HomeMy WebLinkAbout2007 CON Portillo Concrete - Change Order #1 National City Blvd. Streetscape and Fountain Plaza ImprovementsCHANGE ORDER (C/O) CIO Number One To (Contractor): Portillo Concrete, Inc. C/O Initiation Date: March 12, 2007 Project: National City Blvd Streetscape and 9t1 Fountain Plaza Improvements Project Specification No.: 06-1 A Change Order is hercbv recommended for the following work in the amount identified in this document: DESCRIPTION OF CHANGE: This change order will add the removal and disposal of buried railroad tics and ballast that were discovered under the existing asphalt and concrete pavement section on National ('ity Boulevard in the proposed median area between 2" and 7`1' Streets during the road excavation. The proposal includes the work for a full depth of 12" and replacement and compaction of Class "A" topsoil for the 12". The demolition areas are 300', 25' and 400' long with a width of approximately 11', for a total area of 7,975 square feet. The removal is one foot deep for a total removal of 295 cubic yards. See attached Portillo Concrete's request for contract change dated March 8, 2007 and the proposed cost breakdown. COST RECONCILATION: Costs were reviewed by the City Project Manager and negotiated with the Contractor. Construction Contract Accounting Summary: The original Contract Amount $3,298,308.00 Net change by previously authorized Change Orders $ 0.00 The contract Amount prior to this Change Orders S3,298,308.00 With Change Order Number One the Contract cost is increased by $ 42,419.76 New Contract Amount $ 3, 340,727.76 Contract Time (unchanged): Contract Completion Date: Approval by: DESIGN CONSULTANT/ CTION MANAGER CONTRACTOR/PORTILLO CONCRE'fl . INC. DATE DATE 3/ y/o7 160 Working Days October 15, 2007 DATE CITY OF NATIO CITY DATE CC: Construction Fi e IQft''0 (..... t `(7..) A.16 - --10 — Inspector # Equipment 1 Bobcat Roller 3-5 ton PORTILLO CONCRETE, INC. 3528 HARRIS ST. LEMON GROVE, CA. 91945 OFFICE (619) 466-4639 FAX (619) 466-4685 Hours 8 1 10 Wheeler 8 Bobtail Dump Truck 2 Ton Lumber Truck 1 1 Ton Tool Truck 32 Rate Extension $20.00 $160.00 $30.00 $0.00 $25.00 $200.00 $25.00 $0.00 Date Job Name Job # Agency By 3/8/07 National City Streetscape 2007-04 City of National City Mario Portillo $25.00 $0.00 Description Of Work: $15.00 Transfer truck & op Water truck 1 BackHoe 710 32 Roller 5-8 ton saw & truck 2 Semi -End Dump 16 $480.00 Remove railroad ties and ballast in median. $95.00 $0.00 $35.00 $0.00 $60.00 $1,920.00 $52.00 $0.00 $57.00 $0.00 $95.00 $3.040.00 Skiploader $ 28.00 $0.00 Tack Rig $ 15.00 $0.00 Demo Hammer $ 15.00 $0.00 Compressor Package $ 40.00 $0.00 Materials Dump Fees (Railroad Ties) Dump Fees (Ballast Material) Class "A" Topsoil (Includes Compaction Factor) Labor 1 Foreman - Req Foreman - O.T. Cement Mason - Reg Cement Mason - O.T. 3 Laborer - Reg Laborer - Reg Laborer - O.T. 1 Operator - Reg 1 Operator - Reg 1 Teamster - Reg Teamster - O.T. Hours Rate Extension 32 $71.00 $2.272.00 $102.00 $0.00 $51.00 $0.00 $76.50 $0.00 32 $49.50 $4,752.00 $49.50 $0.00 $73.00 $0.00 32 $69.00 $2,208.00 8 $69.00 $552.00 8 $50.50 $404.00 $83.50 $0.00 Carpenter - Req $56.50 $0.00 Carpenter - O.T. $84.75 $0.00 Qty. 840 4 295 Unit Price Extension In. ft. $5.00 $4,200.00 load $100.00 $400.00 cu. yd. $55.25 $16.298.75 $0.00 Total Labor Cost Total Equip. Cost Total Mat. Cost Labor Mark-up Eq/Mat Mark-up Total Price $10,188.00 $5,800.00 $20,898.75 $1,528.20 $4,004.81 $42,419.76 RESOLUTION NO. 2007 — 60 RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY AUTHORIZING THE CITY ENGINEER TO EXECUTE CHANGE ORDER NO. 1 WITH PORTILLO CONCRETE, INC. IN THE AMOUNT OF $42,419.76 FOR THE REMOVAL AND DISPOSAL OF BURIED RAILROAD TIES AND BALLAST UNDER THE EXISTING PAVEMENT, AND REPLACEMENT OF COMPACTED CLASS "A" TOPSOIL AS PART OF THE NATIONAL CITY BOULEVARD STREETSCAPE AND 9TH STREET FOUNTAIN PLAZA IMPROVEMENTS WHEREAS, on January 9, 2007, the City adopted Resolution No. 2007-4 approving an agreement with Portillo Concrete, Inc. for the National City Boulevard Streetscape and 9th Street Fountain Plaza Improvements; and WHEREAS, during the demolition of the existing asphalt and concrete section for the proposed median on National City Boulevard between 2nd and 7th Street, the contractor encountered buried railroad ties and ballast, which must be removed to continue the project. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of National City hereby authorizes the City Engineer to execute Change Order No. 1 with Portillo Concrete, Inc. in the amount of $42,419.76 for the removal and disposal of buried railroad ties and ballast under the existing pavement, and replacement of compacted Class "A" topsoil as part of the National City Boulevard Streetscape and 9th Street Fountain Plaza Improvements. PASSED and ADOPTED this 3rd day of April, on Morrison, Mayor ATTEST: APPROVED AS TO FORM: George H. Eiser, III City Attorney Passed and adopted by the Council of the City of National City, Califomia, on April 3, 2007 by the following vote, to -wit: Ayes: Councilmembers Morrison, Natividad, Parra, Ungab, Zarate. Nays: None. Absent: None. Abstain: None. AUTHENTICATED BY: RON MORRISON Mayor of the City of National City, California h, City Cle of the Ci of N 'tional City, California By: Deputy I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of RESOLUTION NO. 2007-60 of the City of National City, Califomia, passed and adopted by the Council of said City on April 3, 2007. City Clerk of the City of National City, Califomia By: Deputy c_ CI0R-0\ MEETING DATE April 3, 2007 City of National City, California COUNCIL AGENDA STATEMENT AGENDA ITEM NO. 11 )TEM TITLE Resolution of the City Council of National City approving Change Order Number One with Portillo Concrete, Inc. for the removal and disposal of buried railroad ties and ballast under the existing pavement and replacement of compacted class "A" topsoil in the amount of $42,419.76 as part of the National City Boulevard Streetscape and 9th Street Fountain Plaza Improvements and authorizing the City Engineer to execute the Change Order Funded through State Pilot Smart Growth Incentive Pro ram and Community Development Commission) PREPARED BY Din Dancshlar PEPARTMENT Engineering EXT. 4387 FJCPLANATION See attached explanation. 2 ( Environmental Review _X__ N/A Financial Statement See attached statement. MIS Approval Approved By: t 1 ` -+ Finance Director Account No. ga6T1 STAFF RECOMMENDATION Adopt the Resolution. BOARD / COMMISSION RECOMM NDATION N/A ATTACHMENTS ( Listed Below ) Resolution No. 60 Resolution 2. C'hange Order Number One along with pertinent attachments A-200 (Rev. 7/03) RE: Resolution of the City Council of National City approving Change Order Number One with Portillo Concrete, Inc. for the removal and disposal of buried railroad ties and ballast under the existing pavement and replacement of compacted class "A" topsoil in the amount of $42,419.76 as part of the National City Boulevard Streetscape and 9th Street Fountain Plaza Improvements and authorizing the City Engineer to execute the Change Order (Funded through State Pilot Smart Growth Incentive Program and Community Development Commission) On January 9, 2007 a contract was awarded to Portillo Concrete, Inc. to install landscaped medians with street trees and traffic striping/marking on National City Boulevard between 7th and Division Streets. In addition, the improvements include the sidewalk area rehabilitation of an area on National City Boulevard between 12th and 7th Streets with an installation of a Fountain Plaza Promenade on 9th Street between "A" Avenue and National City Boulevard. On February 26, 2007 the Contractor began the work. During the demolition of the existing asphalt and concrete sections for the proposed median on National City Boulevard between 2'1 and 7th Streets the Contractor encountered series of buried railroad ties and ballast. The ties and ballast were discovered within the depth of 26-inch below the pavement surface. The removal of asphalt and concrete sections were included in the original plans but not the removal of the ties and ballast. The purpose of the change order Number One is to add the removal and disposal of the buried material and replacement of compacted class "A" topsoil into the original contract. Staff has negotiated the cost and schedule with the Contractor. The proposed total cost ($42,419.76) will include the removal, and disposal of the ties and ballast and the replacement of the compacted Class "A" topsoil. The class "A" topsoil material will fill the 26-inch void within the proposed median area for landscaping. The construction duration will remain unchanged. See attached contract change request form along with the proposed cost breakdown dated March 8, 2007. Financial Statement The total estimated construction cost approved by Resolution No. 2007-4 that included surveying, construction engineering, material testing, and contingency items was $3,892,308.50. This amount included the proposed lowest bid amount ($3,298,308.50), approximately 2% ($66,000) for surveying, approximately 23I0 ($66,000) for material testing, approximately 4% ($132,000) for construction engineering, and approximately 10% ($330,000) for contingencies. 1 With the approved total additional construction engineering/surveying costs ($261,650) through approved Amendments One and Two approved the estimated construction cost was increased from $3,298,308.50 to $3,559,958.50. With the approval of the proposed Change Order Number One the total project cost will increase by $42,419.76 from $3,559,958.50 to $3,602,378.26. With the amendments (one & two) and Change Order Number One the remaining amount in the approved budget will be $289,930.24 which will be available for material testing fees ($66,000) and other potential costs ($223, 930.24). 2 Financial Statement The total cost for Change Order Number One is $42,419.76. Funding is available through Community Development Commission (CDC) in the Account No. 900911. The total estimated construction cost approved by Resolution No. 2007- 4 that included surveying, construction engineering, material testing, and contingency items was $3,892,308.50. This amount included the proposed lowest bid amount ($3,298,308.50), approximately 2% ($66,000) for surveying, approximately 2% ($66,000) for material testing, approximately 4% ($132,000) for construction engineering, and approximately 10% ($330,000) for contingencies. CHANGE ORDER (C/O) C/O Number One To (Contractor): Portillo Concrete, Inc. C/O Initiation Date: March 12, 2007 Project: National City Blvd Streetscape and 9th Fountain Plaza Improvements Project Specification No.: 06-1 A Change Order is hereby recommended for the following work in the amount identified in this document: DESCRIPTION OF CHANGE: This change order will add the removal and disposal of buried railroad ties and ballast that were discovered under the existing asphalt and concrete pavement section on National City Boulevard in the proposed median area between 2"d and 7th Streets during the road excavation. The proposal includes the work for a full depth of 12" and replacement and compaction of Class "A" topsoil for the 12". The demolition areas are 300', 25' and 400' long with a width of approximately 1 1', for a total area of 7,975 square feet. The removal is one foot deep for a total removal of 295 cubic yards. See attached Portillo Concrete's request for contract change dated March 8. 2007 and the proposed cost breakdown. COST RECONCILATION: Costs were reviewed by the City Project Manager and negotiated with the Contractor. Construction Contract Accounting Summary: The original Contract Amount Net change by previously authorized Change Orders The contract Amount prior to this Change Orders With Change Order Number One the Contract cost is increased by New Contract Amount Contract Time (unchanged): Contract Completion Date: Approval by: DESIGN CONSULTANT/ UCTION MANAGER r"c i CL CONTRAC'TOR/POR I ILLO CONCRETE, INC. DATE > C.(�.0 DATI-: $3,298,308.00 $ 0.00 $3,298,308.00 S 42.419.76 $3,340,727.76 160 Working Days CI I Y OF NATIONAL CITY DATE E; CC: Construction File Inspector October 15, 2007 • Equipment 1 Bobcat PORTILLO CONCRETE, INC. 3528 HARRIS ST. LEMON GROVE, CA. 91945 OFFICE (619) 466-4639 FAX (619) 466-4685 Hours 8 Rate Extension $20.00 $160.00 Roller 3-5 ton 1 10 Wheeler Bobtail Dump Truck 2 Ton Lumber Truck 1 1 Ton Tool Truck Transfer truck & op $30.00 $0.00 8 $25.00 $200.00 $25.00 $0.00 Date Job Name Job # Agency By 3/8/07 National City Streetscape 2007-04 City of National City Mario Portillo $25.00 $0.00 Description Of Work: 32 $15.00 $480.00 Remove railroad ties and ballast in median. $95.00 $0.00 Water truck 1 BackHoe 710 32 Roller 5-8 ton saw & truck 2 Semi -End Dump 16 Skiploader Tack Rig Demo Hammer Compressor Package Materials Dump Fees (Railroad Ties) Dump Fees (Ballast Material) $35.00 $0.00 $60.00 $1,920.00 $52.00 $0.00 $57.00 $0.00 $95.00 $3,040.00 $ 28.00 $0.00 $ 15.00 $0.00 $ 15.00 $0.00 $ 40.00 $0.00 Class "A" Topsoil (Includes Compaction Factor) Labor Hours 1 Foreman - Reg 32 Foreman - O.T. Cement Mason - Reg Cement Mason - O.T. 3 Laborer - Reg 32 Laborer - Reg Laborer - O. T 1 Operator - Reg 32 1 Operator - Req 8 1 Teamster - Reg 8 Teamster - O.T. Rate Extension $71.00 $2,272.00 $102.00 $0.00 $51.00 $0.00 $76.50 $0.00 $49.50 $4,752.00 $49.50 $0.00 $73.00 $0.00 $69.00 $2,208.00 $69.00 $552.00 $50.50 $404.00 $83.50 $0.00 Carpenter - Reg Carpenter - O.T. $56.50 $0.00 $84 75 $0.00 Qty. 840 4 295 In. ft. load cu. yd. Unit Price Extension $5.00 $4.200.00 $100.00 $400.00 $55.25 $16,298.75 Total Labor Cost Total Equip. Cost Total Mat. Cost Labor Mark-up Eq/Mat Mark-up Total Price $0.00 $10,188.00 $5,800.00 $20,898.75 $1,528.20 $4, 004.81 $42,419.76 RESOLUTION NO. 2007 — RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY AUTHORIZING THE CITY ENGINEER TO EXECUTE CHANGE ORDER NO. 1 WITH PORTILLO CONCRETE, INC. IN THE AMOUNT OF $42,419.76 FOR THE REMOVAL AND DISPOSAL OF BURIED RAILROAD TIES AND BALLAST UNDER THE EXISTING PAVEMENT, AND REPLACEMENT OF COMPACTED CLASS "A" TOPSOIL AS PART OF THE NATIONAL CITY BOULEVARD STREETSCAPE AND 9TH STREET FOUNTAIN PLAZA IMPROVEMENTS WHEREAS, on January 9, 2007, the City adopted Resolution No. 2007-4 approving an agreement with Portillo Concrete, Inc. for the National City Boulevard Streetscape and 9th Street Fountain Plaza Improvements; and WHEREAS, during the demolition of the existing asphalt and concrete section for the proposed median on National City Boulevard between 2nd and 7th Street, the contractor encountered buried railroad ties and ballast, which must be removed to continue the project. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of National City hereby authorizes the City Engineer to execute Change Order No. 1 with Portillo Concrete, Inc. in the amount of $42,419.76 for the removal and disposal of buried railroad ties and ballast under the existing pavement, and replacement of compacted Class "A" topsoil as part of the National City Boulevard Streetscape and 9th Street Fountain Plaza Improvements. PASSED and ADOPTED this 3rd day of April, 2007. Ron Morrison, Mayor ATTEST: Michael R. Dalla, City Clerk APPROVED AS TO FORM: George H. Eiser, III City Attorney City of National City Office of the City Clerk 1243 National City Boulevard, National City, CA 91950-4397 Michael R. Della, CMC - City Clerk (619) 336-4228 Fax: (619) 336-4229 April 5, 2007 Mr. Mario Portillo President Portillo Concrete, Inc. 3528 Harris Street Lemon Grove, CA 91945 Dear Mr. Portillo, On April 3, 2007, Resolution No. 2007-60 was passed and adopted by the City Council of National City, authorizing the execution of Change Order No. 1 to agreement with Portillo Concrete, Inc. for the National City Blvd. Streetscape and 9rn Street Fountain Plaza Improvements. We are enclosing for your records a certified copy of the above Resolution and a fully executed copy of the change order. Michael R. Dalla, CMC City Clerk Enclosures cc: Engineering Dept. ® Recycled Paper