HomeMy WebLinkAbout2008 CON Koch Armstrong - Change Order #4 Street Resurfacing Project FY 08-09City of National City
National City Streets Resurfacing Project
Project #08-04
CHANGE ORDER #4
August 11, 2008
Contractor: KOCH-ARMSTRONG
A Change Order is hereby recommended for the following work in the amount identified below:
Description of Change in the Contract
This Change Order will ADD the removal and replacement of 10 I.f. of Type "H" curb ($580) and 35 I.f. of
modified curb and gutter ($1,687.50).
Cost Reconciliation
This change in the contract was reviewed and negotiated by and between the City Representatives and the
Contractor and represents the entire agreement for the work described herein and includes all costs
associated with the work including but not limited to manpower, equipment, labor, fees, taxes, insurance,
bonding, overhead, profit, etc. and there will be no other compensation. This Change Order hereby
incorporates the original contract and all its referenced documents' terms and conditions.
Justification for Change in Contract
These changes are made due to the existing condition of badly damaged H curb and modified curb and gutter
than was not in the original contract that needs replacement to facilitate the overlay program.
Construction Contract Accounting Summary
Original Contract Amount: 5,327,000.00
Net change by previously authorized Change Orders: 21,508.00
Contract amount prior to this Change Order: 5,348,508.00
Amount of this change order: 2,267.50
New contract amount: $ 5,350,775.50
Original contract time (calendar days): 90
Previously approved additional working days: 0
Additional working days for this change order: 0
Total contract time (working days): 90
Reviewed by:
/Of -2 ' "t:
sneer ~� Dat
Manag
er • 9 Project Date
Agreed to and Accepted by:
CC: Construction File
Koch -Armstrong
CALL.FO NIA, -
NATIO : 0
acitty •
INCORPOAATED
OFFICE OF THE CITY CLERK
1243 National City Blvd., National City, CA 91950
619-336-4228 phone • 619-336-4229 fax
KOCH-ARMSTRONG GENERAL ENGINEERING
Change Order #4
Tess in Engineering Forwarded
Copy of the Change Order to the Vendor