HomeMy WebLinkAbout2008 CON Koch Armstrong - Change Order #7 Street Resurfacing Project FY 08-09City of National City National City Streets Resurfacing Project Project #08-04 CHANGE ORDER #7 August 12, 2008 Contractor: KOCH-ARMSTRONG A Change Order is hereby recommended for the following work in the amount identified below: Description of Change in the Contract This Change Order will ADD the application of a root systemic herbicide (i.e. Roundup) per manufacturers specifications on all plant growth existing in all streets where work is remaining to be done. Cost Reconciliation This change in the contract was reviewed and negotiated by and between the City Representatives and the Contractor and represents the entire agreement for the work described herein and includes all costs associated with the work including but not limited to manpower, equipment, labor, fees, taxes, insurance, bonding, overhead, profit, etc. and there will be no other compensation. This Change Order hereby incorporates the original contract and all its referenced documents' terms and conditions. Justification for Change in Contract These changes are made at the request and direction of the City to systemically erradicate the weeds growing in the streets were work is to be done to prevent future damage. Construction Contract Accounting Summary Original Contract Amount: 5,327,000.00 Net change by previously authorized Change Orders: 35,815.50 Contract amount prior to this Change Order: 5,362,815.50 Amount of this change order: 4,615.00 New contract amount: $ 5,367,430.50 Original contract time (calendar days): 90 Previously approved additional working days: 0 Additional working days for this change order: 0 Total contract time (working days): 90 Reviewed by: Ciiy Engineer «r Principal Civil Engineer Date V-2-Z)I Da Agreed to and Accepted by: och-Ar ..trong CC: Construction File Koch -Armstrong Date Project Manager Date _r — KOCH-ARMSTRONG GENERAL ENGINEERING, INC. P.O. BOX 1190, LAKESIDE, CA 92040-0906 TEL: (619) 561-2005 FAX: (619) 561-0317 LICENSE 194819-A CHANGE ORDER PROPOSAL #13 HERBICIDE SPRAYING PAGE 1 OF 1 (REVISION at 8-12-08) TO: NATIONAL CITY STREET RESURFACING FY 06-07 ATTN: BYRON WADE 1243 NATIONAL CITY BLVD. TEL: (619) 336-4380 NATIONAL CITY , CA. 91950 FAX: (619) 336 4397 DATE: 8/15/2008 We propose to furnish all labor, material, and equipment necessary to perform the following Items of work, subject to terms and conditions stated. This quotation expires 30 days from the date above and is good for work completed within one Year of date above unless otherwise noted. JOB LOCATION CONTRACT STREETS EXCLUDING # 5, 24, 98, 104, 105 & 106, IDENTIFIED "NATIONAL CITY STREET RESURFACING PROJECT.", CHANGE ORDER PROPOSAL #13- HERBICIDE SPRAYING ITEM DESCRIPTION APPROX. QUANTITY UNIT UNIT PRICE TOTAL 1 APPLY PRE AND POST EMERGENT HERBICIDE APPLICATION TO REMAINING STREETS (APPROXIMATEL) 1 LS CAL WEST WEED 1 LS 2250.00 KOCH-ARMSTRONG'S MARK-UP 15% PCT 337.50 BOND COST 0.015 PCT 38.81 SUB -TOTAL 1 LS 2626.31 TOTAL- CHANGE ORDER PROPOSAL 1 LS 2630.00 TERMS: 1 INCLUDES: ONE MOVE IN, PREVAILING WAGES, BOND COST 2 EXCLUDES:ANY WORK/LABOR/ MATERIALS OR ITEM NOT SPECIFICALLY STATED IN QUOTE, SPRAYING STREETS THAT HAVE BEEN CRACKSEALED AT BEGINNING OF START DATE _ I 1 CONDITIONS: 1.Does not include permits. bonds, any form of engineenng(staking, testing. inspection, etc.), base under concrete. redwood headers, striping. traffic control, or utility adjustment unless otherwise specified. 2. Monthly Progress Payments and Full Payment upon completion. Accounts are delinquent after 30 days, and they are subject to the maximum finance charge allowable by law. 3. Work to be done in accordance with plans, specifications, and quantities identified above. Koch -Armstrong General Engineering, Inc. shall be notified in writing prior to any proposed changes. 4.Subgrade to be taken from +1' 10' to balance and at or below optimum moisture before Koch -Armstrong General Engineering, Inc. begins work unless otherwise specified. 5. Any unusual conditions of subsoil encountered, such as buried slabs, underground piping, trash deposits, etc. shall be deemed cause for additional charges. 6. Required California Preliminary Lien information (California Civil Code Section 3007/3098) shall be provided to Koch -Armstrong General Engineering, Inc. before work begins. 7. Subject to Credit Approval and verification of California Preliminary Lien information. 8. Class 2 material if included is 314" recycled Class 2 per Callrans Standard Specification Section 26 unless otherwise noted. Acceptance: Please sign and return one copy -this quotation constitutes the sole and only agreement. Any prior agreements, negotiations. etc., not set forth herein are of no force or effect. Firm: NATIONAL CITY STREET RESURFACING FY 06-07 By: By: KOCH-ARMSTRONG GENERAL ENGINEERING, INC. 8/15/08 Date FRANK HERRERA KOCH-ARMSTRONG GENERAL ENGINEERING, INC. P.O. BOX 1190, LAKESIDE, CA 92040-0906 TEL: (619) 561-2005 FAX: (619) 561-0317 LICENSE 194819-A CHANGE ORDER PROPOSAL #24 HERBICIDE SPRAYING PCC , 1 e PAGE 1 OF 1 (REVISION #2. ADD OPTION *1: 8-15-08) TO: NATIONAL CITY STREET RESURFACING FY 06-07 ATTN: BYRON WADE 1243 NATIONAL CITY BLVD. TEL: (619) 336.4380 NATIONAL CITY , CA. 91950 FAX: (619) 336 4397 DATE: 9/15/2008 We propose to fumish all labor, material, and equipment necessary to perform the following items of work, subject to terms and conditions stated. This quotation expires 30 days from the date above and is good for work completed within one year of date above unless otherwise noted. JOB LOCATION APPROXIMATELY 50 - 60 STREETS IDENTIFIED "NATIONAL CITY STREET RESURFACING PROJECT.", CHANGE ORDER PROPOSAL #24- HERBICIDE SPRAYING AGAINST PCC. ITEM DESCRIPTION APPROX. QUANTITY UNIT UNIT PRICE TOTAL 1 APPLY PRE AND POST EMERGENT HERBICIDE APPLICATION TO STREETS, AGAINST CURBS 1 LS AND GUTTERS(APPROXIMATELY 50-60), THAT HAVE NOT BEEN SPRAYED. CAL WEST WEED 1 LS 1700.00 KOCH-ARMSTRONG'S MARK-UP 15% PCT 255.00 BOND COST 0.015 1 PCT 29.33 SUB -TOTAL 1 LS 1984.33 TOTAL- CHANGE ORDER PROPOSAL 1 LS 1985.00 i TERMS: 1 INCLUDES: ONE MOVE IN, PREVAILING WAGES, BOND COST 2 EXCLUDES:ANY WORK/LABOR/ MATERIALS OR ITEM NOT SPECIFICALLY STATED IN QUOTE, 3 QUOTE BASED ON SPRAYING THOSE STREETS THAT WERE NOT SPRAYED DURING MOVE #1. THIOSE STREETS HAD NOT YET BEEN CRACKSEALED 1 1 CONDITIONS: 1.Does not include permits, bonds, any form of engineering(staking, testing. inspection, etc.). base under concrete, redwood headers. striping, traffic control, or utility adjustment unless otherwise specified. 2. Monthly Progress Payments and Full Payment upon completion. Accounts are delinquent after 30 days, and they are subject to the maximum finance charge allowable by law. 3. Work to be done in accordance with plans, specifications, and quantities identified above. Koch -Armstrong General Engineering, Inc. shall be notified in writing prior to any proposed changes. 4 Subgrade to be taken from .1- .10' to balance and at or below optimum moisture before Koch -Armstrong General Engineenng, Inc. begins work unless otherwise specified. 5 Any unusual conditions of subsoil encountered, such as buried slabs, underground piping, trash deposits. etc. shall be deemed cause for additional charges. 6. Required California Preliminary Lien information (California Civil Code Section 3097/3098) shall be provided to Koch -Armstrong General Engineering. Inc before work begins. 7. Subject to Credit Approval and verification of California Preliminary Lien information. 8. Class 2 material 1 included is 341- recycled Class 2 per Caltrans Standard Specification Section 26 unless otherwise noted. Acceptance: By: Please sign and return one copy -this quotation constitutes the sole and only agreement. Any prior agreements, negotiations, etc., not set forth herein are of no force or effect. NATIONAL CITY STREET RESURFACING FY 06-07 By: KOCH-ARMSTRONG GENERAL ENGINEERING, INC. 9/15/08 Date FRANK HERRERA + CALIFORNIA NATILCFV --- INCORPORATED OFFICE OF THE CITY CLERK 1243 National City Blvd., National City, CA 91950 619-336-4228 phone • 619-336-4229 fax KOCH-ARMSTRONG GENERAL ENGINEERING Change Order #7 Tess in Engineering Forwarded Copy of the Change Order to the Vendor