HomeMy WebLinkAbout2007 CON CDC Healey Construction - Change Order #1 Foodland MarketCHANGE ORDER
C/O Number 1
To Healey Construction Co.: C/O Initiation Date: January 8, 2007
Project: Foodland Market
Project Specification No.: 06-04
A Change Order is hereby recommended for the following work in the amount identified in this
document:
DESCRIPTION OF CHANGE:
It is proposed that the existing concrete walkway (230 SF) he removed and replaced located at
the most northern front entrance to Foodland ]\Market.
REASON FOR CHANGE:
This portion of the work was included in the larger anticipated concrete patio eatery arca under
the Alternative Bid item. Due to budget constrains the work was not awarded. Adding this small
section will remove all the deteriorated concrete from the front entrance and enhance the overall
appearance. This work will approximately remove and replace 230 square feet of concrete
pavement.
COST RECONCILIATION:
Costs were reviewed and negotiated to the satisfaction of the City. The work will be
compensated through Capital Project Reserve funds (See attached detailed breakdown).
Construction Contract Accounting Summary :
The original Contract Amount (Base Bid) $ 290, 326.00
Net change by previously authorized Change Orders $ 0.00
The Contract Amount prior to this Change Order $ 290,326.00
With this Change Order request the Contract cost is increased by S 4,021.32
New Contract Amount $ 294, 347.32
Change in Contract Time: 0 Working Days
Contract Completion Date (Unchanged): April 27. 2007
1
Approval by:
TY PROJECT MANEGER
HEALEY CON STRUC
co
COMMISSION
N "I
CITY OVNATIO �j CITY
ENGINEERING ARTMENT
CC: Construction File
Inspector
DAT
Change Order No. 1
/EA/6 7
DATE
-"7
DATE
DATE
1 -r - 07
2
Construction Estimate Page 1
File Name: Foodland Market.Change Order RFI No. 17.est
Qty Craft@Hours Unit Material Labor Equipment Total
RFI No. 17 _..---- -- -- -- - -
City of National City
Owner Addr: Office of City Clerk,
1243 National City Blvd
National City, CA
91950
Replace additional Concrete in front of building.
December 15, 2006
Demo Concrete
1.00 CC@4.000 30.00 266.00 354.00 650.00
Dump Fees
1.00--@.0000 336.00 0.00 0.00 336.00
Rebar
1.00 CC@2.000 186.00 133.00 0.00 319.00
Form
1.00 CC@1.000 -- 198.00 66.60 17.40 282.00
Concrete
1.00 CC@8.000 405.90 532.00 30.00 967.90
Strip Forms & Clean
1.00 CC@2.000 48.00 133.00 30.00 211.00
Patch Asphalt
1.00--@.0000 0.00 0.00 0.00 420.00
65.74 66.60 0.00 132.34
Drain
1.00 CC@1.000
Expantion Joint & Tape
1.00 CC@1.000
56.35 66.60 6.00 128.95
Total Manhours. Material. Labor, and Equipment:
19.0
Total Only (Subcontract) Costs:
1.325.99
1.263.80 437.40 3.027.19
420.00
Subtotal:
3,447.19
Construction Estimate Page 2
File Name: Foodland Market.Change Order RFI No. 17.est
Qty Craft@Hours Unit Material Labor Equipment Total
5.00% Overhead:
1.00% Insurance:
10.00% Profit:
172.36
36.20
365.57
Estimate Total: 4,021.32