HomeMy WebLinkAbout2009 CON L.B. Civil Construction - Change Order #4 Bay Marina Drive Widening ProjectCity of National City
Bay Marina Drive Widening
Specification 08-13
CHANGE ORDER #4
May 13, 2009
Contractor: L.B. Civil Construction
A Change Order is hereby recommended for the following work in the amount identified below:
Description of Change in the Contract
This change in the contract adds the costs of additional work and materials required by utilities for the under
the railroad casings at all locations. See Attachment "A" for details.
Cost Reconciliation
This change in the contract was reviewed and negotiated by and between the City Representatives and the
Contractor and represents the entire agreement for the work described herein and includes all costs
associated with the work including but not limited to manpower, equipment, labor, fees, taxes, insurance,
bonding, overhead, profit, etc. and represents all the work and parts necessary for a complete installation as
described and there will be no other compensation. This Change Order hereby incorporates the original
contract and all its referenced documents' terms and conditions.
Justification for Change in Contract
See Attachment "A".
Construction Contract Accounting Summary
Original Contract amount:
Net change by previously authorized Change Orders:
Contract amount prior to this Change Order:
Amount of this Change Order:
New Contract amount:
Original Contract time (calendar days):
Previously approved additional working days:
Additional working days for this Change Order:
Total Contract time (working days):
(see Weekly Statement of Contract Time for completion date)
Reviewed by:
riricipai Civil Engineer
Agreed to and Accepted by:
00'
ate
.5/8 o%
L.B. Civil Construction Dat
cc: Contractor, Construction File, Project Manager, City Clerk
66
1
10
77
1,060,500.30
5,840.59
1,066,340.89
17,468.34
1,083,809.23
Recommended for approval by:
Recommended for approval by:
Approved by:
City
D9'
er Date
4-se,44 6 /ye y
City of National City
Bay Marina Drive Widening
Specification 08-13
ATTACHMENT "A" Change Order #4
This change in the contract will add the additional costs of the installation of the utility line casings for under
railroad installations as required by MTS and SDG&E. The plans and requirements for the casings under the
railroads changed significantly from bid time from SDG&E's basic design to the final design that was delivered
after bid were accepted. There are 2 extra conduits, more spacers, larger and smaller casings and AT&T must
be in their own casing separate from SDG&E. Additionally, all casings must be filled with slurry. The costs
described below are itemized for reference purposes only. The lump sum price for this change order includes
all costs associated with the work including but not limited to manpower, equipment, labor, fees, taxes,
insurance, bonding, overhead, profit, etc. and represents all the work and parts necessary for a complete
installation as described herein and per the latest SDG&E plans and there will be no other compensation
whether it is itemized below or not.
No Item Units # Units Price/Units Costs
1 Additional 4" conduit LF 165 1.03 169.95
2 Additional 5" conduit LF 165 1.20 198.00
3 Additional 4" sweeps EA 28 14.68 411.04
4 Additional 5" sweeps EA 12 19.58 234.96
5 Credit 4" conduit, now sweeps LF 81 (1.03) (83.43)
6 Credit 5" conduit, now sweeps LF 36 (1.20) (43.20)
7 Additional spacers EA 24 145.00 3,480.00
8 Additional slurry, 50-50 mix SY 27 81.78 2,208.06
9 Additional cost for 28" casing LF 165 66.76 11,015.40
10 Credit for 12" casing LF 165 (26.18) (4,319.70)
11 Pump Surcharge EA 3 250.00 750.00
12 Labor: Pipe Layer HR 3 35.61 106.83
13 Labor: Lead Man HR 3 41.61 124.83
14,252.74
Sub Mark-up @ 15% 2,137.91
subtotal 16,390.65
Prime Mark-up @ 5% 819.53
subtotal 17,210.18
Bond @ 1.5% 258.15
TOTAL COST 17,468.34
JUSTIFICATION:
In order to meet the deadline of June 1, 2009 for completion of the improvements on Bay Marina Drive, in time
for the Hotel grand opening, the plans and specifications were put out to bid with SDG&E's best estimate of
what would be required for the under railroad crossings. SDG&E's final design whichwas received after the
bids where in, are significantly different than the orginal design, (as described above). These requirements
meet final design needs for the utility companies and cannot be changed or adjusted downward. These
changes will complete the undergrounding phase for all utilites for Bay Marina Drive, Harrison, 23rd and
Cleveland.
RESOLUTION NO. 2009 — 129
RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF NATIONAL CITY
RATIFYING CHANGE ORDER NO. 4 WITH
L.B. CIVIL CONSTRUCTION IN THE NOT -TO -EXCEED
AMOUNT OF $17,468.34 TO PROVIDE CONSTRUCTION
CHANGES FOR THE FINAL DESIGN PLANS FOR
SDG&E AND AT&T UNDERGROUNDING FOR
THE BAY MARINA DRIVE WIDENING PROJECT
WHEREAS, on February 17, 2009, the City Council adopted Resolution No.
2009-25, approving a contract in the amount of $1,060,500.30 with L.B. Civil Construction, Inc.,
for construction improvements associated with the Bay Marina Drive Widening Project; and
WHEREAS, on April 29, 2009, Change Order No. 1 was approved in the amount
of $3,303.09 to address the stripping necessary to change 23rd Street from a one-way street to
a two-way street to provide access to businesses in the area when Harrison Avenue is closed to
through traffic; and
WHEREAS, Change Order No. 2 provided for the slurry seal of casings installed
under railroad crossings to accomplish final designs for SDG&E at one location, but was voided
and is now included in Change Order No. 4, which includes all locations; and
WHEREAS, Change Order No. 3 in the amount of $2,537.50 dated May 5, 2009,
provided for the installation of the future waterline tie-in under the sidewalk at Harrison adjacent
to Bay Marina Drive, which will save the cost of removing and replacing a new sidewalk for the
Streetscape phase of the work in the future; and
WHEREAS, Change Order No. 4 in the amount of $17,468.34, provides for the
slurry seal of casings installed under the railroad crossings; and
WHEREAS, pursuant to the Disposition and Development Agreement between
the Community Development Commission of the City Of National City and Marina Gateway
Development Company, LLC., and Sycuan Tribal Development Corporation, the City of National
City is obligated to complete the Bay Marina Project by June 1, 2009, therefore it was necessary
to authorize Change Order No. 4 prior to council approval.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby ratifies Change Order No. 4 to the Agreement with L.B. Construction, Inc.,
in the amount of $17,468.34 for the slurry seal of casings installed under the railroad crossings
for the Bay Marina Drive Widening Project.
ATTEST:
4
PASSED and ADOPTED this 2nd day of June,
on Morrison, Mayor
APPROVED AS TO FORM:
/.
Midhael R. Dalla, C1ty Clerk George H. Eiser, III, City Attorney
Passed and adopted by the Council of the City of National City, California, on June 2,
2009 by the following vote, to -wit:
Ayes: Councilmembers Parra, Sotelo-Solis, Van Deventer, Zarate.
Nays: None.
Absent: Councilmember Morrison.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
21.r:46/11
City erk of the City of National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2009-129 of the City of National City, California, passed and adopted
by the Council of said City on June 2, 2009.
City Clerk of the City of National City, California
By:
Deputy
City of National City, California
COUNCIL AGENDA STATEMENT
`'01PMEETING DATE June 2, 2009
AGENDA ITEM NO.
7
ITEM TITLE Resolution of the City of National City Council ratifying Change Order #4 to the contract with
L.B. Civil Construction in the not to exceed amount of $17,468.34 to provide construction changes for the
final design plans of SDG & E and AT&T undergrounding for Bay Marina Drive Project. (Funded by Tax
Increment Fund)
PREPARED BY Barby Tipton DEPARTMENT Engineering EXT. 4583
EXPLANATION
See attached explanation
Environmental Review X N/A
Financial Statement
MIS Approval
Approved By
Funds are available in expenditure account 511-409-500-
598-3842
Finance Director
Account No
STAFF RECOMMENDATION
Adopt the Resolution.
BOARD / COMMISSION RECOMMN 'ATM
N/A
ATTACHMENTS (Listed Below) Resolution No.
1. Resolution
2. Change Order #4
lb
A-200 (Rev. 7/03)
ALIFORNI,It
INCORPORATL+'Q
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
Michael R. Dalla, CMC - City Clerk
619-336-4228 phone • 619-336-4229 fax
L.B. Civil Construction
Resolution No. 2009-129
Change Order #4
Bay Marina Drive Widening Project
Judy Hernandez (Engineering)
Forwarded Copy of Change Order to Contractor