HomeMy WebLinkAbout2008 CON City of Chula Vista - 1st Amendment Construction Management ServicesAMENDMENT NUMBER ONE
TO THE AGREEMENT FOR PROFESSIONAL SERVICES
BETWEEN THE CITY OF NATIONAL CITY
AND CITY OF CIIULA VISTA
This Amendment Number One to the Agreement for Professional Services
Between the City of National City and City of Chula Vista ("Amendment") is entered into
this loth day of September 2008, by and between the City of National City, a municipal
corporation ("CITY"), and the City of Chula Vista (the "CONTRACTOR").
RECITALS
A. The CITY and the CONTRACTOR entered into an agreement on June 3,
2008, entitled Agreement for Professional Services between the City of
National City and City of Chula Vista ("Original Agreement"), wherein the
CONTRACTOR agreed to provide construction engineering, management.
and inspection services for the C'ITY'S major active projects.
B. The Original Agreement provides that CITY may increase the Scope of
Services to be performed by CONTRACTOR.
C. The CITY now seeks to increase the Scope of Services by increasing the
number of staff/staff hours to provide additional construction engineering,
management, and inspection services for the National City major active
projects, and CONTRACTOR seeks to perform this increased work.
1). The CITY and CONTRACTOR have negotiated and agreed upon the
additional compensation associated with this increased work.
AGREEMENT
NOW, THEREFORE, the parties hereto agree as follows:
1. This Amendment specifies additional work to be performed by
CONTRACTOR for CITY at specified hourly rates, which is detailed in
Exhibit "A", attached hereto and incorporated herein by reference.
This Amendment authorizes the payment of an amount not to exceed
S275,000 for this additional work, increasing the not to exceed amount in
Section h of the Original Agreement from TWO -HUNDRED THOUSAND
DOLLARS (S200.000) to FOUR -HUNDRED SEVENTY-FIVE
THOUSAND DOLLARS (5475.000) for all services, including the
additional services that are the subject of this Amendment.
3. The parties agree that with the foregoing exception, each and every term
and provision of the Original Agreement shall remain in full force and
effect.
IN WITNESS WHEREOF, the parties hereto have executed this Amendment on
the date and year first above written.
CITY OF NATIONAL CITY CITY OF CHULA VISTA
l i ,
By: j
Ron Morrison, Mayor avid Garc a, City Manager
APPROVED AS TO FORM:
/-D
George H. Eiser, III
City Attorney
-2
By:
R.A. I (op'kiryS City Engineer
Amendment No One to Agreement
Between National City and Chula Vista
City of National City
124 3 National City i3lvd
National City, (:A 01050
.^tin ri Nlar yang Liahaki
CI1Y OF
CHUTA VISTA
I)Il'AI(IMINI Of INCINrU 1N(,
EXHIBIT "A"
September c), 200ti
1 Ile No N(' 0SO4
PRO.11':('1': PROPOSALS FOR NATIONAI. (•CI'1', 1'AVENIEN I RI':SIiRFA(•IN(:, I.II3,ILAM'
REMODEL, ANi) O'FlIF:It iLF.I.I':"ANT I'ILO,FI':(' I'ti
SUBJECT': AN11':N[MIEN 'I. NIINIKI':I& I I'() AGILI':F':N1ENi'
Based upon the anticipated work schedule tilr the reniainder of Phase 2 cc)nsuuction (60 workin:;
days), construction duration 1i)t Phase 3 construction (40 working days), construction duration for
IAnal y Remodel project (30 wotknu!, days), and anticipated staffing rcyuuc nlcnts ti)r the liutldinl;
DC1110lltiorl Protect as well as oilier relevant pioiects, out proposal is the foIIoc1 rift;
.1 AS1:
.1.1 1'1.I
I'F.RSONNI2.1,
I IOI)1LS
I1OIJIL1 1'
ILA ATV
I Ol Al.
(•OS.I
Inspection Set tees-
( Phase 2)
inspectuol Set c tees
Si Public W'otks
Inspect();
('Irlus Melendez
5,10
SI21 00
S65,14010
Associate -
(Phase ?)
hispecuon Set% ices
I:n} Inecl
Associate Civil ~
Ben Juan
540
tit 21 01)
SO 140 00
(Phase ;
( )
Lnrrncct
Pan lck tlloneda
) 10
S 1 2 i 001;69,120
--
00
—
Inspection Set flees
Sento' Public
(Phase 3)
\Narks Inspeetol
-
Mike Schedule
-
- -- -- -
60
-- -
ti 121 .00
-
5, l 1,>OO OO
---
('oristluchutt
Management
(Phase. 2 and I'h.t,c 3),
i'roicct Management
(iitiilding 1)emolltton
Sr Civil inn ineet
Jelt Moneda
400
tit 10 tit►
Sio,000 00
Project) -
Project ManagentCiit
Sr Budding,
Projects
(. 'lot don I )ay
120
1 ?O 01)
$ I >.1 2(1 00
Super lsOI
PRO I'Oti:11. 'I O'1 .\ 1. $114,480.0O
11 should be noted that the hours slims n ahove are based on the anticipated schedule from
August 18, 20118 to construction completion.
l he pioposal hrcakdol vn shot\ n above is based on the anticipated consntiction schedule lilt the
rein:tinder fit. Phase 2, the consttuction duration shalln In tits spectlit ;Iron, 1(1 1'11asc .; Ilt:;hlan(1
Avcinic, and the anticipated construction schedule for the 1.thtaty lLenlodcl and l3riil(Iirt Demolition
!'f, III A11N14 / ( 1114 1 \'Isl-\ ( AlIf()I(NI•\'II'liO 26S1 / ,LI'll h'tI ,II!I
CITY OF NATIONAL CITY 2 - September 9, 2008
projects. If the project requires project management/inspection services beyond the work hours
assumed for this estimate or if services are needed beyond the estimate shown above, staff costs will
increase accordingly. Invoicing shall be based on 0.10 hour increments.
Should the projects require City of Chula Vista services heyond the scope outlined above, we will
proceed on a time and material basis based on our agreement with the City of National City and at
the direction of the City of National City's City Engineer.
It should be noted that our agreement with the City of National City authorizes an aggregate
payment amount not to exceed $200,000.00 for engineering, construction management, and
project management services. The authorization of this scope of work for $314,480.00, in
addition to the previous invoices for June and July 2008 totaling $83,417.50, would increase
the aggregate total payment amount to $397,897.50 for all aforementioned projects.
Total Contract
In addition to the above scope of work, it was mutually agreed that an additional $50,000 in Building
Project Manager (Gordon Day) services would be needed for Park Phases 1, 2, and 3, the Police
Department and Former Library Remodel projects. Additional work has also been assigned to Mr.
Day. We conservatively estimate that the total cost of services to be provided by Mr. Day may
approach $75,000.
Therefore, we recommend that the contract's "not -to -exceed" authorization be increased to $475,000
at this time. This would result in an amendment amount of $275,000. An exhibit is attached
showing staff costs per project.
Should you have any questions, please do not hesitate to contact me.
RICHARD A. HOPKINS, P.E.
CITY OF CHULA VISTA DIRECTOR OF ENG VEERING
c: lracscma Quilantan, Assistant Director of Engineering
Mcrceditas LeClair, Engineering
Jeff Moncda, Senior Civil Engineer
Gordon Day, Building Project Manager
M \General Scrvices\Dcsign\National Cuty\Proposalk\Phase 2 & Phase 3 & Lihrary I'roposal Letter Revised Sept 2008 DOC
CITY OF CHULA VISTA
NATIONAL CITY EXHIBIT
Project
Staff Costs to Date (7/31/08)
Anticipated Staff Costs
Total Project Cost
Phase 1 Slurry Seal (07-03)
S18,560
$7,640
$26,200
Phase 2 Resurfacing (08-04)
$74,560
$205,000
$279,560
Phase 3 Highland Avenue (08-08)
$2,775
$69,640
$72,415
Miscellaneous Bldgs and Parks
$8,575
$76,000
$84,575
Building Demolition Project (08-02)
$1,050
$11,200
$12,250
Total Project Staff Cost $475,000
Approved Amount Per
Current Agreement S200,000
Requested Amendment
Amount Per New
Agreement $275,000
275,000
Project
Original Scope Staff Costs
Increase in Scope of Work
Staff Costs
Total Project Cost
Phase 1 Slurry Seal (07-03)
$10,000
$16,200
$26,200
Phase 2 Resurfacing (08-04)
$145,000
$134,560
$279,560
Phase 3 Highland Avenue (08-08) New Project
$0
$72,415
$72,415
Miscellaneous Bldgs and Parks
$45,000
$39,575
$84,575
Building Demolition Project (08-02) New Project
$0
$12,250
$12,250
Total $200,000 $275,000 $475,000
RESOLUTION NO. 2008 — 187
RESOLUTION OF THE CITY COUNCIL OF
THE CITY OF NATIONAL CITY AUTHORIZING
THE MAYOR TO EXECUTE AMENDMENT NO. ONE
TO AGREEMENT WITH THE CITY OF CHULA VISTA
THE AMOUNT OF $275,000 TO PROVIDE ADDITIONAL
CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES
TO THE NATIONAL CITY ENGINEERING DEPARTMENT
FOR MAJOR NATIONAL CITY PROJECTS
WHEREAS, on June 3, 2008, the City Council adopted Resolution No. 2008-96,
approving an agreement with the City of Chula Vista in the amount of $200,000 to provide
construction, engineering, management, and inspection services to the Engineering Department
for major National City projects; and
WHEREAS, because most of the Engineering Department's major projects will
be under construction at the same time, additional construction, engineering, management, and
inspection services are required to meet the deadline for each project.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby authorizes the Mayor to execute Amendment No. 1 to Agreement with the
City of Chula Vista to provide construction, engineering, management, and inspection services
to the National City Engineering Department for major National City projects.
PASSED and ADOPTED this 16th day of September, 2008.
on Morrison, Mayor
ATTEST:
ilt
4
M hael R. Dalla, y Clerk
APPROVED AS TO FORM.
George H. Eiser, III
City Attorney
Passed and adopted by the Council of the City of National City, California, on
September 16, 2008 by the following vote, to -wit:
Ayes: Councilmembers Morrison, Parra, Ungab, Zarate.
Nays: None.
Absent: Councilmember Natividad.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
i4 ii
City Ierk of the City ql National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2008-187 of the City of National City, California, passed and
adopted by the Council of said City on September 16, 2008.
City Clerk of the City of National City, California
By:
Deputy
City of National City
Office of the City Clerk
1243 National City Boulevard, National City, CA 91950-4397
Michael R. Dalla, CMC - City Clerk
(619) 336-4228 Fax: (619) 336-4229
September 18, 2008
Mr. Richard Hopkins
Director of Engineering
Department of Engineering
City of Chula Vista
276 Fourth Avenue
Chula Vista, CA 91910
Dear Mr. Hopkins
On September 16th, 2008, Resolution No. 2008-187 was passed and adopted by
the City Council of the City of National City, authorizing execution of Amendment
No. 1 to Agreement with the City of Chula Vista.
We are enclosing for your records a certified copy of the above Resolution and a
fully executed original amendment.
Sincerely,
Michael R. DaIIa, CMC
City Clerk
Enclosures
cc: Engineering Department
® I'JpLr