HomeMy WebLinkAbout2006 CON MJC Construction - Paradise Creek Educational Park Change Order #2CHANGE ORDER C/O Number 2 To (Contractor): California C/O Initiation Date: August 30, 2006 MJC Construction, Project: Paradise Creek Education Park Project Specification No.: 04-5 A Change Order is hereby recommended for the following work in the amount identified in this document: DESCRIPTION OF CHANGE: This change order is to exclude the Additive Alternatives A4 (Central Boardwalk) & A5 (Boardwalk Connections) from the original contract in the amount of $315,000 (Lump Sum) and complete the installation of the North/South Boardwalk (T&M) in a not to exceed amount of $315,000. The change order includes installation of galvanized steel cable rail and completes the installation of the North/South Boardwalk for the lump sum amount of $315,000 which includes all time, materials and equipment used and expended by the contractor for all boardwalk installation to date. Additionally, the contractor will install the cable rail per the design of the sample submittal using galvanized metal for the posts and rails. COST RECONCILATION: The changes were reviewed by the City Project Manager and negotiated with the Contractor. Construction Contract Accounting Summary: The original Contract Amount $ 1,008 900.00 Net change by previously authorized Change Orders $ 150.000.00 The Contract Amount prior to this Change Order $ 1,158,900.00 With the Change Order request the contract cost will remain unchanged New Contract Amount S 1,158,900.00 Change in Contract Time: Contract Completion Date: Recommended for Approval by: /0/171/a CITY PROJECT MANAGI4( DATE Approved by: CONTRACTO CITY OF N • 1'I A NAL CITY CC: Construction File Inspector DATE DATE 118 Working Days September 5, 2006 RESOLUTION NO. 2006 - 203 RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY AUTHORIZING THE CITY ENGINEER TO EXECUTE CHANGE ORDER NO. 2 WITH MJC CONSTRUCTION, INC., TO EXCLUDE THE ADDITIVE ALTERNATIVES A4 AND A5 (CENTRAL BOARDWALK AND CONNECTIONS) FROM THE ORIGINAL CONTRACT, AND ADD THE NORTH/SOUTH (NEW ALIGNMENT) BOARDWALK BASED ON TIME AND MATERIALS WITH NO CHANGE IN THE COST FOR THE PARADISE CREEK PARK PROJECT WHEREAS, the contract for the construction of the first phase of the Paradise Creek Educational Park was awarded to MJC Construction, Inc., on August 16, 2005, by the adoption of Resolution No. 2005-179; and WHEREAS, on December 20, 2005, the City Council approved Change Order No. 1, in the not to exceed amount of $150,000, for the removal and disposal of approximately 1,500 cubic yards of contaminated soil from the Paradise Creek site in accordance with State and federal regulations; and WHEREAS, during the installation of raised boardwalks and pile driving along the west side of Paradise Creek, the contractor discovered layers/pieces of hard material at various design depths and locations that resulted in a new boardwalk alignment based on Time and Materials; and WHEREAS, due to the shift in the original alignment of the boardwalks and piling shaft locations, the central boardwalk and connection (additive Alternates A4 and A5) were adjusted accordingly and designated by the new alignments as the north/south and east/west boardwalk; and WHEREAS, Change Order No. 2 is necessary to exdude the Additive Altematives A4 and A5 (Central Boardwalk and Connections) in the amount of $315,000 from the original contract, and add the installation of the north/south (new alignment) boardwalk based on Time and Materials, In a not to exceed amount of $315,000. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of National City hereby authorizes the City Engineer to execute Change Order No. 2 with MJC Construction, Inc., to exdude the Additive Alternatives A4 and A5 (Central Boardwalk and Connections) In the amount of $315,000 from the original contract, and add the installation of the north/south (new alignment) boardwalk based on Time and Materials, in a not to exceed amount of $315,000. ATTEST: PASSED and ADOPTED this 3rd day of October, 2006. Nick Inz APPROVED AS TO FORM: Mi el Della, Ci Cle George FT-Eier, III City Attorney Passed and adopted by the Council of the City of National City, Califomia, on October 3, 2006, by the following vote, to -wit: Ayes: Councilmembers Inzunza, Morrison, Natividad , Parra, Zarate. Nays: None. Absent: None. Abstain: None. AUTHENTICATED BY: NICK INZUNZA Mayor of the City of National City, California City CI of the City National City, Califomia By: Deputy I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of RESOLUTION NO. 2006-203 of the City of National City, California, passed and adopted by the Council of said City on October 3, 2006. City Clerk of the City of National City, Califomia By: Deputy City of National City, California COUNCIL AGENDA STATEMENT MEETING DATE October 3, 2006 AGENDA ITEM NO. 3 ITEM TITLEResolution of the City Council of National City approving Change Order Number Two with MJC Construction to exclude the Additive Alternatives A4 and A5 (Central Boardwalk and Connections) from the original contract and add the north/south (new alignment) boardwalk based on Time and Material (T&M) method with no change in the cost for the Paradise Creek Education Park Project PREPARED BY Din Daneshfar DEPARTMENT Engineering EXT•4337 EXPLANATION See attached explanation. Environmental Review X N/A MIS Approval Financial Statement N/A Approved By: Finance Director Account No. STAFF RECOMMENDATION Adopt the Resolution. BOARD / COMMISSION RECOMMENDATION N/A ATTACHMENTS ( Listed Below) Resolution No. 2C.x)& ' 203 1. Resolution 2. Change Order Number 2 A-200 (Rev. 7/03) Re: Resolution of the City Council of National City approving Change Order Number Two with MJC Construction to exclude the Additive Alternatives A4 and A5 (Central Boardwalk and Connections) from the original contract and add the north/south (new aligmnent) boardwalk based on Time and Material (T&M) method with no change in the cost for the Paradise Creek Education Park Project On August 16, 2004, the City Council by Resolution Number 2005-179 awarded a contract to MJC Construction in the amount of $1,008,900 for the construction of the first phase of the Paradise Creek Education Park. On September 19, 2005, the construction of the project began. On December 20, 2005, the City Council approved the Change Order Number One in the not to exceed amount of $150,000 for the removal and disposal of contaminated soils from the site. During the installation of the raised boardwalks and pile driving along the west side of Paradise Creek, the Contractor encountered layers/pieces of hard material at various design depths and locations. These new conditions made the excavation very difficult and time consuming, and resulted in suspension of the pile setting construction activities. The Contractor had to find the drillable spots by trial and error. This area used to be a dumpsite and considered to be an environmentally sensitive site. These conditions were reviewed and checked against the existing soils report. The findings were that the material testing included only random sampling spots and did not address the soils condition at various depths within the construction area. After having a number of meetings with the Contractor, the City and the Contractor came to a conclusion that the Additive Alternatives A4 and AS (Central Boardwalk and Connections) be excluded from the original contract and the work be completed with a new boardwalk alignment based on Time and Materials (T&M). Due to the shift in the original alignment of the boardwalks and piling shaft locations, the central boardwalk and connections (Additive Alternates, A4 and A5) were adjusted accordingly and designated by the new alignments as the north/south (260 ft) and east/west (160 ft) boardwalk. On April 4, 2006, the Contractor started the T&M work, however, the work had to be suspended on August 7, 2006 in order to avoid a cost overrun. Currently, the seventy five percent (75%) of the work has been completed on the north/south boardwalk. Based on the staff's negotiation with the Contractor, it is recommended to complete the work as outlined by the following two change orders: • Change Order Number Two (attached) will exclude the Additive Alternatives A4 and A5 (Central Boardwalk and Connections) from the original contract in the amount of $315,000 (Lump Sum) and add the installation of the north/south (new alignment) boardwalk based on Time and Material (T&M) method in a not to exceed amount of $315,000. alignment) boardwalk based on Time and Material (T&M) method in a not to exceed amount of $3.15,000. • The Change Order Number Three will add the east/west (new Alignment) boardwalk which has been presented to the City Council as a separate item at tonight's meeting agenda. In order to complete the north/south boardwalk some of the actual improvements design will be deviated from the original plans. The main deviation will be the alignment of the boardwalk and locations of the piling shafts that will be changed to avoid the conflict with the hard subsurface material. Another major deviation will be removing the installation of the red brass railing and replacing it with a galvanized steel cable rail. The red brass railing can be very attractive target for vandalizing and costly for maintenance. The changes will reduce the cost and complete the project with the suitable alternate improvements. The current total contract amount will remain unchanged at $1,158,900 (Original Bid and Change Order Number One). 2