HomeMy WebLinkAbout2005 CON C.C. Serv. Inc. - Restroom Renovation Change Order #1City of National City, California
COUNCIL AGENDA STATEMENT
MEETING DATE June 21, 2005
7
AGENDA ITEM NO.
ITEM TITLE
Resolution of the City of National City approving Change Order Number 1 for Las Palmas
Park Restroom Re -roofing and Renovation, Specification No. 04-3, in the amount of $9,276.88 for costs
attributable to stucco, new coat of paint, and installation of new sewer vents and authorizing the City Engineer to
sign the change order.
PREPARED BY Alberto Griego DEPARTMENT Engineering EXT. 4386
EXPLANATION
See attached Explanation.
L
i
X
Environmental Review N/A
MIS Approval
Financial Statement
Approved By:
This amount is within the estimated budget for this project of $32,000.
Funding is available through Account Number 271-409-500-598-4126.
Fi ce Director
Account No.
STAFF RECOMMENDATION
Adopt the Resolution.
B'AR
N/A
ATTACHMENTS ( Listed Below )
t. Resolution 2. Contract Change Order No. 1 3. Change Order from C.C. Serv., Inc. las
C LDQtf 33
e4, 490.7-t 3
A-200 (Rev. 7/03)
Resolution No.
RE: Resolution of the City of National City approving Change Order Number 1 for Las Palmas Park
Restroom Re -roofing and Renovation, Specification No. 04-3, in the amount of $9,276.88 for costs
attributable to stucco, new coat of paint, and installation of new sewer vents and authorizing the City
Engineer to sign the change order.
Explanation:
The City of National City is currently doing the Las Palmas Park Re-roofmg and Renovation Project. The
existing exterior walls are in deteriorated condition and concrete in the joints between the blocks in the
wall do not provide a good aspect of this surface. The interior and exterior require a fresh coat of paint.
The contractor will grind existing excess grout, water -blast walls, apply one coat of stucco and finish with
paint. Also included are new sewer vents. Engineering is recommending that the original contract be
increased by $9,276.88 to repair these conditions.
The total amount of Contract Change Order Number One is $9,276.88, increasing the current cost of the
project from $20,708.14 to $29,985.02.
On July 20, 2004 a City Council Resolution was awarded for this project. In this resolution it was stated
that approximately 20% ($6,400) was to be used for contingencies and approximately 15% ($4,891.86)
for inspection. Engineering staff did the inspection therefore saving the amount money assigned for
inspection. It is requested that $ 2,876.88 from the inspection money be added to the contingencies to pay
for this change order.
RESOLUTION NO. 2005 ā
RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF NATIONAL CITY
AUTHORIZING THE CITY ENGINEER TO EXECUTE
CHANGE ORDER NO. 1 IN THE AMOUNT OF $9,276.88 FOR STUCCO,
NEW COAT OF PAINT, AND INSTALLATION OF NEW SEWER VENTS
FOR THE LAS PALMAS PARK RESTROOM RE -ROOFING
AND RENOVATION PROJECT
WHEREAS, the contract for the Las Palmas Park Restroom Re -roofing
and Renovation Project was awarded to C.C. Serv, Inc. on July 20, 2004, by the
adoption of Resolution No. 2004-126; and
WHEREAS, during the construction of this project it was revealed that the
existing exterior walls and roof are in a deteriorated condition
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City
of National City hereby authorizes the City Engineer to execute Change Order No. 1
with C.C. Serv, Inc. in the not to exceed amount of $9,276.88 for stucco, new coat of
paint, and installation of new sewer vents for the Las Palmas Park Restroom Re -
Roofing and Renovation Project.
PASSED and ADOPTED this 21st day of June, 2005.
Nick Inzunza, Mayor
ATTEST:
Michael Dalla, City Clerk
APPROVED AS TO FORM:
George H. Eiser, III
City Attorney
CONTRACT CHANGE ORDER NO. 1
DATE: 6/21/05
PROJECT: Las Palmas Park Restroom Re -roofing and Renovation
Specification No. 04-3
TO:
Mr. Brian R. Barber, Vice President
C. C. Serv. Inc.
1315 Cleveland Street
Oceanside, CA 92054
DESCRIPTION OF CHANGE:
This change order is written to add item numbers 5,6 and 7 to the contract (shown
below).
Current Contract
Adjusted Contract
(CCO #1)
No
Item
Unit
Bid Qty
Unit Price
Amount
Bid
Qty1
Unit Price
Amount
1
Mobilization
LS
1
$1,353.00
$1,353.00
$1,353.00
$1,353.00
2
Removal, Disposal, and
Replacement of Roof
SF
980
$12.76
$12,505.14
980
$12.76
$12,505.14
3
Construction of Wall Extension
SF
54
$60.19
$3,250.00
54
$60.19
$3,250.00
.,,4
Lights
EA
8
$450.00
$3,600.00
8
$450.00
$3,600.00
5
Exterior Stucco and wall
preparation
SY
200
$37.50
$7,500.00
6
Paint
SF
1,868
$0.54
$1,000.00
7
Instalation of Vents
EA
2
$388.44
$776.88
Totals
$20,708.14
$29,985.02
DISCUSSION:
The City of National City is currently doing the Las Palmas Park Re -roofing and
Renovation Project. The existing exterior walls are in deteriorated condition and concrete
in the joints between the blocks in the wall do not provide a good aspect of this surface.
The interior and exterior request a fresh coat of paint including new wood roof rafters and
beams. The contractor will grind existing excess grout, water -blast walls, apply one coat
of stucco and finish with paint and install 2 new sewer vents. Also included is the
replacement of rotted steel post and base and painting of the interior and exterior side tool
room door. Engineering is recommending that the original contract be increased by
$9,276.88 to repair these conditions.
CONTRACT ADJUSTMENT:
As a result of this change order, the contract price is adjusted as follows:
1. The contract price is increased in the amount of $9,276.88, from the current
contract price of $20,708.14 to a new contract price of $29,985.02.
Page 1
CONTRACT CHANGE ORDER NO. 1
2. The contract time is increased by Fifteen (15) working days. A Notice to
Proceed was given previously on Monday, November 29, 2004, to initiate work.
The contract time is also increased by Twenty Two (22) working days due to
the heavy rains that affected the region. Due to the increase of workload from
contract change order number one and the rain season, the completion date was
set for Thursday, March 16, 2005.
Project was delayed for another Thirty (30) working days due to changes of their
Project Manager in two separate occasions. This delay was requested verbally by
the Contractor. The final completion date is set for Friday May 06, 2005.
This change order shall be considered full compensation for furnishing and installing the
materials, labor, tools and equipment, profit, overhead, and all incidentals for performing
the work described above. C.C. Serv, Inc. will not be entitled to damages or additional
payment for delays as described in the 1997 edition of the Standard Specifications for
Public Works Construction, Section 6-6.3, for performing the work as described above.
RECOMMENDED F PROVAL BY:
Alberto Gr
, Associa
APPROVED BY:
neer
Brian Barber, Senice President
C.C. Serv, Inc.
nffin,
Serv, Inc.
ident
Date
Date
-9 -as--
Date
Stephen M. Kirkpatrick, P.E. Date
City Engineer of the City of National City
Page 2
Jun OU Llb U:J:;it.,a
tax
619424132BU
p.2
C.C. Serv., Inc.
1315 S. Cleveland
Oceanside CA 92054
780-754-6300
Billed To: City of National City
Engineering Department
1243 National City Blvd.
Naliiiuonal City CA 91950
License: 762854
Invoice
Invoice#: 2581-2
Date: 04/10/2005
Project: Las Palmas Park Remodel
1243 National City Blvd
National City CA 91950
Due Date: 04/30/2005
Terms: 20DY Order#
Description Amount
Change Order#1 - 100% Completion 9,276.88
Change Order approved 03/15/05
Waterblasted walls, applied bonder coat. brown cement and coat of stucco,
finished with a standard color. Approximately 200 square yards.: 57.500.00
Paint approximately 1,868 square feet of surface area.: $1,000.00
Instalation of new vents 2@ $388.44 = $776.88
.Ai service charge of 1.50 % per annum will be charged on all amounts
overdue on regular statement dates.
Thank you for your prompt payment(
Non -Taxable Amount:
Taxable Amount:
Sales Tax:
9,276.88
0.00
0.00
Amount Due 9,276.88
Jun 08 US U J:J1a Fax
3e 2420..xs2 C o,
C.C. Serv., Inc. Change Order Rifiuest
Date: 05-17-05
Owner: City of National City
Project #: 2581
C.O. #: 001
Project Location: Las Palmas Park
Change (add/delete) the following work to the original contr& re :
J
C. C. Serv. Ina.
No.
5
6
7
Item Only
Stucco and wall
preparabon
Paint
Inslalalion of
new vents
200
1,868
2
Unit
SY
SF
EA
Change Order No..1
Unit Price
$37.50
$0.54
$385, 44
Amount
$7,$00.00
$1.000.00
S776.88
Total Change Order No. 1
59,276.53
'Change the original contract amount by + $
Payment terms as follows:
We agree to furnish labor & materials complete in accordance 'YviM the above
s. - tcatio (price stated above.
Ci5/18/05
Date
Above additional work to be performed under the saute condit'h n.i as specified in the
original contract unless otherwise stipulated.
Owner Represented.
])ate
C.C. Serv., Inc.
1315 South Cleveland St.
Ocean Side, CA. 92054
(760) 754-6300 fax (760) 757-8424
7t52654 D.O.S.H 629
B-1, C-2,, C-21 ASB, HAZ
Trslurrlla Waste Mgrnt. 047
II(:RC # 40935
room nā.a s nn
RESOLUTION NO. 2005-123
RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF NATIONAL CITY
AUTHORIZING THE CITY ENGINEER TO EXECUTE
CHANGE ORDER NO. 1 IN THE AMOUNT OF $9,276.88 FOR STUCCO,
NEW COAT OF PAINT, AND INSTALLATION OF NEW SEWER VENTS
FOR THE LAS PALMAS PARK RESTROOM RE -ROOFING
AND RENOVATION PROJECT
WHEREAS, the contract for the Las Palmas Park Restroom Re -roofing
and Renovation Project was awarded to C.C. Serv, Inc. on July 20, 2004, by the
adoption of Resolution No. 2004-126; and
WHEREAS, during the construction of this project it was revealed that the
existing exterior walls and roof are in a deteriorated condition
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City
of National City hereby authorizes the City Engineer to execute Change Order No. 1
with C.C. Serv, Inc. in the not to exceed amount of $9,276.88 for stucco, new coat of
paint, and installation of new sewer vents for the Las Palmas Park Restroom Re -
Roofing and Renovation Project.
PASSED and ADOPTED this 21 st day of June, 2005.
ick Inzunza, Mayor
ATTEST:
elD
Mich
Mi alt a, ity Clerk
APPROVED AS TO FORM:
George H. Eiser, III
City Attorney
Passed and adopted by the Council of the City of National City, California, on June 21,
2005, by the following vote, to -wit:
Ayes: Councilmembers Inzunza, Morrison, Natividad, Parra, Zarate.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: NICK INZUNZA
By:
Mayor of the City of National City, California
MICHAEL R. DALLA
City Clerk of the City of National City, California
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2005-123 of the City of National City, California, passed and
adopted by the Council of said City on June 21, 2005.
By:
City erk of the City f National City, California
Deputy