HomeMy WebLinkAbout2009 CON Harris & Associates - Addendum #1 As Needed Engineering ServicesADDENDUM NUMBER ONE
TO THE AGREEMENT BY AND BETWEEN
THE CITY OF NATIONAL CITY
AND
HARRIS & ASSOCIATES
This Addendum Number One to the Agreement for "As -Needed" Civil
Engineering/Traffic Engineering Services by and between the City of National City and
Harris & Associates is entered into this 7th day of April, 2009 by and between the City of
National City, a municipal corporation (the "CITY"), and Harris & Associates, a
Corporation (the "CONSULTANT").
RECITALS
A. The CITY and the CONSULTANT entered into an Agreement ("Original
Agreement") on January 6, 2009, by Resolution 2009-3, wherein the
CONSULTANT agreed to provide "as -needed" Civil Engineering/Traffic
Engineering Services for the City's Capital Improvement Projects.
B. The Original Agreement provides that the CITY may request Civil
Engineering/Traffic Engineering Services from the CONTRACTOR for a
period of 1 year from the date of execution of the Original Agreement,
such that the total cost of all work completed shall not exceed $100,000.
C. The CITY now requests Civil Engineering/Traffic Engineering Services
from the CONTRACTOR to assist staff in completion of the City's
Comprehensive Transportation Plan document, and the CONTRACTOR
seeks to perform these services.
D. The CITY and CONTRACTOR have negotiated and agreed upon the
scope of work and compensation associated with these services.
AGREEMENT
NOW, THEREFORE, the parties hereto agree as follows:
1. This Addendum specifies work to be performed by the CONTRACTOR for
the CITY at specified hourly rates, which are detailed in Exhibits "A" and
"B", attached hereto and incorporated herein by reference.
2. This Addendum authorizes the payment of an amount not to exceed
$39,990 for Civil Engineering/Traffic Engineering Services to assist staff in
completion of the City's Comprehensive Transportation Plan document.
3. The parties agree that each and every term and provision of the Original
Agreement shall remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have executed this Addendum on
the date and year first above written.
CITY OF NATIONAL CITY HARRIS & AS
By:
Ron Morrison
Mayor
By:
APPROVED AS TO FORM:
George H. Eiser, III
City Attorney
Gerges, P.E.
Design Services Manager
/
er Saunders, P.E.
onal Manager — San Diego
EXHIBIT A gm
March 13, 2009
Mr. Steve Manganiello
City of National City, Engineering
1243 National City Boulevard.
National City, CA 91950
Harris & Associates
Program Ntanagees
Construction Managers
Civil Engineers
Subject: Comprehensive Transportation Plan (CTP) for the City of National City.
Dear Steve,
Harris is pleased to submit this proposal for professional engineering services to assist and provide support
services to the City of National City in the preparation of a comprehensive transportation plan.
BACKGROUND
Back in 1972, the City utilized a federally funded program named TOPICS (Transportation Operations Program
to Increase Capacity and Safety), which is no longer available, to implement a Citywide Traffic Study conducted
by Gruen Associates. The purpose of the study was to identify the traffic improvements required to improve
efficiency for the five-year Capital Improvement Program budget and to balance the share of improvement costs
with the supplemental Federal funds and the Gas Tax funds.
PROJECT UNDERSTANDING
The scope of this project is to provide professional traffic engineering services to assist and support City staff in
preparing a detailed Comprehensive Transportation Plan (CTP) document that will act as a blueprint to address
traffic deficiencies improve safety and operations, and plan for redevelopment in the City.
SCOPE OF SERVICES
1. Provide a literature review on public agency transportation master plans.
2. Provide comments / recommendations on the current CTP outline.
3. Provide an existing conditions inventory of traffic signage, striping, curb markings and geometric
deficiencies; efforts to be focused on Circulation Element streets (i.e. arterials and collectors).
4. Provide site -specific field surveys and technical analysis as needed.
5. Provide recommendations on traffic / pedestrian safety and operational improvements based on
existing deficiencies.
6. Provide recommendations for future Capital Improvement Program (CIP) projects to mitigate
existing deficiencies and plan for redevelopment.
7. Prepare tables, figures and graphics to be included in the CTP report; City Engineering will
draft the document.
l larris & Associates 750 B Street, Suite 1800, San Diego, CA 92101 619.236.1778 Fax 619.236.1179
City of National City
Steve Manganiello
March 13, 2009
Page 2 of 2
8. Prepare a Synchro base model to include Circulation Element streets, all signalized intersections
and key unsignalized intersections; input link and node geometries, basic traffic control (i.e.
signal or stop/yield control, no signal phasing / timing), and available turning movement
volumes.
9. Attend six (6) progress meetings with City staff (1-hour each).
10. Attend one (1) Planning Commission meeting and 1 City Council meeting to support City staff
(2-hours each); City Engineering will present the CTP.
Our proposed effort is limited to the number of hours indicated in the attached Estimated Hourly Effort. The total
number of hours per task is an estimate only based on the information available.
SCHEDULE
The schedule for final submittal of the report, tables and exhibits to City staff is June 15, 2009. Final submittal
would be pending receipt of final comments by City.
CITY RESPONSIBILITIES/EXCLUSIONS FROM SCOPE
• Provide all available existing data and information relevant to the proposed project
• Provide all pertinent Specific Plans, the General Plan and the five (5) year Strategic Plan and Goals
• Provide As-Builts of street improvements, parcel maps and assessors parcel maps as needed to use for the
support services for the required tasks
• Traffic volume data collection is not included in these services
FEE
Harris & Associates proposes to provide the above services for the total "not to exceed" fee of $39,990. Fees
would be invoiced monthly based on the actual hours of work completed. Our services would be accomplished
per our existing agreement with the City with all terms and conditions stated therein.
Thank you for the continued opportunity to be of service to the City of National City. Should you have any
questions, or need additional information regarding this proposal, please do not hesitate to contact me at (619)
236-1778 x 352 or Ali Shahzad at x 414.
Sincerely,
Harris & Associates
Ehab S. Gerges, PE
Design Manager/Associate
Cc: Ali Shahzad, PE
Javier Saunders, PE
2
HARRIS ASSOCIATES
3/12/2009
Harris & Associates
Program Managers
Construction Managers
Civil Engineers
Task/Subtask
Estimated Hourly Effort CITY OF NATIONAL CITY
Comprehensive Transportation Plan Outline
QA!QC
Provide a literature review on public agency transportation master plans.
S200
Harris & Associates
PM PE
$19(1
2
16
$150
2 Provide comments / recommendations on the current CEP outline. 2
16
TECH
$90
Provide an existing conditions inventory of traffic signage, striping. curb markings and
geometric deficiencies; efforts to be focused on Circulation Element streets (i.e. arterials
3 and collectors).
4
8
4 Provide site -specific field surveys and technical analysis as needed.
Provide recommendations on traffic / pedestrian safety and operational improvements
5 based on existing deficiencies.
6
7
8
Provide recommendations for future Capital Improvement Program (CIP) projects to
mitigate existing deficiencies and plan for redevelopment.
12
45
12
Subtotals
S3,440
$3,440
$6,010
$3,660
20
$3,800
Prepare tables, figures and graphics to be included in the C IP report; City Engineering
will draft the document.
18
4
4
Prepare a Synchro base model to include Circulation Element streets, all signalized
intersections and key unsignalized intersections; input link and node geometries, basic
traffic control (i.e. signal or stop/yield control, no signal phasing i timing), and available
turning movement volumes.
9
10
Attend 6 progress meetings with City staff (1-hour each). 6
Attend 1 Planning Commission meeting and 1 City Council meeting to support City staff
(2-hours each); City Engineering will present the CTP.
4
Subtotal Hours = 14
28
12
4
134
36
14
53,420
$4.600
$6.580
14
107
$3,480
$1,560
269
Subtotal (5) - $2,800
$25,460
S2,100
$9,630
S39,990
National City Traffic Eng.fee 03-12-09.xls 3/12/2009
RESOLUTION NO. 2009 — 69
RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF NATIONAL CITY
AUTHORIZING THE MAYOR TO EXECUTE
ADDENDUM ONE TO AGREEMENT WITH
HARRIS & ASSOCIATES IN THE NOT -TO -EXCEED
AMOUNT OF $39,990 FOR "AS NEEDED"
CIVIL ENGINEERING/TRAFFIC ENGINEERING
SERVICES TO ASSIST IN THE COMPLETION
OF THE NATIONAL CITY COMPREHENSIVE
TRANSPORTATION PLAN
WHEREAS, on January 6, 2009, the City Council adopted Resolution No 2009-3,
approving an agreement with Harris & Associations in the not to exceed amount of $100,000 for
"as needed" civil engineering/traffic engineering services for capital improvement projects; and
WHEREAS, the Engineering Department requires additional profession
engineering support services to assist staff in completing the National City Comprehensive
Transportation Plan (the "Plan") documents; and
WHEREAS, Addendum No. One to Agreement with Harris & Associates in the
not -to -exceed amount of $39,990 will provide "as needed" civil engineering/traffic engineering
services to assist staff in the completion of Plan documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
National City that the Mayor is hereby authorized to execute Addendum No. One to Agreement
with Harris & Associates in the not -to -exceed amount of $39,990 to provide "as needed" civil
engineering/traffic engineering services to assist staff in the completion of the National City
Comprehensive Transportation Plan documents. Said Addendum No. One to Agreement is on
file in the office of the City Clerk.
PASSED and ADOPTED this 7th day of April, 20
on Morrison, Mayor
ATTEST:
!/ 4 1%
Michael R. Dalla, Cit Clerk
APPROVED AS TO FORM:
George H. Eiser, III
City Attorney
Passed and adopted by the Council of the City of National City, California, on April 7,
2009 by the following vote, to -wit:
Ayes: Councilmembers Morrison, Parra, Sotelo-Solis, Van Deventer, Zarate.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
City Clerk of the City of Ifational City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2009-69 of the City of National City, California, passed and adopted
by the Council of said City on April 7, 2009.
City Clerk of the City of National City, California
By:
Deputy
City of National City, California
COUNCIL AGENDA STATEMENT
vito. QIEETING DATE April 7, 2009
AGENDA ITEM NO.
12
%ITEM TITLE
Resolution of the City Council of the City of National City approving an Agreement Addendum 1 and
authorizing the Mayor to execute addendum with Harris & Associates for "As -Needed" Civil
Engineering/Traffic Engineering Services to assist City Engineering in the completion of the City's
Comprehensive Transportation Plan document for the "not to exceed" amount of $39,990 (funded through
Capital Improvement Project sources)
PREPARED BY Stephen Manganiello DEPARTMENT Engineering EXT. 4382
EXPLANATION
On January 6, 2009, the City entered into an agreement with Harris & Associates to provide "as -needed"
Engineering Services authorized by Resolution No. 2009-3 (see attached).
This addendum provides authority for engineering services for a specific project (Comprehensive
Transportation Plan).
Funds were transferred from various Capital Improvement Projects to the Engineering Department's
Maintenance and Operations budget where funds area available for this work.
See attached detailed explanation.
i
Environmental Review X N/A
MIS Approval7_,
Financial Statement Approved Bk
Funds are available in account 001-421-000-299-0000 in the amount of $14 15
and 001-421-000-213-0000 in the amount of $25,875.
F nance Director
Account No
STAFF RECOMMEND4TIC)N
A. • pt h - Resolution
jyv
BOAR
N/A
/ COMMISSIO
ECOMMEDATION
ATTACHMENTS (Listed Below)
1. Explanation & Request for Services
2. Resolution
3. Agreement Addendum (2 originals)
Resolution No.
A-200 (Rev. 7/03)
City of National City
Office of the City Clerk
1243 National City Boulevard, National City, CA 91950-4397
Michael R. Della, CMC - City Clerk
(619) 336-4228 Fax: (619) 336-4229
April 14, 2009
Mr. Javier Saunders
Regional Manager
Harris & Associates
750 B Street, Suite 1800
San Diego, CA 92101
Dear Mr. Saunders,
On April 7th, 2009, Resolution No. 2009-69 was passed and adopted by the City
Council of the City of National City, authorizing execution of Addendum No. 1 to
Agreement with Harris & Associates.
We are enclosing for your records a certified copy of the above Resolution and a
fully executed original addendum.
Michael R. Dalla, CMC
City Clerk
Enclosures
cc: Engineering Department
® Rccvcled Paper