Report: 5125105 REPORT # 2 Work renamed tsy._HMS CONSTRUCTION Description of Work: ADDER FOR INSTALLATION OF MODWIED TRAFFIC SIGNAL BASE INCLUDEING NEW REBAR AND CAGE WITH MODIFIED FOOTING PER DETAIL. Equip No. EQUIPMENT Hours Hourly Rate Extended Amounts P.R. Ht. LABOR Hours Hourly Rate Extended Amounts UTILITY TRUCK 16.00 22.00 352.00 UTILITY TECH s er. 0.00 0.00 UTILITY TRUCK 16.00 22.00 352.00 MM. 16.00 25.00 400.00 COMPRESSOR 16.00 14.52 232, UTILITY TECH or. 0.00 0.00 BACIG$OE 16.00 30.25 580.00 .Te. 16.00 25.00 400.00 D.00 0.00 SUPERINTENDANT o.r. 0.00 0.00 0.00 0.00 in. 16.00 720,00 0.00 0.00 o.T. 0.00 0.00 0.00 0.0 .Me. 0.00 0.0 0.00 0. Y.T. 0.00 0.00 0.09 0.00 Ma. 0.00 0.0 000 0.00 Y.T. 0.00 0.00 0.00 0.00 MM. 0.00 0.00 SUBTOTAL 1 1,516.32 o.T. 0.00 0.00 Iva 0.00 OAO + + + + + sw•TOTJL 1.520.00 MATERIAL ANDJOR WORK DONE BY $PECIAUSTS DESCRIPTION No. Unit Unit Cost Extended Labor Surcharge- (See Special Provisions) Subsistence No. Q 36% 547.20 CONCRETE (YARDS) 5 139.00 695.00 MBAR 1 526.00 526.00 S CAGES 2 865.00 1,730.00 Travel Expense No. 0 S 0.00 Other 0.00 - TOTAL COST OF LABOR 0.0 A 2067.20 SUBTOTAL 2,951.00 TOTAL COST OF EQUIPMENT, MATERIALS AND WORK ' < B 4,467.32 7.75 %SAL6s TAX 0 (SEE CONTRACT} WORK 228.70 20 %MARKUP ON LABOR COST /(A) ( B ) (T+ ) SUBTOTAL ( D) 413.44 Contractors Representative ACCEPTED FOR PROGRESS PAYMENT 15%MARKUP ONEQUIPMENT 704A0 10 %MARKUP ON SUBCONTRACTED 1.5 % BOND AND LIABILITY INSURANCE 7,881.07 Resider£ngineer 118.22 WON. OO'Eufl! OROT®1 INCTWfl Resider Engineer TOTAL 7,999.28