HomeMy WebLinkAbout2007 CON Portillo Concrete - Change Order #1 Misc. Concrete ImprovementsCHANGE ORDER (C/O) C/O Number One
To (Contractor): Portillo Concrete, Inc. CIO Initiation Date: March 12, 2007
Project: Miscellaneous Concrete Improvements Project
Project Specification No.: 06-2
A Change Order is hereby recommended for the lollowingg work in the amount identified in this
document:
DESCRIPTION OF CIIANGE:
This change order will add truncated domes tiles to the proposed pedestrian ramps in order to
meet the latest American with Disabilities Act (ADA) requirement. The truncated domes are
detectable warning surfaces (2'X4') that shall be incorporated to the pedestrian ramps per the
new ADA requirements. See attached contract change request form along with the proposed cost
breakdown dated March 12, 2007. See attached Portillo Concrete's request for contract change
form and the proposed cost breakdown.
COST RECONCILATION:
Costs were reviewed by the City Project Manager and negotiated with the C'ontractor.
Construction Contract Accounting Summary:
The original Contract Amount $131,825.00
Net change by previously authorized Change Orders $ 0.00
The contract Amount prior to this Change Orders $131,825.00
With Change Order Number One the Contract cost is increased by $ 13,488.00
New Contract Amount $145,313.00
Contract Time (unchanged):
Contract Completion Date:
Approval by:
I'tY PROJECT MANAGE
C
CONTRACTOR/PORIILLO CONCRETE,
INC.
/07
DATE
CITY OF NATI AI. 1TY DAT
CC: Construction File
Inspector
30 Working Days
April 9, 2007
tto<i2,d COvL. k.sOt,-"itby
M.$r' le u i u.Y: u•tp
Marto ror't1to
oto-too-riot p.1
Equipment
PORTILLO CONCRETE, INC.
3528 HARRIS ST.
LEMON GROVE, CA. 91945
OFFICE (619) 466-4639
FAX (619) 466-4685
Hours Rate Extension Date
Job Name
Bobcat $20.00 $0.00 Job #
Roller 3-5 ton $30.00 $0.00 gency
10 Wheeler $25.00 $0.00 By
Bobtail Dump Truck $25.00
50.00
2 Ton Lumber Truck $25.00
1 1 Ton Tool Truck 0.5 $15.00
Transfer truck & op $95.00
Water truck $35.00
$0.00
$7.50
$0.00
BackHoe 710 $60.00
$0.00
Roller 5-8 ton $52.00
$0.00
saw & truck $57.00
$0.00
Semi -End Dump $95.00
Skiploader $ 28.00
Tack Rig $ 15.00
Demo Hammer $ 15.00
$0.00
$0.00
$0.00
$0.00
Compressor Package
$ 40.00 $0.00
Materials
Whitecap Industries (Armortile Truncated Dome)
Labor
1 Foreman - Reg
Foreman - O.T.
1 Cement Mason - Reg
Cement Mason - O.T.
1 Laborer - Reg
Laborer - Reg
Laborer - O.T.
Operator - Reg
Operator - Reg
Teamster - Reg
Teamster - O.T.
Flours Rate Extension
1 $71.00 $71.00
$102.00 $0.00
1 $51.00 $51.00
$76.50 $0.00
1 $49.50 $49.50
$49.50 $0.00
$73.00
$69.00
$0.00
$0.00
$69.00 $0.00
$50.50 $0.00
$83.50 $0.00
24 Pedestrian Ramps LA $582.00 per ramp
3/8/2007
National City Misc Conc Impr
2007-01
City of National City
Mario Portl110
Description Of Work:
Add truncated domes per pedestrian ramp
Qty.
1
Unit Price
$310.00
Total Labor Cost
Total Equip. Cost
Total Mat. Cost
Labor Mark-up
Eq/Mat Mark-up
Total Price
Total
Extension
$310.00
$0.00
$0.00
$0.00
$171.50
$7.50
$310.00
$25.73
$47.63
$582.35
$13,488.00
RESOLUTION NO. 2007 — 59
RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF NATIONAL CITY
AUTHORIZING THE CITY ENGINEER TO EXECUTE
CHANGE ORDER NO. 1 WITH PORTILLO CONCRETE, INC.
IN THE AMOUNT OF $13,488 FOR THE MISCELLANEOUS
CONCRETE IMPROVEMENTS PROJECT
WHEREAS, on December 5, 2006, the City adopted Resolution No. 2006-246
approving an agreement with Portillo Concrete, Inc. for miscellaneous concrete improvements,
including curbs, gutters, sidewalks, and pedestrian ramps at various locations within National
City; and
WHEREAS, due to new Americans with Disability Act (ADA) requirements,
truncated dome tiles (detectable warning devices) must be added to the new pedestrian ramps.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby authorizes the City Engineer to execute Change Order No. 1 with Portillo
Concrete, Inc. in the amount of $13,488 for truncated dome tiles for the new pedestrian ramps.
PASSED and ADOPTED this 3rd day of April, 2
Ron Morrison, Mayor
ATTEST:
11
Michel R. Della,C
h
,4,14471
APPROVED AS TO FORM:
George H. Eiser, III
City Attorney
Passed and adopted by the Council of the City of National City, Califomia, on April 3,
2007 by the following vote, to -wit:
Ayes: Councilmembers Morrison, Natividad, Parra, Ungab, Zarate.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
fl VIC rk of the City oo
City nal City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2007-59 of the City of National City, California, passed and adopted
by the Council of said City on April 3, 2007.
City Clerk of the City of National City, California
By:
Deputy
c, aoa • 5�
City of National City, California
COUNCIL AGENDA STATEMENT
MEETING DATE April 3, 2007
AGENDA ITEM NO. 10
)ITEM TITTLE Resolution of the City Council of National City approving Change Order Number One with
Portillo Concrete, Inc. to add the installation of truncated dome tiles (24) to the new pedestrian ramps in
the total amount of $13,488 as part of the Miscellaneous Concrete Improvements Project and authorizing
the City Engineer to execute the Change Order (Funded through CDBG and Gas Tax funds)
PREPARED BY Din Daneshfar DEPARTMENT Engineering EXT. 4387
EXPLANATION
See attached explanation.
J
Environmental Review jN/A
MIS Approval
Financial Statement
See attached statement.
>STAFF RECOMMENDATION
Approved By:'
France DIa r !i tar
Tat- -59f - 6/J4I A / 7
Account No. / - goq- 520-�9
Adopt the Resolution. /'\-(
BOARD / COMMISSION RECOMMEND ON
N/A
ATTACHMENTS ( Listed Below) Resolution No. " ca �!' -
L1. Resolution 2. Change Order Number One along with pertinent attachments
A-200 (Rev. 7/03)
RE: Resolution of the City Council of National City approving Change Order
Number One with Portillo Concrete, Inc. to add the installation of truncated dome
tiles (24) to the new pedestrian ramps in the total amount of $13,488 as part of
the Miscellaneous Concrete Improvements Project and authorizing the City
Engineer to execute the Change Order and (Funded through CDBG and Gas Tax
funds)
On December 5, 2006 a contract was awarded to Portillo Concrete, Inc. to install
miscellaneous concrete improvements including curbs, gutters, sidewalks, and
pedestrian ramps at various locations. The project includes the removal and
replacement of existing curb and gutter, sidewalk, and installation of new
concrete sidewalks, and pedestrian ramps, involving minor pavement repairs, at
various locations in National City.
The purpose of the Change Order is to add truncated dome tiles to the proposed
pedestrian ramps in order to meet the latest American with Disability Act (ADA)
requirement. The truncated dome tiles are detectable warning surfaces (2'X4')
required by the new ADA requirements. The City of National City's modified
Standard Drawing for the pedestrian ramps do not include the truncated domes.
These drawings will be revised and signed by the City Engineer to reflect the
truncated domes in accordance with the new ADA requirements. See attached
contract change request form along with the proposed cost breakdown dated
March 12, 2007.
The total estimated construction cost approved by Resolution No. 2006-246 that
included surveying, construction engineering, material testing, and contingency
items was $158,825.00. This amount included the proposed lowest bid amount
($131,825), approximately 5% ($7,000) for surveying, and approximately 15%
($20,000) for contingencies. The sources of funding for the project are the
Community Development Block Grant and Gas Tax.
1
CHANGE ORDER (C/O) C/O Number One
To (Contractor): Portillo Concrete, Inc. C/O Initiation Date: March 12, 2007
Project: Miscellaneous Concrete Improvements Project
Project Specification No.: 06-2
A Change Order is hereby recommended for the following work in the amount identified in this
document:
DESCRIPTION OF CHANGE:
This change order will add truncated domes tiles to the proposed pedestrian ramps in order to
meet the latest American with Disabilities Act (ADA) requirement. the truncated domes are
detectable warning surfaces (2'X4') that shall he incorporated to the pedestrian ramps per the
new ADA requirements. See attached contract change request form along with the proposed cost
breakdown dated March 12, 2007. See attached Portillo Concrete's request for contract change
form and the proposed cost breakdown.
COST RECONCILATION:
Costs were reviewed by the City Project Manager and negotiated with the Contractor.
Construction Contract Accounting Summary:
The original Contract Amount $131,825.00
Net change by previously authorized Change Orders $ 0.00
The contract Amount prior to this Change Orders $131,825.00
With Change Order Number One the Contract cost is increased by $ 13 488.00
New Contract Amount $145, 313.00
Contract Time (unchanged):
Contract Completion Date:
Approval by:
30 Working Days
April 9, 2007
(:Tl'Y PROJECT MANAGER DATE
apoi(ZIt6— 3-/ V- 67
CONTRACTOR/PORTILLO CONCRETE, DATE
INC.
CITY OFTlAIIONAI. CITY DATE
CC: Construction File
Inspector
rrwr zc ur rTarzo rorczl.co
bco-gbb-vro.
PORTILLO CONCRETE, INC.
3628 HARRIS ST.
LEMON GROVE, CA. 91945
OFFICE (619) 466.4639
FAX (619) 466-4685
# Equipment Hours Rate Extension Date 3/8/2007
Job Name National City Misc Cone Impr
Bobcat $20.00 $0.00 Job # 2007-01
Roller 3-5 ton $30.00 $0.00 gency City of National City
10 Wheeler $25.00 $0.00 By Marto Perrillo
Bobtail Dump Truck $25.00 $0.00
2 Ton Lumber Truck $25.00 $0.00 Description Of Work:
1 1 Ton Tool Truck 0.5 $15.00 $7.50 Add truncated domes per pedestrian ramp
Transfer truck & op $95.00 $0.00
Water truck $35.00 $0.00
BackHoe 710 $60.00 $0.00
Roller 5-8 ton $52.00 $0.00
saw & truck $57.00 $0.00
Semi -End Dump $95.00 $0.00
Skiploader $ 28.00 $0.00
Tack Rig $ 15.00 $0.00
Demo Hammer $ 15.00 $0.00
Compressor Package $ 40.00 $0.00
Materials
Whitecap Industries (Armortile Truncated Dome)
Labor Ilours Rate Extension
1 Foreman - Reg 1 $71.00 $71.00
Foreman - O.T. $102.00 $0.00
1 Cement Mason - Reg 1 $51.00 $51.00
Cement Mason - O.T. $76.50 $0.00
1 Laborer - Reg 1 $49.50 $49.50
Laborer - Reg $49.50 so on
Laborer - O.T. $73.00 $0.00
Operator - Reg $69.00 $0.00
Operator - Reg
$69.00 $0.00
Teamster - Reg
Teamster - O.T.
$50.50 $0.00
$83.50 $0.00
Qty. Unit Price Extension
1 $310.00 $310.00
Total Labor Cost
Total Equip. Cost
Total Mat. Cost
Labor Mark-up
Eq/Mat Mark-up
$0.00
$0.00
$0.00
$171.50
$7.50
$310.00
_ $25.73
$47.63
Total Price $582.35
24 Pedestrian Ramps t $562.00 per ramp Total $13,488.00
RESOLUTION NO. 2007 —
RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF NATIONAL CITY
AUTHORIZING THE CITY ENGINEER TO EXECUTE
CHANGE ORDER NO. 1 WITH PORTILLO CONCRETE, INC.
IN THE AMOUNT OF $13,488 FOR THE MISCELLANEOUS
CONCRETE IMPROVEMENTS PROJECT
WHEREAS, on December 5, 2006, the City adopted Resolution No. 2006-246
approving an agreement with Portillo Concrete, Inc. for miscellaneous concrete improvements,
including curbs, gutters, sidewalks, and pedestrian ramps at various locations within National
City; and
WHEREAS, due to new Americans with Disability Act (ADA) requirements,
truncated dome tiles (detectable warning devices) must be added to the new pedestrian ramps.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby authorizes the City Engineer to execute Change Order No. 1 with Portillo
Concrete, Inc. in the amount of $13,488 for truncated dome tiles for the new pedestrian ramps.
PASSED and ADOPTED this 3rd day of April, 2007.
Ron Morrison, Mayor
ATTEST:
Michael R. Dalla, City Clerk
APPROVED AS TO FORM:
George H. Eiser, III
City Attorney
City of National City
Office of the City Clerk
1243 National City Boulevard, National City, CA 91950-4397
Michael R. Della, CMC - City Clerk
(619) 336-4228 Fax: (619) 336-4229
April 5, 2007
Mr. Mario Portillo
President
Portillo Concrete, Inc.
3528 Harris Street
Lemon Grove, CA 91945
Dear Mr. Portillo,
On April 3, 2007, Resolution No. 2007-59 was passed and adopted by the City
Council of National City, authorizing the execution of Change Order No. 1 to
agreement with Portillo Concrete, Inc. for the miscellaneous concrete
improvements project.
We are enclosing for your records a certified copy of the above Resolution and a
fully executed copy of the change order.
Sincerely,
/J
Michael R. Da a, CMC
City Clerk
Enclosures
cc: Engineering Dept.
40 Recycled Paper